메뉴 건너뛰기




Volumn 59, Issue , 2015, Pages 24-37

A BIM-based automated site layout planning framework for congested construction sites

Author keywords

Actual travel paths; Building information modelling (BIM); Congested sites; Construction site layout planning (CSLP); Facility dimensions optimization; Interior storage

Indexed keywords

CONSTRUCTION; CONSTRUCTION EQUIPMENT; DIGITAL STORAGE; GENETIC ALGORITHMS; TRANSPORTATION PERSONNEL;

EID: 84941342239     PISSN: 09265805     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.autcon.2015.07.008     Document Type: Article
Times cited : (164)

References (40)
  • 2
    • 0027607458 scopus 로고
    • Interactive dynamic layout planning
    • I. Tommelein, and P. Zouein Interactive dynamic layout planning J. Constr. Eng. Manag. 119 2 1993 266 287
    • (1993) J. Constr. Eng. Manag. , vol.119 , Issue.2 , pp. 266-287
    • Tommelein, I.1    Zouein, P.2
  • 3
    • 5244248406 scopus 로고    scopus 로고
    • ArcSite: Enhanced GIS for construction site layout
    • M. Cheng, and J. O'Connor ArcSite: Enhanced GIS for construction site layout J. Constr. Eng. Manag. 122 4 1996 329 336
    • (1996) J. Constr. Eng. Manag. , vol.122 , Issue.4 , pp. 329-336
    • Cheng, M.1    O'Connor, J.2
  • 4
    • 0032187321 scopus 로고    scopus 로고
    • Site-level facilities layout using genetic algorithms
    • H. Li, and P.E. Love Site-level facilities layout using genetic algorithms J. Comput. Civ. Eng. 12 4 1998 227 231
    • (1998) J. Comput. Civ. Eng. , vol.12 , Issue.4 , pp. 227-231
    • Li, H.1    Love, P.E.2
  • 5
    • 0029344681 scopus 로고
    • Construction-site layout using annealed neural network
    • I.-C. Yeh Construction-site layout using annealed neural network J. Comput. Civ. Eng. 9 3 1995 201 208
    • (1995) J. Comput. Civ. Eng. , vol.9 , Issue.3 , pp. 201-208
    • Yeh, I.-C.1
  • 7
    • 79954583036 scopus 로고    scopus 로고
    • Automated multi-objective optimization system for airport site layouts
    • A. Khalafallah, and K. El-Rayes Automated multi-objective optimization system for airport site layouts Autom. Constr. 20 4 2011 313 320
    • (2011) Autom. Constr. , vol.20 , Issue.4 , pp. 313-320
    • Khalafallah, A.1    El-Rayes, K.2
  • 8
    • 4344695708 scopus 로고    scopus 로고
    • Genetic algorithms for construction site layout in project planning
    • M.J. Mawdesley, S.H. Al-Jibouri, and H. Yang Genetic algorithms for construction site layout in project planning J. Constr. Eng. Manag. 128 5 2002 418 426
    • (2002) J. Constr. Eng. Manag. , vol.128 , Issue.5 , pp. 418-426
    • Mawdesley, M.J.1    Al-Jibouri, S.H.2    Yang, H.3
  • 10
    • 0141990673 scopus 로고    scopus 로고
    • A hybrid CAD-based construction site layout planning system using genetic algorithms
    • H.M. Osman, M.E. Georgy, and M.E. Ibrahim A hybrid CAD-based construction site layout planning system using genetic algorithms Autom. Constr. 12 6 2003 749 764
    • (2003) Autom. Constr. , vol.12 , Issue.6 , pp. 749-764
    • Osman, H.M.1    Georgy, M.E.2    Ibrahim, M.E.3
  • 11
    • 84871747122 scopus 로고    scopus 로고
    • Dynamic site layout planning through minimization of total potential energy
    • M. Andayesh, and F. Sadeghpour Dynamic site layout planning through minimization of total potential energy Autom. Constr. 31 2013 92 102
    • (2013) Autom. Constr. , vol.31 , pp. 92-102
    • Andayesh, M.1    Sadeghpour, F.2
  • 12
    • 84899867149 scopus 로고    scopus 로고
    • The time dimension in site layout planning
    • M. Andayesh, and F. Sadeghpour The time dimension in site layout planning Autom. Constr. 44 2014 129 139
