Resource-constrained project scheduling problem: A hybrid neural approach
-
Weglarz J, Jozefowska J, editors
-
Colak S, Agarwal A, Erenguc SS. Resource-constrained project scheduling problem: a hybrid neural approach. In: Weglarz J, Jozefowska J, editors. Perspectives in modern project scheduling. 2006. p. 297318.
-
(2006)
Perspectives in Modern Project Scheduling
, pp. 297-318
-
-
Colak, S.1
Agarwal, A.2
Erenguc, S.S.3
-
3
-
-
0026822242
-
An iterative scheduling technique for resource-constrained project scheduling
-
K. Li, and R. Willis An iterative scheduling technique for resource-constrained project scheduling European Journal of Operational Research 56 1992 370 379
-
(1992)
European Journal of Operational Research
, vol.56
, pp. 370-379
-
-
Li, K.1
Willis, R.2
-
7
-
-
0029393209
-
A survey on the resource-constrained project scheduling problem
-
L. Ozdamar, and G. Ulusoy A survey on the resource-constrained project scheduling problem IIE Transactions 27 1995 574 586
-
(1995)
IIE Transactions
, vol.27
, pp. 574-586
-
-
Ozdamar, L.1
Ulusoy, G.2
-
9
-
-
0032736579
-
Resource-constrained project scheduling: Notation, classification, models, and methods
-
P. Brucker, A. Drexl, R. Mohring, K. Neumann, and E. Pesch Resource-constrained project scheduling: notation, classification, models, and methods European Journal of Operational Research 112 1 1999 3 41
-
(1999)
European Journal of Operational Research
, vol.112
, Issue.1
, pp. 3-41
-
-
Brucker, P.1
Drexl, A.2
Mohring, R.3
Neumann, K.4
Pesch, E.5
-
10
-
-
0034559432
-
Experimental evaluation of stateof-the-art heuristics for the resource-constrained project scheduling problem
-
S. Hartmann, and R. Kolisch Experimental evaluation of stateof-the-art heuristics for the resource-constrained project scheduling problem European Journal of Operational Research 127 2000 394 407
-
(2000)
European Journal of Operational Research
, vol.127
, pp. 394-407
-
-
Hartmann, S.1
Kolisch, R.2
-
11
-
-
0000801563
-
An integrated survey of deterministic project scheduling
-
R. Kolisch, and R. Padman An integrated survey of deterministic project scheduling OMEGA 29 2001 249 272
-
(2001)
OMEGA
, vol.29
, pp. 249-272
-
-
Kolisch, R.1
Padman, R.2
-
12
-
-
33845270624
-
Experimental investigation of heuristics for resource-constrained project scheduling: An update
-
R. Kolisch, and S. Hartmann Experimental investigation of heuristics for resource-constrained project scheduling: an update European Journal of Operational Research 174 1 2006 23 37
-
(2006)
European Journal of Operational Research
, vol.174
, Issue.1
, pp. 23-37
-
-
Kolisch, R.1
Hartmann, S.2
-
13
-
-
0014574409
-
Multiproject scheduling with limited resources: A zero-one programming approach
-
A.A.B. Pritsker, L.J. Watters, and P.M. Wolfe Multiproject scheduling with limited resources: a zero-one programming approach Management Science 16 1969 93 107
-
(1969)
Management Science
, vol.16
, pp. 93-107
-
-
Pritsker, A.A.B.1
Watters, L.J.2
Wolfe, P.M.3
-
14
-
-
0016028677
-
A horizon-varying, zero-one approach to project scheduling
-
J.H. Patterson, and W.D. Huber A horizon-varying, zero-one approach to project scheduling Management Science 20 1974 990 998
-
(1974)
Management Science
, vol.20
, pp. 990-998
-
-
Patterson, J.H.1
Huber, W.D.2
-
15
-
-
0017268482
-
Scheduling a project under multiple resource constraints: A zero-one programming approach
-
J.H. Patterson, and G.W. Roth Scheduling a project under multiple resource constraints: a zero-one programming approach AIIE Transactions 8 1976 449 455
-
(1976)
