Volumn 37, Issue , 2014, Pages 68-80

Integrating building information models with construction process simulations for project scheduling support

Author keywords

Building information modeling; Operations simulation; Quantity takeoffs; Scheduling; Stroboscope

Indexed keywords

BUILDING INFORMATION MODEL - BIM; CONSTRUCTION PROCESS; LIMITED INFORMATION; OPERATIONS SIMULATION; PROJECT SCHEDULING; QUANTITY TAKEOFF; RESOURCE ALLOCATION STRATEGIES; TRANSFER INFORMATION;

EID: 84887850438     PISSN: 09265805     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.autcon.2013.10.009     Document Type: Article
Times cited : (123)

References (39)
  • 1
    • 51849088974 scopus 로고    scopus 로고
    • Areas of application for 3D and 4D models on construction projects
    • T. Hartmann, J. Gao, and M. Fisher Areas of application for 3D and 4D models on construction projects J. Constr. Eng. Manag. 134 10 2008 776 785
    • (2008) J. Constr. Eng. Manag. , vol.134 , Issue.10 , pp. 776-785
    • Hartmann, T.1    Gao, J.2    Fisher, M.3
  • 2
    • 0034227635 scopus 로고    scopus 로고
    • Feasibility study of 4D CAD in commercial construction
    • B. Koo, and M. Fisher Feasibility study of 4D CAD in commercial construction J. Constr. Eng. Manag. 126 4 2000 251 260
    • (2000) J. Constr. Eng. Manag. , vol.126 , Issue.4 , pp. 251-260
    • Koo, B.1    Fisher, M.2
  • 3
    • 0742285899 scopus 로고    scopus 로고
    • Virtual building for construction projects
    • L.M. Sheppard Virtual building for construction projects IEEE Comput. Graph. Appl. 24 1 2004 6 12
    • (2004) IEEE Comput. Graph. Appl. , vol.24 , Issue.1 , pp. 6-12
    • Sheppard, L.M.1
  • 4
    • 10444242643 scopus 로고    scopus 로고
    • Moving beyond the fourth dimension with an IFC-based single project
    • A.M. Tanyer, and G. Aouad Moving beyond the fourth dimension with an IFC-based single project Autom. Constr. 14 1 2005 15 32
    • (2005) Autom. Constr. , vol.14 , Issue.1 , pp. 15-32
    • Tanyer, A.M.1    Aouad, G.2
  • 5
    • 70350060197 scopus 로고    scopus 로고
    • Visualization of construction progress monitoring with 4D simulation model overlaid on time-lapsed photographs
    • M. Golparvar-Fard, F. Peña-Mora, C.A. Arboleda, and S. Lee Visualization of construction progress monitoring with 4D simulation model overlaid on time-lapsed photographs J. Comput. Civ. Eng. 23 6 2009 391 404
    • (2009) J. Comput. Civ. Eng. , vol.23 , Issue.6 , pp. 391-404
    • Golparvar-Fard, M.1    Peña-Mora, F.2    Arboleda, C.A.3    Lee, S.4
  • 6
    • 76549114928 scopus 로고    scopus 로고
    • An evaluation of the applicability of 4D CAD on construction projects
    • A. Mahalingam, R. Kashyap, and C. Mahajan An evaluation of the applicability of 4D CAD on construction projects Autom. Constr. 19 2010 148 159
    • (2010) Autom. Constr. , vol.19 , pp. 148-159
    • Mahalingam, A.1    Kashyap, R.2    Mahajan, C.3
  • 7
    • 79551684087 scopus 로고    scopus 로고
    • BIM- and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies
    • J.P. Zhang, and Z.Z. Hu BIM- and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies Autom. Constr. 20 2011 155 166
    • (2011) Autom. Constr. , vol.20 , pp. 155-166
    • Zhang, J.P.1    Hu, Z.Z.2
  • 8
    • 77949485153 scopus 로고    scopus 로고
    • The use of a virtual building design and construction model for developing an effective project concept in 5D environment
    • V. Popov, V. Juocevicius, D. Migilinskas, L. Ustinovichius, and S. Mikalauskas The use of a virtual building design and construction model for developing an effective project concept in 5D environment Autom. Constr. 19 1 2010 66 72
    • (2010) Autom. Constr. , vol.19 , Issue.1 , pp. 66-72
    • Popov, V.1    Juocevicius, V.2    Migilinskas, D.3    Ustinovichius, L.4    Mikalauskas, S.5
  • 9
    • 77949484698 scopus 로고    scopus 로고
    • Using the MD CAS model to develop the time-cost integrated schedule for construction projects
    • C.W. Feng, Y.J. Chen, and J.R. Huang Using the MD CAS model to develop the time-cost integrated schedule for construction projects Autom. Constr. 19 2010 347 356
