Volumn 29, Issue 2, 2013, Pages 133-139

Quantification of delay factors using the relative importance index method for construction projects in Turkey

Author keywords

Construction projects; Relative importance index method; Schedule delay

Indexed keywords

CONSTRUCTION DELAYS; CONSTRUCTION PROJECTS; CONTROL DELAY; DELAY FACTORS; IMPORTANCE INDEX; LITERATURE REVIEWS; PROJECT PERFORMANCE; SCHEDULE DELAY;

EID: 84875014117     PISSN: 0742597X     EISSN: None     Source Type: Journal    
DOI: 10.1061/(ASCE)ME.1943-5479.0000129     Document Type: Article
Times cited : (303)

References (27)
  • 1
    • 0033883312 scopus 로고    scopus 로고
    • Construction delay: A quantitative analysis
    • IPMAEL
    • Al-Momani, A. (2000). " Construction delay: A quantitative analysis." Int. J. Project Manage., 18 (1), 51-59. IPMAEL
    • (2000) Int. J. Project Manage. , vol.18 , Issue.1 , pp. 51-59
    • Al-Momani, A.1
  • 2
    • 0006865274 scopus 로고
    • Reasons for delays in public projects in Turkey
    • " 0144-6193 10.1080/01446198500000013
    • Arditi, R. D., Akan, G. T., and, Gurdamar, S. (1985). " Reasons for delays in public projects in Turkey." Constr. Manage. Econ., 3 (2), 171-181. 0144-6193 10.1080/01446198500000013
    • (1985) Constr. Manage. Econ. , vol.3 , Issue.2 , pp. 171-181
    • Arditi, R.D.1    Akan, G.T.2    Gurdamar, S.3
  • 3
    • 33645965860 scopus 로고    scopus 로고
    • Causes of delay in large construction projects
    • IPMAEL
    • Assaf, S. A., and, Al-Hejji, S. (2006). " Causes of delay in large construction projects." Int. J. Project Manage., 24 (4), 349-357. IPMAEL
    • (2006) Int. J. Project Manage. , vol.24 , Issue.4 , pp. 349-357
    • Assaf, S.A.1    Al-Hejji, S.2
  • 4
    • 84927635730 scopus 로고
    • Causes of delay in large building construction projects
    • " JMENEA 0742-597X 10.1061/(ASCE)0742-597X(1995)11:2(45)
    • Assaf, S. A., Al-Khalil, M., and, A-Hazmi, M. (1995). " Causes of delay in large building construction projects." J. Manage. Eng., 11 (2), 45-50. JMENEA 0742-597X 10.1061/(ASCE)0742-597X(1995)11:2(45)
    • (1995) J. Manage. Eng. , vol.11 , Issue.2 , pp. 45-50
    • Assaf, S.A.1    Al-Khalil, M.2    A-Hazmi, M.3
  • 5
    • 0015159159 scopus 로고
    • Causes of delay in the construction industry
    • JCCEAZ 0569-7948
    • Baldwin, J., and, Manthei, J. (1971). " Causes of delay in the construction industry." J. Constr. Div., 97 (2), 177-187. JCCEAZ 0569-7948
    • (1971) J. Constr. Div. , vol.97 , Issue.2 , pp. 177-187
    • Baldwin, J.1    Manthei, J.2
  • 6
    • 0031078243 scopus 로고    scopus 로고
    • A comparative study of causes of time delays in Hong Kong construction projects
    • IPMAEL
    • Chan, D. W., and, Kumaraswamy, M. M. (1997). " A comparative study of causes of time delays in Hong Kong construction projects." Int. J. Project Manage., 15 (1), 55-63. IPMAEL
    • (1997) Int. J. Project Manage. , vol.15 , Issue.1 , pp. 55-63
    • Chan, D.W.1    Kumaraswamy, M.M.2
  • 7
    • 34248366102 scopus 로고    scopus 로고
    • Using fuzzy risk assessment to rate cost overrun risk in international construction projects
    • " IPMAEL
    • Dikmen, I., Birgönül, M. T., and, Han, S. (2007). " Using fuzzy risk assessment to rate cost overrun risk in international construction projects." Int. J. Project Manage., 25 (5), 494-505. IPMAEL
