Volumn 39, Issue 5, 2012, Pages 890-901

An effective shuffled frog-leaping algorithm for resource-constrained project scheduling problem

Author keywords

Combined local search; Design of experiment; Resource based crossover; Resource constrained project scheduling; Shuffled frog leaping algorithm; Speed up evaluation

Indexed keywords

LOCAL SEARCH; RESOURCE CONSTRAINED PROJECT SCHEDULING; RESOURCE-BASED CROSSOVER; SHUFFLED FROG-LEAPING ALGORITHMS; SPEED-UPS;

EID: 80052261681     PISSN: 03050548     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.cor.2011.07.010     Document Type: Article
Times cited : (151)

References (49)
  • 2
    • 11644286761 scopus 로고    scopus 로고
    • Scheduling medical research experiments: An application of project scheduling methods
    • University Kiel, Germany
    • Hartmann S. Scheduling medical research experiments: an application of project scheduling methods. Technical Report, University Kiel, Germany; 1997.
    • (1997) Technical Report
    • Hartmann, S.1
  • 3
    • 33947217417 scopus 로고    scopus 로고
    • Software project management with GAs
    • DOI 10.1016/j.ins.2006.12.020, PII S0020025507000175
    • E. Alba, and J.F. Chicano Software project management with GAs Information Science 177 10 2007 2380 2401 (Pubitemid 46435498)
    • (2007) Information Sciences , vol.177 , Issue.11 , pp. 2380-2401
    • Alba, E.1    Francisco Chicano, J.2
  • 6
    • 0019342681 scopus 로고
    • Scheduling projects subject to resource constraints: Classification and complexity
    • J. Blazewicz, J.K. Lenstra, and K. Rinnoy Scheduling projects subject to resource constraints: classification and complexity Discrete Applied Mathematics 5 1 1983 11 24
    • (1983) Discrete Applied Mathematics , vol.5 , Issue.1 , pp. 11-24
    • Blazewicz, J.1    Lenstra, J.K.2    Rinnoy, K.3
  • 7
    • 0030121479 scopus 로고    scopus 로고
    • Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation
    • R. Kolisch Serial and parallel resource-constrained project scheduling methods revisited: theory and computation European Journal of Operational Research 90 2 1996 320 333 (Pubitemid 126652217)
    • (1996) European Journal of Operational Research , vol.90 , Issue.2 , pp. 320-333
    • Kolisch, R.1
  • 9
    • 0016498438 scopus 로고
    • A comparison of heuristic and optimum solutions in resource-constrained project scheduling
    • E.W. Davis, and J.H. Patterson A comparison of heuristic and optimum solutions in resource-constrained project scheduling Management Science 21 7 1975 944 955
    • (1975) Management Science , vol.21 , Issue.7 , pp. 944-955
    • Davis, E.W.1    Patterson, J.H.2
  • 11
    • 0030231487 scopus 로고    scopus 로고
    • Efficient priority rules for the resource-constrained project scheduling problem
    • DOI 10.1016/0272-6963(95)00032-1
    • R. Kolisch Efficient priority rules for the resource-constrained project scheduling problem Journal of Operations Management 14 3 1996 179 192 (Pubitemid 126365433)
    • (1996) Journal of Operations Management , vol.14 , Issue.3 , pp. 179-192
    • Kolisch, R.1
  • 13
    • 0043114396 scopus 로고
    • A note on serial and parallel heuristics for resource-constrained project scheduling
    • D.F. Cooper A note on serial and parallel heuristics for resource-constrained project scheduling Foundations of Control Engineering 2 4 1977 131 133
    • (1977) Foundations of Control Engineering , vol.2 , Issue.4 , pp. 131-133
    • Cooper, D.F.1
  • 14
    • 0030718178 scopus 로고    scopus 로고
    • An investigation into the relationship of heuristic performance with network-resource characteristics
    • P.R. Thomas, and S. Salhi An investigation into the relationship of heuristic performance with network-resource characteristics Journal of the Operational Research Society 48 1 1997 34 43 (Pubitemid 127602674)