    • (2010) Autom. Constr. , vol.19 , pp. 347-356
    • Feng, C.W.1    Chen, Y.J.2    Huang, J.R.3
  • 12
    • 65449170044 scopus 로고    scopus 로고
    • Integration of four-dimensional computer-aided design modeling and three-dimensional animation of operations simulation for visualizing construction of the main stadium for the Beijing 2008 Olympic games
    • M. Lu, Y. Zhang, J.P. Zhang, Z.Z. Hu, and J.L. Li Integration of four-dimensional computer-aided design modeling and three-dimensional animation of operations simulation for visualizing construction of the main stadium for the Beijing 2008 Olympic games Can. J. Civ. Eng. 36 3 2009 473 479
    • (2009) Can. J. Civ. Eng. , vol.36 , Issue.3 , pp. 473-479
    • Lu, M.1    Zhang, Y.2    Zhang, J.P.3    Hu, Z.Z.4    Li, J.L.5
  • 14
    • 77957259807 scopus 로고    scopus 로고
    • A three-stage framework for introducing a 4D tool in large consulting firms
    • M.H. Tsai, S.C. Kang, and S.H. Hsieh A three-stage framework for introducing a 4D tool in large consulting firms Adv. Eng. Inform. 24 2010 476 489
    • (2010) Adv. Eng. Inform. , vol.24 , pp. 476-489
    • Tsai, M.H.1    Kang, S.C.2    Hsieh, S.H.3
  • 17
    • 13244275240 scopus 로고    scopus 로고
    • Application of 4D for dynamic site layout and management of construction projects
    • DOI 10.1016/j.autcon.2004.08.011, PII S0926580504001104, International Conference for Construction Information Technology
    • Z. Ma, Q. Shen, and J. Zhang Application of 4D for dynamic site layout and management of construction projects Autom. Constr. 14 3 2005 369 381 (Pubitemid 40183428)
    • (2005) Automation in Construction , vol.14 , Issue.3 , pp. 369-381
    • Ma, Z.1    Shen, Q.2    Zhang, J.3
  • 18
    • 33746364173 scopus 로고    scopus 로고
    • Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualisation
    • DOI 10.1016/j.autcon.2005.08.005, PII S092658050500124X
    • Z. Mallasi Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualization Autom. Constr. 15 2006 640 655 (Pubitemid 44118734)
    • (2006) Automation in Construction , vol.15 , Issue.5 , pp. 640-655
    • Mallasi, Z.1
  • 19
    • 3142565144 scopus 로고    scopus 로고
    • 4D dynamic management for construction planning and resource utilization
    • H.J. Wang, J.P. Zhang, K.W. Chau, and M. Anson 4D dynamic management for construction planning and resource utilization Autom. Constr. 13 5 2004 575 589
    • (2004) Autom. Constr. , vol.13 , Issue.5 , pp. 575-589
    • Wang, H.J.1    Zhang, J.P.2    Chau, K.W.3    Anson, M.4
  • 20
    • 75149127614 scopus 로고    scopus 로고
    • An integrated safety management with construction management
    • V. Benjaoran, and S. Bhokha An integrated safety management with construction management Autom. Constr. 48 2010 395 403
    • (2010) Autom. Constr. , vol.48 , pp. 395-403
    • Benjaoran, V.1    Bhokha, S.2
  • 23
    • 0034322953 scopus 로고    scopus 로고
    • Simplifying simulation modeling through integration with 3D CAD
    • DOI 10.1061/(ASCE)0733-9364(2000)126:6(475)
    • S. AbouRizk, and K. Mather Simplifying simulation modeling through integration with 3D CAD J. Constr. Eng. Manag. 126 6 2000 475 483 (Pubitemid 32022001)
    • (2000) Journal of Construction Engineering and Management , vol.126 , Issue.6 , pp. 475-483
    • AbouRizk, S.1    Mather, K.2
  • 27
  • 28
    • 34848867519 scopus 로고    scopus 로고
    • Generic representation of 3D motion paths in dynamic animations of simulated construction processes
    • DOI 10.1016/j.autcon.2007.04.002, PII S092658050700060X
    • V.R. Kamat, and J.C. Martinez Generic representation of 3D motion paths in dynamic animations of simulated construction processes Autom. Constr. 12 2008 188 200 (Pubitemid 47489769)
    • (2008) Automation in Construction , vol.17 , Issue.2 , pp. 188-200
    • Kamat, V.R.1    Martinez, J.C.2
  • 29
    • 70350060196 scopus 로고    scopus 로고
    • Three-dimensional simulation and visualization of crane-assisted construction erection processes
    • S.C. Kang, H.L. Chi, and E. Miranda Three-dimensional simulation and visualization of crane-assisted construction erection processes J. Comput. Civ. Eng. 23 6 2009 363 371