    • (2007) Int. J. Project Manage. , vol.25 , Issue.5 , pp. 494-505
    • Dikmen, I.1    Birgönül, M.T.2    Han, S.3
  • 9
    • 54249100948 scopus 로고    scopus 로고
    • Causes of delay in building construction projects in Eygpt
    • "
    • El Razek, M. E., Basssioni, H. A., and, Mobarak, A. M. (2008). " Causes of delay in building construction projects in Eygpt." J. Constr. Eng. Manage., 134 (11), 831-841.
    • (2008) J. Constr. Eng. Manage. , vol.134 , Issue.11 , pp. 831-841
    • El Razek, M.E.1    Basssioni, H.A.2    Mobarak, A.M.3
  • 10
    • 0038721064 scopus 로고    scopus 로고
    • Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study
    • " IPMAEL
    • Frimpong, Y., Oluwoye, J., and, Crawford, L. (2003). " Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study." Int. J. Project Manage., 21 (5), 321-326. IPMAEL
    • (2003) Int. J. Project Manage. , vol.21 , Issue.5 , pp. 321-326
    • Frimpong, Y.1    Oluwoye, J.2    Crawford, L.3
  • 12
    • 0039997969 scopus 로고    scopus 로고
    • Factors influencing construction time and cost in Indonesia construction industry
    • " 0144-6193 10.1080/014461997373132
    • Kaming, P. F., Olomolaiye, P. O., Holt, G. D., and, Harris, F. C. (1997). " Factors influencing construction time and cost in Indonesia construction industry." Constr. Manage. Econ., 83-94. 0144-6193 10.1080/014461997373132
    • (1997) Constr. Manage. Econ. , pp. 83-94
    • Kaming, P.F.1    Olomolaiye, P.O.2    Holt, G.D.3    Harris, F.C.4
  • 13
    • 84948867627 scopus 로고
    • Attributes of UK construction clients influencing project consultants' performance
    • " 0144-6193 10.1080/01446199400000053
    • Kometa, S. T., Olomolaiye, P. O., and, Harris, F. C. (1994). " Attributes of UK construction clients influencing project consultants' performance." Constr. Manage. Econ., 12 (5), 433-443. 0144-6193 10.1080/01446199400000053
    • (1994) Constr. Manage. Econ. , vol.12 , Issue.5 , pp. 433-443
    • Kometa, S.T.1    Olomolaiye, P.O.2    Harris, F.C.3
  • 14
    • 16444365584 scopus 로고    scopus 로고
    • Delays and cost increase in the construction of private residential projects in Kuwait
    • " 0144-6193 10.1080/0144619042000326710
    • Koushki, P. A., Al-Rashid, K., and, Kartam, N. (2005). " Delays and cost increase in the construction of private residential projects in Kuwait." Constr. Manage. Econ., 23 (3), 285-294. 0144-6193 10.1080/0144619042000326710
    • (2005) Constr. Manage. Econ. , vol.23 , Issue.3 , pp. 285-294
    • Koushki, P.A.1    Al-Rashid, K.2    Kartam, N.3
  • 15
    • 3342970967 scopus 로고    scopus 로고
    • Large construction projects in developing countries: A case study from Vietnam
    • " IPMAEL
    • Long, D. N., and, Ogunlana, S. O., Quang, T., and, Lam, K. C. (2004). " Large construction projects in developing countries: A case study from Vietnam." Int. J. Project Manage., 22 (7), 553-561. IPMAEL
    • (2004) Int. J. Project Manage. , vol.22 , Issue.7 , pp. 553-561
    • Long, D.N.1    Ogunlana, S.O.2    Quang, T.3    Lam, K.C.4
  • 16
    • 56749181092 scopus 로고    scopus 로고
    • Quantifying schedule risk in construction projects using Bayesian belief networks
    • " IPMAEL
    • Luu, V., Kim, S., Van Tuan, N., and, Ogunlana, S. (2009). " Quantifying schedule risk in construction projects using Bayesian belief networks." Int. J. Project Manage., 27 (1), 39-50. IPMAEL