AIIE Transactions
, vol.8
, pp. 449-455
-
-
Patterson, J.H.1
Roth, G.W.2
-
16
-
-
0000813734
-
An algorithm for optimal project scheduling under multiple resource constraints
-
E.W. Davis, and G.E. Heidorn An algorithm for optimal project scheduling under multiple resource constraints Management Science 17 1971 803 816
-
(1971)
Management Science
, vol.17
, pp. 803-816
-
-
Davis, E.W.1
Heidorn, G.E.2
-
17
-
-
0017997005
-
An efficient integer programming algorithm with network cuts for solving resource constrained scheduling problems
-
F.B. Talbot, and J.H. Patterson An efficient integer programming algorithm with network cuts for solving resource constrained scheduling problems Management Science 24 11 1978 1163 1174
-
(1978)
Management Science
, vol.24
, Issue.11
, pp. 1163-1174
-
-
Talbot, F.B.1
Patterson, J.H.2
-
19
-
-
0002907360
-
A branch-and-bound procedure for the multiple resource-constrained project scheduling problems
-
E. Demeulemeester, and W. Herroelen A branch-and-bound procedure for the multiple resource-constrained project scheduling problems Management Science 38 12 1992 1803 1818
-
(1992)
Management Science
, vol.38
, Issue.12
, pp. 1803-1818
-
-
Demeulemeester, E.1
Herroelen, W.2
-
20
-
-
0031272722
-
New benchmark results for the resource-constrained project scheduling problem
-
E. Demeulemeester, and W. Herroelen New benchmark results for the resource-constrained project scheduling problem Management Science 43 11 1997 1485 1492 (Pubitemid 127606206)
-
(1997)
Management Science
, vol.43
, Issue.11
, pp. 1485-1492
-
-
Demeulemeester, E.L.1
Herroelen, W.S.2
-
21
-
-
0032096810
-
A branch & bound algorithm for the resource-constrained project scheduling problem
-
P. Brucker, S. Knust, A. Schoo, and O. Thiele A branch & bound algorithm for the resource-constrained project scheduling problem European Journal of Operational Research 107 2 1998 272 288
-
(1998)
European Journal of Operational Research
, vol.107
, Issue.2
, pp. 272-288
-
-
Brucker, P.1
Knust, S.2
Schoo, A.3
Thiele, O.4
-
22
-
-
0032070635
-
An exact algorithm for project scheduling with resource constraints based on new mathematical formulation
-
A. Mingozzi, V. Maniezzo, S. Ricciardelli, and L. Bianco An exact algorithm for project scheduling with resource constraints based on new mathematical formulation Management Science 44 5 1998 714 729
-
(1998)
Management Science
, vol.44
, Issue.5
, pp. 714-729
-
-
Mingozzi, A.1
Maniezzo, V.2
Ricciardelli, S.3
Bianco, L.4
-
24
-
-
0016498438
-
A comparison of heuristic and optimum solutions in resource-constrained project scheduling
-
E.W. Davis, and J.H. Patterson A comparison of heuristic and optimum solutions in resource-constrained project scheduling Management Science 21 81 1975 944 955
-
(1975)
Management Science
, vol.21
, Issue.81
, pp. 944-955
-
-
Davis, E.W.1
Patterson, J.H.2
-
25
-
-
0016972372
-
Heuristics for scheduling resource-constrained projects: An experimental investigation
-
D.F. Cooper Heuristics for scheduling resource-constrained projects: an experimental investigation Management Science 22 1976 1186 1194
-
(1976)
Management Science
, vol.22
, pp. 1186-1194
-
-
Cooper, D.F.1
-
26
-
-
0001849846
-
Heuristic algorithms for resource-constrained project scheduling: A review and an empirical analysis
-
R. Alvares-Valdes, and J.M. Tamarit Heuristic algorithms for resource-constrained project scheduling: a review and an empirical analysis R. Slowinski, J. Weglarz, Advances in project scheduling 1989 Elsevier Amsterdam 113 134
-
(1989)
Advances in Project Scheduling
