Application of Weibull analysis to evaluate and forecast schedule performance in repetitive projects

Author keywords

Earned value method; Quantitative methods; Repetitive projects; Weibull analysis

Indexed keywords

BUDGET CONTROL; FORECASTING; NUMERICAL METHODS; PROBABILITY DISTRIBUTIONS; VALUE ENGINEERING; WEIBULL DISTRIBUTION;

EID: 84954535147     PISSN: 07339364     EISSN: None     Source Type: Journal    
DOI: 10.1061/(ASCE)CO.1943-7862.0001040     Document Type: Article
Times cited : (13)

References (28)
  • 1
    • 0026913088 scopus 로고
    • Statistical properties of construction duration data
    • AbouRizk, S. M., and, Halpin, D. W. (1992). " Statistical properties of construction duration data." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(1992)118:3(525), 525-544. JCEMD4 0733-9364
    • (1992) J. Constr. Eng. Manage. , pp. 525-544
    • AbouRizk, S.M.1    Halpin, D.W.2
  • 3
    • 84872708300 scopus 로고    scopus 로고
    • LOB and CPM integrated method for scheduling repetitive projects
    • Ammar, M. A. (2013). " LOB and CPM integrated method for scheduling repetitive projects." J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000569, 44-50. JCEMD4 0733-9364
    • (2013) J. Constr. Eng. Manage. , pp. 44-50
    • Ammar, M.A.1
  • 4
    • 33645957411 scopus 로고    scopus 로고
    • Earned value project management method and extensions
    • Anbari, F. T. (2003). " Earned value project management method and extensions." Project Manage. J., 34 (4), 12-23. 1938-9507
    • (2003) Project Manage. J. , vol.34 , Issue.4 , pp. 12-23
    • Anbari, F.T.1
  • 6
    • 0035132257 scopus 로고    scopus 로고
    • Optimizing resource utilization for repetitive construction projects
    • El-Rayes, K., and, Moselhi, O. (2001). " Optimizing resource utilization for repetitive construction projects." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2001)127:1(18), 18-27. JCEMD4 0733-9364
    • (2001) J. Constr. Eng. Manage. , pp. 18-27
    • El-Rayes, K.1    Moselhi, O.2
  • 8
    • 84875014117 scopus 로고    scopus 로고
    • Quantification of delay factors using the relative importance index method for construction projects in Turkey
    • Gündüz, M., Nielsen, Y., and, Özdemir, M. (2013). " Quantification of delay factors using the relative importance index method for construction projects in Turkey." J. Manage. Eng., 10.1061/(ASCE)ME.1943-5479.0000129, 133-139. JMENEA 0742-597X
    • (2013) J. Manage. Eng. , pp. 133-139
    • Gündüz, M.1    Nielsen, Y.2    Özdemir, M.3
  • 9
    • 33646584142 scopus 로고    scopus 로고
    • Optimal planning and scheduling for repetitive construction projects
    • Hyari, K., and, El-Rayes, K. (2006). " Optimal planning and scheduling for repetitive construction projects." J. Manage. Eng., 10.1061/(ASCE)0742-597X(2006)22:1(11), 11-19. JMENEA 0742-597X
    • (2006) J. Manage. Eng. , pp. 11-19
    • Hyari, K.1    El-Rayes, K.2
  • 10
    • 65249138825 scopus 로고    scopus 로고
    • Forecasting project schedule completion with earned value metrics
    • Jacob, D. (2003). " Forecasting project schedule completion with earned value metrics." The Measurable News, 7-9.
    • (2003) The Measurable News , pp. 7-9
    • Jacob, D.1
  • 12
    • 77955321825 scopus 로고    scopus 로고
    • Probabilistic forecasting of project duration using Kalman filter and the earned value method
    • Kim, B. C., and, Reinschmidt, K. F. (2010). " Probabilistic forecasting of project duration using Kalman filter and the earned value method." J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000192, 834-843. JCEMD4 0733-9364
    • (2010) J. Constr. Eng. Manage. , pp. 834-843
    • Kim, B.C.1    Reinschmidt, K.F.2
  • 14
    • 64449085007 scopus 로고    scopus 로고
    • Prediction of project outcome the application of statistical methods to earned value management and earned schedule performance indexes
    • Lipke, W., Zwikael, O., Henderson, K., and, Anbari, F. (2009). " Prediction of project outcome the application of statistical methods to earned value management and earned schedule performance indexes." Int. Project Manage., 27 (4), 400-407. 10.1016/j.ijproman.2008.02.009 IPMAEL
    • (2009) Int. Project Manage. , vol.27 , Issue.4 , pp. 400-407
    • Lipke, W.1    Zwikael, O.2    Henderson, K.3    Anbari, F.4
  • 15
    • 22744437020 scopus 로고    scopus 로고
