Volumn 29, Issue 1, 2011, Pages 78-92

Planning-stage estimation of highway project duration on the basis of anticipated project cost, project type, and contract type

Author keywords

Engineering and construction; North America; Project management; Transport

Indexed keywords

BRIDGE CONSTRUCTIONS; CONSTRUCTION PLANNING; CONTRACT ADMINISTRATION; DEVELOPED MODEL; HIGHWAY AGENCIES; HIGHWAY PROJECTS; IMPACT ASSESSMENTS; MATHEMATICAL RELATIONSHIP; MODEL SPECIFICATIONS; NORTH AMERICA; PAVEMENT CONSTRUCTION; PLANNING PHASE; PROJECT COST; PROJECT DEVELOPMENT; PROJECT DURATION; PROJECT IMPLEMENTATION; TIME DURATION; TRANSPORT; USER COST;

EID: 78049299997     PISSN: 02637863     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijproman.2010.01.001     Document Type: Article
Times cited : (56)

References (44)
  • 1
    • 78049271137 scopus 로고    scopus 로고
    • Performance-based contracting for roadway maintenance operations in Indiana. M.S. Thesis, Purdue University, W. Lafayette, Ind.
    • Anastasopoulos, P.Ch., 2007. Performance-based contracting for roadway maintenance operations in Indiana. M.S. Thesis, Purdue University, W. Lafayette, Ind.
    • (2007)
    • Anastasopoulos, P.Ch.1
  • 2
    • 0006865274 scopus 로고
    • Reasons for delays in public projects in Turkey
    • Arditi D., Akan G.T., Gurdamer S. Reasons for delays in public projects in Turkey. J. Constr. Manage. Econ. 1985, 3(2):171-181.
    • (1985) J. Constr. Manage. Econ. , vol.3 , Issue.2 , pp. 171-181
    • Arditi, D.1    Akan, G.T.2    Gurdamer, S.3
  • 3
    • 78049256159 scopus 로고    scopus 로고
    • A simple model for predicting delay at actuated signalized intersections. In: Presented at the 10th Int. Conf. on Appl. of Adv. Tech. in Transp., May 27-31, Athens, Greece.
    • Bhargava, A., Anastasopoulos, P.Ch., Labi, S., Sinha, K.C., Mannering, F.L., 2008. A simple model for predicting delay at actuated signalized intersections. In: Presented at the 10th Int. Conf. on Appl. of Adv. Tech. in Transp., May 27-31, Athens, Greece.
    • (2008)
    • Bhargava, A.1    Anastasopoulos, P.Ch.2    Labi, S.3    Sinha, K.C.4    Mannering, F.L.5
  • 4
    • 0035341251 scopus 로고    scopus 로고
    • Time-cost relationship of public sector projects in Malaysia
    • Chan A.P.C. Time-cost relationship of public sector projects in Malaysia. Int. J. Proj. Manage. 2001, 19:223-229.
    • (2001) Int. J. Proj. Manage. , vol.19 , pp. 223-229
    • Chan, A.P.C.1
  • 5
    • 26644445713 scopus 로고    scopus 로고
    • Time-cost optimization of construction projects with generalized activity constraints
    • Chassiakos A.P., Sakellaropoulos S.P. Time-cost optimization of construction projects with generalized activity constraints. J. Constr. Manage. 2005, 131(10):1115-1124.
    • (2005) J. Constr. Manage. , vol.131 , Issue.10 , pp. 1115-1124
    • Chassiakos, A.P.1    Sakellaropoulos, S.P.2
  • 8
    • 84950651862 scopus 로고
    • Efficiency of Cox's likelihood function for censored data
    • Efron B. Efficiency of Cox's likelihood function for censored data. J. Am. Stat. Assoc. 1977, 72:557-565.
    • (1977) J. Am. Stat. Assoc. , vol.72 , pp. 557-565
    • Efron, B.1
  • 10
    • 0033326356 scopus 로고    scopus 로고
    • Effectiveness of maintenance treatments of flexible pavements
    • Eltahan A.A., Daleiden J.F., Simpson A.L. Effectiveness of maintenance treatments of flexible pavements. Transp. Res. Rec. 1999, 1680:18-25.
    • (1999) Transp. Res. Rec. , vol.1680 , pp. 18-25
    • Eltahan, A.A.1    Daleiden, J.F.2    Simpson, A.L.3