    • (2014) Autom. Constr. , vol.44 , pp. 129-139
    • Andayesh, M.1    Sadeghpour, F.2
  • 13
    • 13944281386 scopus 로고    scopus 로고
    • Dynamic layout of construction temporary facilities considering safety
    • E. Elbeltagi, T. Hegazy, and A. Eldosouky Dynamic layout of construction temporary facilities considering safety J. Constr. Eng. Manag. 130 4 2004 534 541
    • (2004) J. Constr. Eng. Manag. , vol.130 , Issue.4 , pp. 534-541
    • Elbeltagi, E.1    Hegazy, T.2    Eldosouky, A.3
  • 14
    • 70449526183 scopus 로고    scopus 로고
    • Dynamic construction site layout planning using max-min ant system
    • X. Ning, K.-C. Lam, and M.C.-K. Lam Dynamic construction site layout planning using max-min ant system Autom. Constr. 19 1 2010 55 65
    • (2010) Autom. Constr. , vol.19 , Issue.1 , pp. 55-65
    • Ning, X.1    Lam, K.-C.2    Lam, M.C.-K.3
  • 15
    • 84872790095 scopus 로고    scopus 로고
    • Optimal utilization of interior building spaces for material procurement and storage in congested construction sites
    • H. Said, and K. El-Rayes Optimal utilization of interior building spaces for material procurement and storage in congested construction sites Autom. Constr. 31 2013 292 306
    • (2013) Autom. Constr. , vol.31 , pp. 292-306
    • Said, H.1    El-Rayes, K.2
  • 16
    • 45749148242 scopus 로고    scopus 로고
    • Optimal construction site layout considering safety and environmental aspects
    • H.M. Sanad, M.A. Ammar, and M.E. Ibrahim Optimal construction site layout considering safety and environmental aspects J. Constr. Eng. Manag. 134 7 2008 536 544
    • (2008) J. Constr. Eng. Manag. , vol.134 , Issue.7 , pp. 536-544
    • Sanad, H.M.1    Ammar, M.A.2    Ibrahim, M.E.3
  • 17
    • 84863711984 scopus 로고    scopus 로고
    • Multi-objective dynamic construction site layout planning in fuzzy random environment
    • J. Xu, and Z. Li Multi-objective dynamic construction site layout planning in fuzzy random environment Autom. Constr. 27 2012 155 169
    • (2012) Autom. Constr. , vol.27 , pp. 155-169
    • Xu, J.1    Li, Z.2
  • 18
    • 84889057012 scopus 로고    scopus 로고
    • Construction site layout planning using multi-objective artificial bee colony algorithm with Levy flights
    • M. Yahya, and M. Saka Construction site layout planning using multi-objective artificial bee colony algorithm with Levy flights Autom. Constr. 38 2014 14 29
    • (2014) Autom. Constr. , vol.38 , pp. 14-29
    • Yahya, M.1    Saka, M.2
  • 19
    • 0033313625 scopus 로고    scopus 로고
    • Dynamic layout planning using a hybrid incremental solution method
    • P. Zouein, and I. Tommelein Dynamic layout planning using a hybrid incremental solution method J. Constr. Eng. Manag. 125 6 1999 400 408
    • (1999) J. Constr. Eng. Manag. , vol.125 , Issue.6 , pp. 400-408
    • Zouein, P.1    Tommelein, I.2
  • 20
    • 84863694377 scopus 로고    scopus 로고
    • GIS-based dynamic construction site material layout evaluation for building renovation projects
    • X. Su, H. Cai, J. Pan, A. Kandil, and H.M. Said GIS-based dynamic construction site material layout evaluation for building renovation projects Autom. Constr. 27 2012 40 49
    • (2012) Autom. Constr. , vol.27 , pp. 40-49
    • Su, X.1    Cai, H.2    Pan, J.3    Kandil, A.4    Said, H.M.5
  • 21
    • 84897449909 scopus 로고    scopus 로고
    • Automated multi-objective construction logistics optimization system
    • H. Said, and K. El-Rayes Automated multi-objective construction logistics optimization system Autom. Constr. 43 2014 110 122