    • (1997) Journal of the Operational Research Society , vol.48 , Issue.1 , pp. 34-43
    • Thomas, P.R.1    Salhi, S.2
  • 15
    • 0026376478 scopus 로고
    • Scheduling of project networks by job assignment
    • A. Drexl Scheduling of project networks by job assignment Management Science 37 1991 1590 1602
    • (1991) Management Science , vol.37 , pp. 1590-1602
    • Drexl, A.1
  • 16
    • 0032188522 scopus 로고    scopus 로고
    • A competitive genetic algorithm for resource-constrained project scheduling
    • S. Hartmann A competitive genetic algorithm for resource-constrained project scheduling Naval Research Logistics 45 6 1998 733 750 (Pubitemid 128587349)
    • (1998) Naval Research Logistics , vol.45 , Issue.7 , pp. 733-750
    • Hartmann, S.1
  • 17
    • 0042287689 scopus 로고    scopus 로고
    • A Robust Genetic Algorithm for Resource Allocation in Project Scheduling
    • DOI 10.1023/A:1010949931021
    • J. Alcaraz, and C. Maroto A robust genetic algorithm for resource allocation in project scheduling Annals of Operations Research 102 1 2001 83 109 (Pubitemid 33634388)
    • (2001) Annals of Operations Research , vol.102 , Issue.1-4 , pp. 83-109
    • Alcaraz, J.1    Maroto, C.2
  • 18
    • 0036684673 scopus 로고    scopus 로고
    • A self-adapting genetic algorithm for project scheduling under resource constraints
    • DOI 10.1002/nav.10029
    • S. Hartmann A self-adapting genetic algorithm for project scheduling under resource constraints Naval Research Logistics 49 5 2002 433 448 (Pubitemid 34878877)
    • (2002) Naval Research Logistics , vol.49 , Issue.5 , pp. 433-448
    • Hartmann, S.1
  • 19
    • 0030124780 scopus 로고    scopus 로고
    • A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes
    • F.F. Boctor A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes European Journal of Operational Research 90 2 1996 349 361 (Pubitemid 126652219)
    • (1996) European Journal of Operational Research , vol.90 , Issue.2 , pp. 349-361
    • Boctor, F.F.1
  • 20
    • 0031188915 scopus 로고    scopus 로고
    • A simulated annealing algorithm for resource constrained project scheduling problems
    • J.H. Cho, and Y.D. Kim A simulated annealing algorithm for resource constrained project scheduling problems Journal of the Operational Research Society 48 6 1997 736 744
    • (1997) Journal of the Operational Research Society , vol.48 , Issue.6 , pp. 736-744
    • Cho, J.H.1    Kim, Y.D.2
  • 21
    • 0037508562 scopus 로고    scopus 로고
    • A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version
    • K. Bouleimen, and H. Lecocq A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version European Journal of Operational Research 149 2 2003 268 281
    • (2003) European Journal of Operational Research , vol.149 , Issue.2 , pp. 268-281
    • Bouleimen, K.1    Lecocq, H.2
  • 22
    • 0034634797 scopus 로고    scopus 로고
    • Project scheduling with time-varying resource constraints
    • DOI 10.1080/00207540050176094
    • R. Klein Project scheduling with time-varying resource constraints International Journal of Production Research 38 15 2000 3937 3952 (Pubitemid 35401939)
    • (2000) International Journal of Production Research , vol.38 , Issue.16 , pp. 3937-3952
    • Klein, R.1
  • 23
    • 0038522575 scopus 로고    scopus 로고
    • Insertion techniques for static and dynamic resource-constrained project scheduling
    • C. Artigues, P. Michelon, and S. Reusser Insertion techniques for static and dynamic resource-constrained project scheduling European Journal of Operational Research 149 2 2003 249 267
    • (2003) European Journal of Operational Research , vol.149 , Issue.2 , pp. 249-267
    • Artigues, C.1    Michelon, P.2    Reusser, S.3
  • 24
    • 36849084169 scopus 로고    scopus 로고
    • Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times
    • DOI 10.1016/j.ejor.2006.06.069, PII S0377221706008344