  • 11
    • 0015484051 scopus 로고
    • Critical path problems with concave cost-time curve
    • Falk J., Horowitz J.L. Critical path problems with concave cost-time curve. Manage. Sci. 1972, 19:446-455.
    • (1972) Manage. Sci. , vol.19 , pp. 446-455
    • Falk, J.1    Horowitz, J.L.2
  • 12
    • 78049271616 scopus 로고    scopus 로고
    • Federal Highway Administration (FHWA), Life cycle cost analysis in pavement design - in search of better investment decisions. Report FHWA-SA-98-079. Federal Highway Admin., Washington, DC.
    • Federal Highway Administration (FHWA), 1998. Life cycle cost analysis in pavement design - in search of better investment decisions. Report FHWA-SA-98-079. Federal Highway Admin., Washington, DC.
    • (1998)
  • 13
    • 78049287051 scopus 로고    scopus 로고
    • Federal Highway Administration (FHWA), 2007. Price trends for federal-aid highway construction. (accessed December 2007).
    • Federal Highway Administration (FHWA), 2007. Price trends for federal-aid highway construction. (accessed December 2007). http://www.fhwa.dot.gov/programadmin/pt2006q4.cfm.
  • 14
    • 0027222453 scopus 로고
    • Pert and crashing revisited: mathematical generalizations
    • Foldes S., Soumis F. Pert and crashing revisited: mathematical generalizations. Eur. J. Oper. Res. 1993, 64:286-294.
    • (1993) Eur. J. Oper. Res. , vol.64 , pp. 286-294
    • Foldes, S.1    Soumis, F.2
  • 15
    • 0000181338 scopus 로고
    • A network flow computation for project cost curves
    • Fulkerson D.R. A network flow computation for project cost curves. Manage. Sci. 1961, 7:167-178.
    • (1961) Manage. Sci. , vol.7 , pp. 167-178
    • Fulkerson, D.R.1
  • 16
    • 0347534016 scopus 로고    scopus 로고
    • Probabilistic analysis of highway pavement life for Illinois
    • Gharaibeh N.G., Darter M.I. Probabilistic analysis of highway pavement life for Illinois. Transp. Res. Rec. 2003, 1823:111-120.
    • (2003) Transp. Res. Rec. , vol.1823 , pp. 111-120
    • Gharaibeh, N.G.1    Darter, M.I.2
  • 17
    • 0004296209 scopus 로고    scopus 로고
    • Prentice-Hall, Upper Saddle River, NJ
    • Greene W. Econometric Analysis 2000, Prentice-Hall, Upper Saddle River, NJ. foutth ed.
    • (2000) Econometric Analysis
    • Greene, W.1
  • 18
    • 57849122707 scopus 로고    scopus 로고
    • Econometric Software, Inc., Plainview, NY
    • Greene W. Limdep Version 9.0 2007, Econometric Software, Inc., Plainview, NY.
    • (2007) Limdep Version 9.0
    • Greene, W.1
  • 19
    • 78049246125 scopus 로고
    • A note on travelers 'home-stay duration and the efficiency of proportional hazard models'. Working Paper, University of Washington, and Seattle.
    • Hamed, M.K., Kim, S.G., Mannering, F., 1993. A note on travelers 'home-stay duration and the efficiency of proportional hazard models'. Working Paper, University of Washington, and Seattle.
    • (1993)
    • Hamed, M.K.1    Kim, S.G.2    Mannering, F.3
  • 20
    • 0023363930 scopus 로고
    • Hierarchical rule-based activity duration estimation
    • Hendrickson C., Martinelli D., Rehak D. Hierarchical rule-based activity duration estimation. J. Constr. Manage. 1987, 113(2):288-301.
    • (1987) J. Constr. Manage. , vol.113 , Issue.2 , pp. 288-301
    • Hendrickson, C.1    Martinelli, D.2    Rehak, D.3
  • 23
    • 78049312537 scopus 로고    scopus 로고
    • Indiana Department of Transportation (INDOT), The Indiana design manual. Indianapolis, IN. (accessed March 2009).