    • (2014) Autom. Constr. , vol.43 , pp. 110-122
    • Said, H.1    El-Rayes, K.2
  • 22
    • 84906243169 scopus 로고    scopus 로고
    • Framework for work-space planning using four-dimensional BIM in construction projects
    • B. Choi, H.-S. Lee, M. Park, Y.K. Cho, and H. Kim Framework for work-space planning using four-dimensional BIM in construction projects J. Constr. Eng. Manag. 140 9 2014
    • (2014) J. Constr. Eng. Manag. , vol.140 , Issue.9
    • Choi, B.1    Lee, H.-S.2    Park, M.3    Cho, Y.K.4    Kim, H.5
  • 23
    • 84924971295 scopus 로고    scopus 로고
    • Extending BIM interoperability to preconstruction operations using geospatial analyses and semantic web services
    • E.P. Karan, and J. Irizarry Extending BIM interoperability to preconstruction operations using geospatial analyses and semantic web services Autom. Constr. 53 2015 1 12
    • (2015) Autom. Constr. , vol.53 , pp. 1-12
    • Karan, E.P.1    Irizarry, J.2
  • 24
    • 84901259328 scopus 로고    scopus 로고
    • Particle bee algorithm for tower crane layout with material quantity supply and demand optimization
    • L.-C. Lien, and M.-Y. Cheng Particle bee algorithm for tower crane layout with material quantity supply and demand optimization Autom. Constr. 45 2014 25 32
    • (2014) Autom. Constr. , vol.45 , pp. 25-32
    • Lien, L.-C.1    Cheng, M.-Y.2
  • 25
    • 84945131042 scopus 로고    scopus 로고
    • BIM-based fall hazard identification and prevention in construction safety planning
    • S. Zhang, K. Sulankivi, M. Kiviniemi, I. Romo, C.M. Eastman, and J. Teizer BIM-based fall hazard identification and prevention in construction safety planning Saf. Sci. 72 2015 31 45
    • (2015) Saf. Sci. , vol.72 , pp. 31-45
    • Zhang, S.1    Sulankivi, K.2    Kiviniemi, M.3    Romo, I.4    Eastman, C.M.5    Teizer, J.6
  • 26
    • 84926179316 scopus 로고    scopus 로고
    • Applicability of 4D modeling for resource allocation in mega liquefied natural gas plant construction
    • Y. Zhou, L. Ding, X. Wang, M. Truijens, and H. Luo Applicability of 4D modeling for resource allocation in mega liquefied natural gas plant construction Autom. Constr. 50 2015 50 63
    • (2015) Autom. Constr. , vol.50 , pp. 50-63
    • Zhou, Y.1    Ding, L.2    Wang, X.3    Truijens, M.4    Luo, H.5
  • 27
    • 13944251393 scopus 로고    scopus 로고
    • Four-dimensional visualization of construction scheduling and site utilization
    • K. Chau, M. Anson, and J. Zhang Four-dimensional visualization of construction scheduling and site utilization J. Constr. Eng. Manag. 130 4 2004 598 606
    • (2004) J. Constr. Eng. Manag. , vol.130 , Issue.4 , pp. 598-606
    • Chau, K.1    Anson, M.2    Zhang, J.3
  • 28
    • 47749092071 scopus 로고    scopus 로고
    • New mathematical optimization model for construction site layout
    • S.M. Easa, and K.M.A. Hossain New mathematical optimization model for construction site layout J. Constr. Eng. Manag. 134 8 2008 653 662
    • (2008) J. Constr. Eng. Manag. , vol.134 , Issue.8 , pp. 653-662
    • Easa, S.M.1    Hossain, K.M.A.2
  • 29
    • 13244275240 scopus 로고    scopus 로고
    • Application of 4D for dynamic site layout and management of construction projects
    • Z. Ma, Q. Shen, and J. Zhang Application of 4D for dynamic site layout and management of construction projects Autom. Constr. 14 3 2005 369 381
    • (2005) Autom. Constr. , vol.14 , Issue.3 , pp. 369-381
    • Ma, Z.1    Shen, Q.2    Zhang, J.3
  • 30
    • 84904687387 scopus 로고    scopus 로고