    • M. Mika, G. Waligóra, and J. Weglarz Tabu search for multi- mode resource-constrained project scheduling with schedule-dependent setup time European Journal of Operational Research 187 3 2008 1238 1250 (Pubitemid 350236634)
    • (2008) European Journal of Operational Research , vol.187 , Issue.3 , pp. 1238-1250
    • Mika, M.1    Waligora, G.2    Weglarz, J.3
  • 25
    • 13244273704 scopus 로고    scopus 로고
    • Particle swarm optimization-based schemes for resource-constrained project scheduling
    • DOI 10.1016/j.autcon.2004.08.006, PII S0926580504001128, International Conference for Construction Information Technology
    • H. Zhang, X. Li, and H. Li Particle swarm optimization-based schemes for resource-constrained project scheduling Automation in Construction 14 3 2005 393 404 (Pubitemid 40183430)
    • (2005) Automation in Construction , vol.14 , Issue.3 , pp. 393-404
    • Zhang, H.1    Li, X.2    Li, H.3    Huang, F.4
  • 26
    • 36749094527 scopus 로고    scopus 로고
    • A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems
    • DOI 10.1016/j.amc.2007.04.096, PII S009630030700553X
    • B. Jarboui, N. Damak, and P. Siarry A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems Applied Mathematics Computation 195 1 2008 299 308 (Pubitemid 350213083)
    • (2008) Applied Mathematics and Computation , vol.195 , Issue.1 , pp. 299-308
    • Jarboui, B.1    Damak, N.2    Siarry, P.3    Rebai, A.4
  • 27
    • 33244474874 scopus 로고    scopus 로고
    • Shuffled frog-leaping algorithm: A memetic meta-heuristic for discrete optimization
    • DOI 10.1080/03052150500384759, PII R65340053330467
    • M. Eusuff, K. Lansey, and F. Pasha Shuffled frog-leaping algorithm: a memetic meta-heuristic for discrete optimization Engineering Optimization 38 2 2006 129 154 (Pubitemid 43279596)
    • (2006) Engineering Optimization , vol.38 , Issue.2 , pp. 129-154
    • Eusuff, M.1    Lansey, K.2    Pasha, F.3
  • 28
    • 0038363680 scopus 로고    scopus 로고
    • Optimization of water distribution network design using the shuffled frog leaping algorithm
    • DOI 10.1061/(ASCE)0733-9496(2003)129:3(210)
    • M. Eusuff, and K. Lansey Optimization of water distribution network design using the shuffled frog leaping algorithm Journal of Water Resources Planning and Management 129 3 2003 210 225 (Pubitemid 36562716)
    • (2003) Journal of Water Resources Planning and Management , vol.129 , Issue.3 , pp. 210-225
    • Eusuff, M.M.1    Lansey, K.E.2
  • 29
    • 35348847056 scopus 로고    scopus 로고
    • A hybrid multi-objective shuffled frog-leaping algorithm for a mixed-model assembly line sequencing problem
    • DOI 10.1016/j.cie.2007.06.007, PII S0360835207000976
    • A. Rahimi-Vahed, and A.H. Mirzaei A hybrid multi-objective shuffled frog-leaping algorithm for a mixed-model assembly line sequencing problem Computers and Industrial Engineering 53 4 2007 642 666 (Pubitemid 47588649)
    • (2007) Computers and Industrial Engineering , vol.53 , Issue.4 , pp. 642-666
    • Rahimi-Vahed, A.1    Mirzaei, A.H.2
  • 30
    • 37249011258 scopus 로고    scopus 로고
    • Solving a bi-criteria permutation flow-shop problem using shuffled frog-leaping algorithm
    • DOI 10.1007/s00500-007-0210-y
    • A. Rahimi-Vahed, and A.H. Mirzaei Solving a bi-criteria permutation flow-shop problem using shuffled frog-leaping algorithm Soft Computing 12 5 2008 435 452 (Pubitemid 350269058)
    • (2008) Soft Computing , vol.12 , Issue.5 , pp. 435-452
    • Rahimi-Vahed, A.1    Mirzaei, A.H.2
  • 31
    • 63449087667 scopus 로고    scopus 로고
    • A novel hybrid multi-objective shuffled frog-leaping algorithm for a bi-criteria permutation flow shop scheduling problem
    • A. Rahimi-Vahed, M. Dangchi, H. Rafiei, and E. Salimi A novel hybrid multi-objective shuffled frog-leaping algorithm for a bi-criteria permutation flow shop scheduling problem International Journal of Advanced Manufacturing Technology 41 10 2009 1227 1239