    • Indiana Department of Transportation (INDOT), 2009. The Indiana design manual. Indianapolis, IN. (accessed March 2009). http://www.in.gov/dot/div/contracts/standards/dm/.
    • (2009)
  • 24
    • 0003061735 scopus 로고
    • Investigating household purchase timing decisions: a conditional hazard function approach
    • Jain D.C., Vilcassim N.J. Investigating household purchase timing decisions: a conditional hazard function approach. Mark. Sci. 1991, 10(1):1-23.
    • (1991) Mark. Sci. , vol.10 , Issue.1 , pp. 1-23
    • Jain, D.C.1    Vilcassim, N.J.2
  • 25
    • 67349174243 scopus 로고    scopus 로고
    • Cost escalation and schedule delays in road construction projects in Zambia
    • Kaliba C., Muya M., Mumba K. Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Proj. Manage. 2009, 27(5):522-531.
    • (2009) Int. J. Proj. Manage. , vol.27 , Issue.5 , pp. 522-531
    • Kaliba, C.1    Muya, M.2    Mumba, K.3
  • 26
    • 0023594272 scopus 로고
    • Concurrent delays in construction projects
    • Kraiem Z.M. Concurrent delays in construction projects. J. Constr. Manage. 1987, 113(4):591-601.
    • (1987) J. Constr. Manage. , vol.113 , Issue.4 , pp. 591-601
    • Kraiem, Z.M.1
  • 27
    • 56249112590 scopus 로고    scopus 로고
    • Decision support for optimal scheduling of highway pavement preventive maintenance within resurfacing cycle
    • Lamptey G., Labi S., Li Z. Decision support for optimal scheduling of highway pavement preventive maintenance within resurfacing cycle. Decis. Support Syst. 2008, 46(1):376-387.
    • (2008) Decis. Support Syst. , vol.46 , Issue.1 , pp. 376-387
    • Lamptey, G.1    Labi, S.2    Li, Z.3
  • 28
    • 64449085007 scopus 로고    scopus 로고
    • Prediction of project outcome: the application of statistical methods to earned value management and earned schedule performance indexes
    • Lipke W., Zwikael O., Henderson K., Anbari F. Prediction of project outcome: the application of statistical methods to earned value management and earned schedule performance indexes. Int. J. Proj. Manage. 2009, 27:400-407.
    • (2009) Int. J. Proj. Manage. , vol.27 , pp. 400-407
    • Lipke, W.1    Zwikael, O.2    Henderson, K.3    Anbari, F.4
  • 29
    • 33646383843 scopus 로고    scopus 로고
    • Pavement crack initiation prediction from in-service pavements: a duration model approach
    • Loizos A., Karlaftis M.G. Pavement crack initiation prediction from in-service pavements: a duration model approach. Transp. Res. Rec. 2005, 1940:38-42.
    • (2005) Transp. Res. Rec. , vol.1940 , pp. 38-42
    • Loizos, A.1    Karlaftis, M.G.2
  • 30
    • 0032072617 scopus 로고    scopus 로고
    • Factors of non-excusable delays that influence contractor's performance
    • Majid M., McCaffer R. Factors of non-excusable delays that influence contractor's performance. J. Manage. Eng. 1998, 42-49.
    • (1998) J. Manage. Eng. , pp. 42-49
    • Majid, M.1    McCaffer, R.2
  • 32
    • 13944265628 scopus 로고    scopus 로고
    • Flexible model for time-cost trade-off problem
    • Moussourakis J., Haksever C. Flexible model for time-cost trade-off problem. J. Constr. Manage. 2004, 130(3):307-314.
    • (2004) J. Constr. Manage. , vol.130 , Issue.3 , pp. 307-314
    • Moussourakis, J.1    Haksever, C.2
  • 33
    • 29044442114 scopus 로고    scopus 로고
    • Using Weibull analysis for evaluation of cost and schedule performance
    • Nassar K.M., Gunnarsson Hordur G., Hegab M.Y. Using Weibull analysis for evaluation of cost and schedule performance. J. Constr. Manage. 2005, 131(12):1257-1262.