, pp. 113-134
-
-
Alvares-Valdes, R.1
Tamarit, J.M.2
-
27
-
-
0025701919
-
Some efficient multi-heuristic procedures for resource-constrained project scheduling
-
F.F. Boctor Some efficient multi-heuristic procedures for resource-constrained project scheduling European Journal of Operational Research 49 1990 3 13
-
(1990)
European Journal of Operational Research
, vol.49
, pp. 3-13
-
-
Boctor, F.F.1
-
28
-
-
0009627197
-
A local constraint based analysis approach to project scheduling under general resource constraints
-
L. Ozdamar, and G. Ulusoy A local constraint based analysis approach to project scheduling under general resource constraints European Journal of Operational Research 79 1994 287 298
-
(1994)
European Journal of Operational Research
, vol.79
, pp. 287-298
-
-
Ozdamar, L.1
Ulusoy, G.2
-
29
-
-
0030231487
-
Efficient priority rule for the resource-constrained project scheduling problem
-
R. Kolisch Efficient priority rule for the resource-constrained project scheduling problem Journal of Operations Management 14 3 1996 179 192
-
(1996)
Journal of Operations Management
, vol.14
, Issue.3
, pp. 179-192
-
-
Kolisch, R.1
-
30
-
-
84974870375
-
Heuristic performance and network/resource characteristics in resource-constrained project scheduling
-
G. Ulusoy, and L. Ozdamar Heuristic performance and network/resource characteristics in resource-constrained project scheduling Journal of the Operational Research Society 40 1989 1145 1152
-
(1989)
Journal of the Operational Research Society
, vol.40
, pp. 1145-1152
-
-
Ulusoy, G.1
Ozdamar, L.2
-
31
-
-
0032117729
-
A tabu search approach for the resource constrained project scheduling problem
-
P.R. Thomas, and S. Salhi A tabu search approach for the resource constrained project scheduling problem Journal of Heuristics 4 1998 123 139
-
(1998)
Journal of Heuristics
, vol.4
, pp. 123-139
-
-
Thomas, P.R.1
Salhi, S.2
-
32
-
-
0026376478
-
Scheduling of project networks by job assignment
-
A. Drexl Scheduling of project networks by job assignment Management Science 37 1991 1590 1602
-
(1991)
Management Science
, vol.37
, pp. 1590-1602
-
-
Drexl, A.1
-
33
-
-
0030121479
-
Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation
-
R. Kolisch Serial and parallel resource-constrained project scheduling methods revisited: theory and computation European Journal of Operational Research 90 1996 320 333
-
(1996)
European Journal of Operational Research
, vol.90
, pp. 320-333
-
-
Kolisch, R.1
-
34
-
-
0001896880
-
Adaptive search for solving hard project scheduling problems
-
R. Kolisch, and A. Drexl Adaptive search for solving hard project scheduling problems Naval Research Logistics 43 1996 23 40
-
(1996)
Naval Research Logistics
, vol.43
, pp. 23-40
-
-
Kolisch, R.1
Drexl, A.2
-
36
-
-
0000103290
-
Case-based reasoning and improved adaptive search for project scheduling
-
A. Schirmer Case-based reasoning and improved adaptive search for project scheduling Naval Research Logistics 47 2000 201 222
-
(2000)
Naval Research Logistics
, vol.47
, pp. 201-222
-
-
Schirmer, A.1
-
37
-
-
33845274958
-
Strength and adaptability of problem-space based neighborhoods for resource-constrained scheduling
-
V.J. Leon, and B. Ramamoorthy Strength and adaptability of problem-space based neighborhoods for resource-constrained scheduling OR Spektrum 17 1995 173 182
-
(1995)
OR Spektrum
, vol.17
, pp. 173-182
-
-
Leon, V.J.1
Ramamoorthy, B.2
-
39
-
-
0032188522
-
A competitive genetic algorithm for the resource-constrained project scheduling
-