    • (2009) J. Comput. Civ. Eng. , vol.23 , Issue.6 , pp. 363-371
    • Kang, S.C.1    Chi, H.L.2    Miranda, E.3
  • 30
    • 58849155935 scopus 로고    scopus 로고
    • A new 4D management approach to construction planning and site space utilization
    • J.P. Zhang, M. Anson, and Q. Wang A new 4D management approach to construction planning and site space utilization Proceedings of the 8th International Conference on Computing in Civil and Building Engineering (ICCCBE-VIII) 2000 Stanford 15 22 (Pubitemid 35213164)
    • (2000) Computing in Civil and Building Engineering , vol.1 , pp. 15-22
    • Zhang, J.-P.1    Anson, M.2    Wang, Q.3
  • 31
    • 6344232286 scopus 로고    scopus 로고
    • Simplified discrete-event simulation approach for construction simulation
    • DOI 10.1061/(ASCE)0733-9364(2003)129:5(537)
    • M. Lu Simplified discrete-event simulation approach for construction simulation J. Constr. Eng. Manag. 129 5 2003 537 546 (Pubitemid 40265441)
    • (2003) Journal of Construction Engineering and Management , vol.129 , Issue.5 , pp. 537-546
    • Lu, M.1
  • 32
    • 35348876020 scopus 로고    scopus 로고
    • Generic process mapping and simulation methodology for integrating site layout and operations planning in construction
    • DOI 10.1061/(ASCE)0887-3801(2007)21:6(453)
    • M. Lu, W.H. Chan, J.P. Zhang, and M. Cao Generic process mapping and simulation methodology for integrating site layout and operations planning in construction J. Comput. Civ. Eng. 21 6 2007 453 462 (Pubitemid 47587962)
    • (2007) Journal of Computing in Civil Engineering , vol.21 , Issue.6 , pp. 453-462
    • Lu, M.1    Chan, W.-H.2    Zhang, J.-P.3    Cao, M.4
  • 33
    • 77957282618 scopus 로고    scopus 로고
    • Bridge construction schedule generation with pattern-based construction methods and constraint-based simulation
    • I.C. Wu, A. Borrmann, U. Beisert, M. König, and E. Rank Bridge construction schedule generation with pattern-based construction methods and constraint-based simulation Adv. Eng. Inform. 24 2010 379 388
    • (2010) Adv. Eng. Inform. , vol.24 , pp. 379-388
    • Wu, I.C.1    Borrmann, A.2    Beisert, U.3    König, M.4    Rank, E.5
  • 35
    • 79952306806 scopus 로고    scopus 로고
    • Discrete-event simulation based virtual reality environments for construction operations: A technology introduction
    • P.V. Rekapalli, and J.C. Martinez Discrete-event simulation based virtual reality environments for construction operations: a technology introduction J. Constr. Eng. Manag. 137 3 2011 214 224
    • (2011) J. Constr. Eng. Manag. , vol.137 , Issue.3 , pp. 214-224
    • Rekapalli, P.V.1    Martinez, J.C.2
  • 36
    • 79954462583 scopus 로고    scopus 로고
    • Integrated information modeling and visual simulation of engineering operations using dynamic augmented reality scene graphs
    • A.H. Behzadan, and V.R. Kamat Integrated information modeling and visual simulation of engineering operations using dynamic augmented reality scene graphs Electron. J. Inf. Technol. Constr. 16 2011 259 278
    • (2011) Electron. J. Inf. Technol. Constr. , vol.16 , pp. 259-278
    • Behzadan, A.H.1    Kamat, V.R.2
  • 37
    • 84878418673 scopus 로고    scopus 로고
    • 3D AR-based modeling for discrete-event simulation of transport operations in construction
    • H.M. Chen, and P.H. Huang 3D AR-based modeling for discrete-event simulation of transport operations in construction Autom. Constr. 33 2013 123 136
    • (2013) Autom. Constr. , vol.33 , pp. 123-136
    • Chen, H.M.1    Huang, P.H.2
  • 38
    • 84887835524 scopus 로고    scopus 로고
    • Computer Integrated Construction (cic) Research Program Pennsylvania State University PA, USA
    • CIC, Computer Integrated Construction (CIC) Research Program BIM Project Execution Planning Guide - Version 2.1 2011 Pennsylvania State University PA, USA
    • (2011) BIM Project Execution Planning Guide - Version 2.1
  • 39
    • 84887837595 scopus 로고    scopus 로고
    • Autodesk http://usa.autodesk.com/ 2012
    • (2012)
    • Autodesk1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.