    • (2005) J. Constr. Manage. , vol.131 , Issue.12 , pp. 1257-1262
    • Nassar, K.M.1    Gunnarsson, H.G.2    Hegab, M.Y.3
  • 34
    • 0017709268 scopus 로고
    • The asymptotic information in censored survival data
    • Oaks D. The asymptotic information in censored survival data. Biometrika 1977, 64:441-448.
    • (1977) Biometrika , vol.64 , pp. 441-448
    • Oaks, D.1
  • 36
    • 0032208139 scopus 로고    scopus 로고
    • Approximation algorithms for the discrete time-cost trade-off problem
    • Skutella M. Approximation algorithms for the discrete time-cost trade-off problem. Math. Oper. Res. 1998, 23(4):909-929.
    • (1998) Math. Oper. Res. , vol.23 , Issue.4 , pp. 909-929
    • Skutella, M.1
  • 37
    • 33847331195 scopus 로고    scopus 로고
    • Early estimation of building construction speed in Germany
    • Stoy C., Pollalis S., Schalcher H. Early estimation of building construction speed in Germany. Int. J. Proj. Manage. 2007, 25:283-289.
    • (2007) Int. J. Proj. Manage. , vol.25 , pp. 283-289
    • Stoy, C.1    Pollalis, S.2    Schalcher, H.3
  • 38
    • 33645967441 scopus 로고    scopus 로고
    • A comparison of different project duration forecasting methods using earned value metrics
    • Vandevoorde S., Vanhoucke M. A comparison of different project duration forecasting methods using earned value metrics. Int. J. Proj. Manage. 2006, 24:289-302.
    • (2006) Int. J. Proj. Manage. , vol.24 , pp. 289-302
    • Vandevoorde, S.1    Vanhoucke, M.2
  • 39
    • 25444509194 scopus 로고    scopus 로고
    • Survival analysis of fatigue cracking for flexible pavements based on long-term pavement performance data
    • Wang Y., Mahboub K.C., Hancher D.E. Survival analysis of fatigue cracking for flexible pavements based on long-term pavement performance data. J. Transp. Eng. 2005, 131:608-616.
    • (2005) J. Transp. Eng. , vol.131 , pp. 608-616
    • Wang, Y.1    Mahboub, K.C.2    Hancher, D.E.3
  • 41
    • 24944537152 scopus 로고    scopus 로고
    • Chance-constrained time-cost tradeoff analysis considering funding variability
    • Yang I.T. Chance-constrained time-cost tradeoff analysis considering funding variability. J. Constr. Manage. 2005, 131(9):1002-1012.
    • (2005) J. Constr. Manage. , vol.131 , Issue.9 , pp. 1002-1012
    • Yang, I.T.1
  • 42
    • 34250644399 scopus 로고    scopus 로고
    • Using elitist particle swarm optimization to facilitate bicriterion time-cost trade-off analysis
    • Yang I.T. Using elitist particle swarm optimization to facilitate bicriterion time-cost trade-off analysis. J. Constr. Manage. 2007, 133(7):499-505.
    • (2007) J. Constr. Manage. , vol.133 , Issue.7 , pp. 499-505
    • Yang, I.T.1
  • 43
    • 78049270632 scopus 로고    scopus 로고
    • Estimation of pavement lifespan using stochastic duration models. In: Presented at 86th Ann. Mtg., Transp. Res. Board, Washington, DC.
    • Yang, J., 2007. Estimation of pavement lifespan using stochastic duration models. In: Presented at 86th Ann. Mtg., Transp. Res. Board, Washington, DC.
    • (2007)
    • Yang, J.1
  • 44
    • 2342615793 scopus 로고    scopus 로고
    • Applying a genetic algorithm-based multiobjective approach for time-cost optimization
    • Zheng D.X.M., Ng S.T., Kumaraswamy M.M. Applying a genetic algorithm-based multiobjective approach for time-cost optimization. J. Constr. Manage. 2004, 130(2):168-176.
    • (2004) J. Constr. Manage. , vol.130 , Issue.2 , pp. 168-176
    • Zheng, D.X.M.1    Ng, S.T.2    Kumaraswamy, M.M.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.