    • (2009) International Journal of Advanced Manufacturing Technology , vol.41 , Issue.10 , pp. 1227-1239
    • Rahimi-Vahed, A.1    Dangchi, M.2    Rafiei, H.3    Salimi, E.4
  • 32
    • 60849131719 scopus 로고    scopus 로고
    • Application of the shuffled frog leaping algorithm for the optimization of a general large-scale water supply system
    • G. Chung, and K.E. Lansey Application of the shuffled frog leaping algorithm for the optimization of a general large-scale water supply system Water Resource Management 23 4 2009 797 823
    • (2009) Water Resource Management , vol.23 , Issue.4 , pp. 797-823
    • Chung, G.1    Lansey, K.E.2
  • 33
    • 0002030301 scopus 로고    scopus 로고
    • Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification, computational, analysis
    • J. Weglarz, Kluwer Press Berlin
    • R. Kolisch, and S. Hartmann Heuristic algorithms for solving the resource-constrained project scheduling problem: classification, computational, analysis J. Weglarz, Project scheduling: recent models, algorithms and applications 1999 Kluwer Press Berlin 147 178
    • (1999) Project Scheduling: Recent Models, Algorithms and Applications , pp. 147-178
    • Kolisch, R.1    Hartmann, S.2
  • 34
    • 33845274958 scopus 로고
    • Strength and adaptability of problem space based neighborhoods for resource-constrained scheduling
    • V.J. Leon, and B. Ramamoorthy Strength and adaptability of problem space based neighborhoods for resource-constrained scheduling OR Spectrum 17 23 1995 173 182
    • (1995) OR Spectrum , vol.17 , Issue.23 , pp. 173-182
    • Leon, V.J.1    Ramamoorthy, B.2
  • 35
    • 38549091692 scopus 로고    scopus 로고
    • A decomposition-based genetic algorithm for the resource-constrained project-scheduling problem
    • DOI 10.1287/opre.1060.0358
    • D. Debels, and M. Vanhoucke A decomposition-based genetic algorithm for the resource-constrained project scheduling problem Operations Research 55 3 2007 457 469 (Pubitemid 351159503)
    • (2007) Operations Research , vol.55 , Issue.3 , pp. 457-469
    • Debels, D.1    Vanhoucke, M.2
  • 36
    • 0026822242 scopus 로고
    • An iterative scheduling technique for resource constrained project scheduling
    • K.Y. Li, and R.J. Willis An iterative scheduling technique for resource constrained project scheduling European Journal of Operational Research 56 3 1992 370 379
    • (1992) European Journal of Operational Research , vol.56 , Issue.3 , pp. 370-379
    • Li, K.Y.1    Willis, R.J.2
  • 37
    • 0030788844 scopus 로고    scopus 로고
    • PSPLIB - A project scheduling problem library
    • PII S0377221796001701
    • R. Kolisch, and A. Sprecher PSPLIB - a project scheduling problem library European Journal of Operational Research 96 1 1997 205 216 (Pubitemid 127415922)
    • (1997) European Journal of Operational Research , vol.96 , Issue.1 , pp. 205-216
    • Kolisch, R.1    Sprecher, A.2
  • 38
    • 0018011301 scopus 로고
    • Multiple resource-constrained scheduling using branch and bound
    • J.P. Stinson, E.W. Davis, and B.M. Khumawala Multiple resource-constrained scheduling using branch and bound IIE Transactions 10 3 1978 23 40
    • (1978) IIE Transactions , vol.10 , Issue.3 , pp. 23-40
    • Stinson, J.P.1    Davis, E.W.2    Khumawala, B.M.3
  • 40
    • 44849140428 scopus 로고    scopus 로고
    • A random key based genetic algorithm for the resource constrained project scheduling problem
    • J.J. Mendes, J.F. Goncalves, and M.G.C. Resende A random key based genetic algorithm for the resource constrained project scheduling problem Computers and Operations Research 36 1 2009 92 109
    • (2009) Computers and Operations Research , vol.36 , Issue.1 , pp. 92-109
    • Mendes, J.J.1    Goncalves, J.F.2    Resende, M.G.C.3
  • 41