    • Floor-level construction material layout planning model considering actual travel path
    • M. Park, Y. Yang, H.-S. Lee, S. Han, and S.-h. Ji Floor-level construction material layout planning model considering actual travel path J. Constr. Eng. Manag. 138 7 2011 905 915
    • (2011) J. Constr. Eng. Manag. , vol.138 , Issue.7 , pp. 905-915
    • Park, M.1    Yang, Y.2    Lee, H.-S.3    Han, S.4
  • 31
    • 0029470095 scopus 로고
    • Patterns of construction-space use in multistory buildings
    • D.R. Riley, and V.E. Sanvido Patterns of construction-space use in multistory buildings J. Constr. Eng. Manag. 121 4 1995 464 473
    • (1995) J. Constr. Eng. Manag. , vol.121 , Issue.4 , pp. 464-473
    • Riley, D.R.1    Sanvido, V.E.2
  • 32
    • 2342435265 scopus 로고    scopus 로고
    • Site layout planning using nonstructural fuzzy decision support system
    • C. Tam, T.K. Tong, A.W. Leung, and G.W. Chiu Site layout planning using nonstructural fuzzy decision support system J. Constr. Eng. Manag. 128 3 2002 220 231
    • (2002) J. Constr. Eng. Manag. , vol.128 , Issue.3 , pp. 220-231
    • Tam, C.1    Tong, T.K.2    Leung, A.W.3    Chiu, G.W.4
  • 33
    • 3142565144 scopus 로고    scopus 로고
    • 4D dynamic management for construction planning and resource utilization
    • H. Wang, J. Zhang, K. Chau, and M. Anson 4D dynamic management for construction planning and resource utilization Autom. Constr. 13 5 2004 575 589
    • (2004) Autom. Constr. , vol.13 , Issue.5 , pp. 575-589
    • Wang, H.1    Zhang, J.2    Chau, K.3    Anson, M.4
  • 34
    • 0036680436 scopus 로고    scopus 로고
    • Hybrid intelligence utilization for construction site layout
    • J. Zhang, L. Liu, and R. Coble Hybrid intelligence utilization for construction site layout Autom. Constr. 11 5 2002 511 519
    • (2002) Autom. Constr. , vol.11 , Issue.5 , pp. 511-519
    • Zhang, J.1    Liu, L.2    Coble, R.3
  • 35
    • 0041805006 scopus 로고    scopus 로고
    • Automated generation of work spaces required by construction activities
    • B. Akinci, M. Fischer, and J. Kunz Automated generation of work spaces required by construction activities J. Constr. Eng. Manag. 128 4 2002 306 315
    • (2002) J. Constr. Eng. Manag. , vol.128 , Issue.4 , pp. 306-315
    • Akinci, B.1    Fischer, M.2    Kunz, J.3
  • 37
    • 84949115555 scopus 로고    scopus 로고
    • A comparative study of different approaches for finding the shortest path on construction sites
    • M. Andayesh, and F. Sadeghpour A comparative study of different approaches for finding the shortest path on construction sites Procedia Eng. 85 2014 33 41
    • (2014) Procedia Eng. , vol.85 , pp. 33-41
    • Andayesh, M.1    Sadeghpour, F.2
  • 38
    • 4344717496 scopus 로고    scopus 로고
    • A fuzzy based multi-objective path planning of construction sites
    • A. Soltani, and T. Fernando A fuzzy based multi-objective path planning of construction sites Autom. Constr. 13 6 2004 717 734
    • (2004) Autom. Constr. , vol.13 , Issue.6 , pp. 717-734
    • Soltani, A.1    Fernando, T.2
  • 39
    • 0041427756 scopus 로고    scopus 로고
    • Path planning in construction sites: Performance evaluation of the Dijkstra, A, and GA search algorithms
    • A.R. Soltani, H. Tawfik, J.Y. Goulermas, and T. Fernando Path planning in construction sites: performance evaluation of the Dijkstra, A, and GA search algorithms Adv. Eng. Inform. 16 4 2002 291 303
    • (2002) Adv. Eng. Inform. , vol.16 , Issue.4 , pp. 291-303
    • Soltani, A.R.1    Tawfik, H.2    Goulermas, J.Y.3    Fernando, T.4


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.