S. Hartmann A competitive genetic algorithm for the resource-constrained project scheduling Naval Research Logistics 45 1998 733 750
-
(1998)
Naval Research Logistics
, vol.45
, pp. 733-750
-
-
Hartmann, S.1
-
40
-
-
0036684673
-
A self-adapting genetic algorithm for project scheduling under resource constraints
-
S. Hartmann A self-adapting genetic algorithm for project scheduling under resource constraints Naval Research Logistics 49 2002 433 448
-
(2002)
Naval Research Logistics
, vol.49
, pp. 433-448
-
-
Hartmann, S.1
-
41
-
-
0042287689
-
A Robust Genetic Algorithm for Resource Allocation in Project Scheduling
-
DOI 10.1023/A:1010949931021
-
J. Alcaraz, and C. Maroto A robust genetic algorithm for resource allocation in project scheduling Annals of Operations Research 102 2001 83 109 (Pubitemid 33634388)
-
(2001)
Annals of Operations Research
, vol.102
, Issue.1-4
, pp. 83-109
-
-
Alcaraz, J.1
Maroto, C.2
-
42
-
-
24944581849
-
Comparative analysis of meta-heuristics for the resource constrained project scheduling problem
-
Instituto Superior Tecnico, Portugal
-
Coelho J, Tavares L. Comparative analysis of meta-heuristics for the resource constrained project scheduling problem. Technical report, Department of Civil Engineering, Instituto Superior Tecnico, Portugal; 2003.
-
(2003)
Technical Report, Department of Civil Engineering
-
-
Coelho, J.1
Tavares, L.2
-
44
-
-
0036024939
-
Application of genetic algorithms to construction scheduling with or without resource constraints
-
Y.C. Toklu Application of genetic algorithms to construction scheduling with or without resource constraints Canadian Journal of Civil Engineering 29 2002 421 429
-
(2002)
Canadian Journal of Civil Engineering
, vol.29
, pp. 421-429
-
-
Toklu, Y.C.1
-
46
-
-
0030216966
-
An adaptation of the simulated annealing algorithm for solving resource-constrained project scheduling problems
-
F.F. Boctor An adaptation of the simulated annealing algorithm for solving resource-constrained project scheduling problems International Journal of Production Research 34 1996 2335 2351
-
(1996)
International Journal of Production Research
, vol.34
, pp. 2335-2351
-
-
Boctor, F.F.1
-
47
-
-
0031188915
-
A simulated annealing algorithm for resource-constrained project scheduling problems
-
J.H. Cho, and Y.D. Kim A simulated annealing algorithm for resource-constrained project scheduling problems Journal of the Operational Research Society 48 1997 736 744
-
(1997)
Journal of the Operational Research Society
, vol.48
, pp. 736-744
-
-
Cho, J.H.1
Kim, Y.D.2
-
48
-
-
0037508562
-
A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version
-
K. Bouleimen, and H. Lecocq A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version European Journal of Operational Research 149 2003 268 281
-
(2003)
European Journal of Operational Research
, vol.149
, pp. 268-281
-
-
Bouleimen, K.1
Lecocq, H.2
-
50
-
-
0003131416
-
Tabu search algorithms for resource-constrained project scheduling problems
-
T. Baar, P. Brucker, and S. Knust Tabu search algorithms for resource-constrained project scheduling problems S. Voss, S. Martello, I. Osman, C. Roucairol, Metaheuristics: advances and trends in local search paradigms for optimisation 1997 Kluwer Academic Publishers Dordrecht 1 18
-
(1997)
Metaheuristics: Advances and Trends in Local Search Paradigms for Optimisation
, pp. 1-18
-
-
Baar, T.1
Brucker, P.2
Knust, S.3
-
51
-
-
84888782064
-
Formulation and tabu search algorithm for the resource constrained project scheduling problem
-