    • 25444456205 scopus 로고    scopus 로고
    • A hybrid scatter search/electromagnetism meta-heuristic for project scheduling
    • DOI 10.1016/j.ejor.2004.08.020, PII S0377221704005594, Feature Cluster on Scatter Search Methods for Optimization
    • D. Debels, B. Reyck, R. De, Leus, and M. Vanhoucke A hybrid scatter-search/electromagnetism meta-heuristic for the resource-constrained project scheduling problem European Journal of Operational Research 169 3 2006 638 653 (Pubitemid 41375712)
    • (2006) European Journal of Operational Research , vol.169 , Issue.2 , pp. 638-653
    • Debels, D.1    De Reyck, B.2    Leus, R.3    Vanhoucke, M.4
  • 42
    • 34648837872 scopus 로고    scopus 로고
    • A hybrid genetic algorithm for the resource-constrained project scheduling problem
    • DOI 10.1016/j.ejor.2006.12.033, PII S0377221707000616
    • V. Valls, F. Ballestin, and S. Quintanilla A hybrid genetic algorithm for the resource-constrained project scheduling problem European Journal of Operational Research 185 2 2008 495 508 (Pubitemid 47454671)
    • (2008) European Journal of Operational Research , vol.185 , Issue.2 , pp. 495-508
    • Valls, V.1    Ballestin, F.2    Quintanilla, S.3
  • 44
    • 84888782064 scopus 로고    scopus 로고
    • Formulation and tabu search algorithm for the resource constrained project scheduling problem (RCPSP)
    • C.C. Ribeiro, P. Hansen, Kluwer Press Boston
    • K. Nonobe, and T. Ibaraki Formulation and tabu search algorithm for the resource constrained project scheduling problem (RCPSP) C.C. Ribeiro, P. Hansen, Essays and surveys in meta-heuristics 2002 Kluwer Press Boston 557 588
    • (2002) Essays and Surveys in Meta-heuristics , pp. 557-588
    • Nonobe, K.1    Ibaraki, T.2
  • 45
    • 24944581849 scopus 로고    scopus 로고
    • Comparative analysis of meta-heuristics for the resource constrained project scheduling problem
    • Department of Civil Engineering, Instituto Superior Tecnico
    • Coelho J, Tavares L. Comparative analysis of meta-heuristics for the resource constrained project scheduling problem. Technical Report, Department of Civil Engineering, Instituto Superior Tecnico; 2003.
    • (2003) Technical Report
    • Coelho, J.1    Tavares, L.2
  • 46
    • 0000103290 scopus 로고    scopus 로고
    • Case-based reasoning and improved adaptive search for project scheduling
    • A. Schirmer Case-based reasoning and improved adaptive search for project scheduling Naval Research Logistics 47 3 2000 201 222
    • (2000) Naval Research Logistics , vol.47 , Issue.3 , pp. 201-222
    • Schirmer, A.1
  • 47
    • 0001896880 scopus 로고    scopus 로고
    • Adaptive search for solving hard project scheduling problems
    • R. Kolisch, and A. Drexl Adaptive search for solving hard project scheduling problems Naval Research Logistics 43 1 1996 23 40 (Pubitemid 126568742)
    • (1996) Naval Research Logistics , vol.43 , Issue.1 , pp. 23-40
    • Kolisch, R.1    Drexl, A.2
  • 48
    • 78049444992 scopus 로고    scopus 로고
    • A neurogenetic approach for the resource-constrained project scheduling problem
    • A. Agarwal, S. Colak, and S. Erenguc A neurogenetic approach for the resource-constrained project scheduling problem Computer and Operations Research 38 1 2011 44 50
    • (2011) Computer and Operations Research , vol.38 , Issue.1 , pp. 44-50
    • Agarwal, A.1    Colak, S.2    Erenguc, S.3
  • 49
    • 73149125765 scopus 로고    scopus 로고
    • An efficient hybrid algorithm for resource-constrained project scheduling
    • W. Chen, Y.J. Shi, H.F. Teng, X.P. Lan, and L.C. Hu An efficient hybrid algorithm for resource-constrained project scheduling Information Sciences 180 5 2010 1031 1039
    • (2010) Information Sciences , vol.180 , Issue.5 , pp. 1031-1039
    • Chen, W.1    Shi, Y.J.2    Teng, H.F.3    Lan, X.P.4    Hu, L.C.5


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.