    • Schedule is different
    • Lipke, W. H. (2003). " Schedule is different." The Measurable News, 31-34.
    • (2003) The Measurable News , pp. 31-34
    • Lipke, W.H.1
  • 17
    • 0001501655 scopus 로고
    • Application of a technique for research and development program evaluation
    • Malcolm, D. G., Roseboom, J. H., Clark, C. E., and, Fazar, W. (1959). " Application of a technique for research and development program evaluation." Oper. Res., 7 (5), 646-669. 10.1287/opre.7.5.646 OPREAI 0030-364X
    • (1959) Oper. Res. , vol.7 , Issue.5 , pp. 646-669
    • Malcolm, D.G.1    Roseboom, J.H.2    Clark, C.E.3    Fazar, W.4
  • 18
    • 84954537290 scopus 로고    scopus 로고
    • MATLAB version 8.1 (R2013a) [Computer software]. Natick, MA, MathWorks.
    • MATLAB version 8.1 (R2013a) [Computer software]. Natick, MA, MathWorks.
  • 19
    • 13944274914 scopus 로고    scopus 로고
    • Optimized scheduling of linear projects
    • Moselhi, O., and, Hassanein, A. (2003). " Optimized scheduling of linear projects." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2003)129:6(664), 664-673. JCEMD4 0733-9364
    • (2003) J. Constr. Eng. Manage. , pp. 664-673
    • Moselhi, O.1    Hassanein, A.2
  • 21
    • 29044442114 scopus 로고    scopus 로고
    • Using Weibull analysis for evaluation of cost and schedule performance
    • Nassar, K. M., Gunnarsson, H. G., and, Hegab, M. Y. (2005). " Using Weibull analysis for evaluation of cost and schedule performance." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2005)131:12(1257), 1257-1262. JCEMD4 0733-9364
    • (2005) J. Constr. Eng. Manage. , pp. 1257-1262
    • Nassar, K.M.1    Gunnarsson, H.G.2    Hegab, M.Y.3
  • 22
    • 0025447970 scopus 로고
    • RPM: Repetitive project modeling
    • Reda, R. (1990). " RPM: Repetitive project modeling." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(1990)116:2(316), 316-330. JCEMD4 0733-9364
    • (1990) J. Constr. Eng. Manage. , pp. 316-330
    • Reda, R.1
  • 23
    • 45749131796 scopus 로고    scopus 로고
    • Using Gaussian and hyperbolic distributions for quality improvement in construction: Case study approach
    • Tam, V., Le, K., and, Le, H. (2008). " Using Gaussian and hyperbolic distributions for quality improvement in construction: Case study approach." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2008)134:7(555), 555-561. JCEMD4 0733-9364
    • (2008) J. Constr. Eng. Manage. , pp. 555-561
    • Tam, V.1    Le, K.2    Le, H.3
  • 24
    • 0026881995 scopus 로고
    • Monte Carlo technique with correlated random variables
    • Touran, A., and, Wiser, E. (1992). " Monte Carlo technique with correlated random variables." J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(1992)118:2(258), 258-272. JCEMD4 0733-9364
    • (1992) J. Constr. Eng. Manage. , pp. 258-272
    • Touran, A.1    Wiser, E.2
  • 25
    • 33645967441 scopus 로고    scopus 로고
    • A comparison of different project duration forecasting methods using earned value metrics
    • Vandevoorde, S., and, Vanhoucke, M. (2006). " A comparison of different project duration forecasting methods using earned value metrics." Int. J. Project Manage., 24 (4), 289-302. 10.1016/j.ijproman.2005.10.004 IPMAEL
    • (2006) Int. J. Project Manage. , vol.24 , Issue.4 , pp. 289-302
    • Vandevoorde, S.1    Vanhoucke, M.2
  • 27
    • 27744569616 scopus 로고    scopus 로고
    • Stochastic resource-constrained scheduling for repetitive construction projects with uncertain supply of resources and funding
    • Yang, I., and, Chang, C. (2005). " Stochastic resource-constrained scheduling for repetitive construction projects with uncertain supply of resources and funding." Int. Project Manage., 23 (7), 546-553. 10.1016/j.ijproman.2005.03.003 IPMAEL
    • (2005) Int. Project Manage. , vol.23 , Issue.7 , pp. 546-553
    • Yang, I.1    Chang, C.2
  • 28
    • 9444236531 scopus 로고    scopus 로고
    • Evaluation of models for forecasting the final cost of a project
    • Zwikael, O., Globerson, S., and, Raz, T. (2000). " Evaluation of models for forecasting the final cost of a project." Project Manage. J., 31 (1), 53-57. 1938-9507
    • (2000) Project Manage. J. , vol.31 , Issue.1 , pp. 53-57
    • Zwikael, O.1    Globerson, S.2    Raz, T.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.