K. Nonobe, and T. Ibaraki Formulation and tabu search algorithm for the resource constrained project scheduling problem C.C. Ribeiro, P. Hansen, Essays and surveys in metaheuristics 2002 Kluwer Academic Publishers Dordrecht 557 588
-
(2002)
Essays and Surveys in Metaheuristics
, pp. 557-588
-
-
Nonobe, K.1
Ibaraki, T.2
-
52
-
-
0036672003
-
Ant colony optimization for resource-constrained project scheduling
-
DOI 10.1109/TEVC.2002.802450, PII 1011092002802450
-
D. Merkle, M. Middendorf, and H. Schmeck Ant colony optimization for resource-constrained project scheduling IEEE Transactions on Evolutionary Computation 6 2002 333 346 (Pubitemid 35032735)
-
(2002)
IEEE Transactions on Evolutionary Computation
, vol.6
, Issue.4
, pp. 333-346
-
-
Merkle, D.1
Middendorf, M.2
Schmeck, H.3
-
55
-
-
59149093294
-
Using an enhanced scatter search algorithm for a resource-constrained project scheduling problem
-
M.D. Mahdi Mobini, M. Rabbani, M.S. Amalnik, J. Razmi, and A.R. Rahimi-Vahed Using an enhanced scatter search algorithm for a resource-constrained project scheduling problem Soft Computing 13 2009 597 610
-
(2009)
Soft Computing
, vol.13
, pp. 597-610
-
-
Mahdi Mobini, M.D.1
Rabbani, M.2
Amalnik, M.S.3
Razmi, J.4
Rahimi-Vahed, A.R.5
-
56
-
-
44649097606
-
Solving the resource constrained project scheduling problem using filter-and-fan approach
-
M. Ranjbar Solving the resource constrained project scheduling problem using filter-and-fan approach Applied Mathematics and Computation 201 2008 313 318
-
(2008)
Applied Mathematics and Computation
, vol.201
, pp. 313-318
-
-
Ranjbar, M.1
-
57
-
-
52049097838
-
A hybrid scatter search for the discreet time/resource trade-off problem in project scheduling
-
M. Ranjbar, B.D. Reyck, and F. Kianfar A hybrid scatter search for the discreet time/resource trade-off problem in project scheduling European Journal of Operational Research 193 2009 35 48
-
(2009)
European Journal of Operational Research
, vol.193
, pp. 35-48
-
-
Ranjbar, M.1
Reyck, B.D.2
Kianfar, F.3
-
59
-
-
38549091692
-
A decomposition-based genetic algorithm for the resource-constrained project-scheduling problem
-
D. Debels, and M. Vanhoucke A decomposition-based genetic algorithm for the resource-constrained project-scheduling problem Operations Research 55 3 2007 457 469
-
(2007)
Operations Research
, vol.55
, Issue.3
, pp. 457-469
-
-
Debels, D.1
Vanhoucke, M.2
-
60
-
-
0242364615
-
An efficient multi-pass heuristic for project scheduling with constrained resources
-
P. Tormos, and A. Lova An efficient multi-pass heuristic for project scheduling with constrained resources International Journal of Production Research 41 5 2003 1071 1086
-
(2003)
International Journal of Production Research
, vol.41
, Issue.5
, pp. 1071-1086
-
-
Tormos, P.1
Lova, A.2
-
62
-
-
0035617605
-
A Competitive Heuristic Solution Technique for Resource-Constrained Project Scheduling
-
DOI 10.1023/A:1010997814183
-
P. Tormos, and A. Lova A competitive heuristic solution technique for resource constrained project scheduling Annals of Operations Research 102 2001 65 81 (Pubitemid 33634387)
-
(2001)
Annals of Operations Research
, vol.102
, Issue.1-4
, pp. 65-81
-
-
Tormos, P.1
Lova, A.2
-
63
-
-
25444456205
-
A hybrid scatter search/electromagnetism meta-heuristic for project scheduling
-
D. Debels, B. De Reyck, R. Leus, and M. Vanhoucke A hybrid scatter search/electromagnetism meta-heuristic for project scheduling European Journal of Operational Research 169 2 2006 638 653
-
(2006)
European Journal of Operational Research
, vol.169
, Issue.2
, pp. 638-653
-
-
Debels, D.1
De Reyck, B.2
Leus, R.3
Vanhoucke, M.4
|