    • (2009) Int. J. Project Manage. , vol.27 , Issue.1 , pp. 39-50
    • Luu, V.1    Kim, S.2    Van Tuan, N.3    Ogunlana, S.4
  • 18
    • 0032072617 scopus 로고    scopus 로고
    • Factors of non-excusable delays that influence contractors' performance
    • JMENEA 0742-597X 10.1061/(ASCE)0742-597X(1998)14:3(42)
    • Majid, M. Z., and, McCaffer, R. (1998). " Factors of non-excusable delays that influence contractors' performance." J. Manage. Eng., 14 (3), 42-49. JMENEA 0742-597X 10.1061/(ASCE)0742-597X(1998)14:3(42)
    • (1998) J. Manage. Eng. , vol.14 , Issue.3 , pp. 42-49
    • Majid, M.Z.1    McCaffer, R.2
  • 19
    • 0000725583 scopus 로고
    • Causes of delay and cost overruns in Nigerian construction projects
    • " IPMAEL
    • Mansfield, N. R., Ugwu, O. O., and, Doran, T. (1994). " Causes of delay and cost overruns in Nigerian construction projects." Int. J. Project Manage., 12 (4), 254-260. IPMAEL
    • (1994) Int. J. Project Manage. , vol.12 , Issue.4 , pp. 254-260
    • Mansfield, N.R.1    Ugwu, O.O.2    Doran, T.3
  • 20
    • 84992957706 scopus 로고    scopus 로고
    • Causes of delays in the construction industry in Lebanon
    • 0969-9988 10.1108/eb021079
    • Mezher, T. M., and, Tawil, W. (1998). " Causes of delays in the construction industry in Lebanon." Eng. Constr. Archit. Manage., 5 (3), 251-260. 0969-9988 10.1108/eb021079
    • (1998) Eng. Constr. Archit. Manage. , vol.5 , Issue.3 , pp. 251-260
    • Mezher, T.M.1    Tawil, W.2
  • 21
    • 0036132474 scopus 로고    scopus 로고
    • Causes of construction delay: Traditional contracts
    • IPMAEL
    • Odeh, A. M., and, Battaineh, H. T. (2002). " Causes of construction delay: Traditional contracts." Int. J. Project Manage., 20 (1), 67-73. IPMAEL
    • (2002) Int. J. Project Manage. , vol.20 , Issue.1 , pp. 67-73
    • Odeh, A.M.1    Battaineh, H.T.2
  • 22
    • 0030074893 scopus 로고    scopus 로고
    • Construction delays in a fast growing economy: Comparing Thailand with other economies
    • " IPMAEL
    • Ogunlana, S. O., Promkuntong, K., and, Jearkjirm, V. (1996). " Construction delays in a fast growing economy: Comparing Thailand with other economies." Int. J. Project Manage., 14 (1), 37-45. IPMAEL
    • (1996) Int. J. Project Manage. , vol.14 , Issue.1 , pp. 37-45
    • Ogunlana, S.O.1    Promkuntong, K.2    Jearkjirm, V.3
  • 24
    • 34248402903 scopus 로고    scopus 로고
    • Causes and effects of delays in Malaysian construction industry
    • IPMAEL
    • Sambasivan, M., and, Soon, Y. W. (2007). " Causes and effects of delays in Malaysian construction industry." Int. J. Project Manage., 25 (5), 517-526. IPMAEL
    • (2007) Int. J. Project Manage. , vol.25 , Issue.5 , pp. 517-526
    • Sambasivan, M.1    Soon, Y.W.2
  • 25
    • 13944264725 scopus 로고    scopus 로고
    • Constructability practices among construction contractors in Indonesia
    • JCEMD4 0733-9364 10.1061/(ASCE)0733-9364(2004)130:5(656)
    • Trigunarsyah, B. (2004). " Constructability practices among construction contractors in Indonesia." J. Constr. Eng. Manage., 130 (5), 656-665. JCEMD4 0733-9364 10.1061/(ASCE)0733-9364(2004)130:5(656)
    • (2004) J. Constr. Eng. Manage. , vol.130 , Issue.5 , pp. 656-665
    • Trigunarsyah, B.1
  • 26
    • 68649106829 scopus 로고
    • Master's thesis, Construction Engineering and Management Dept. King Fahd Univ. of Petroleum and Minerals, Dhahran, Saudi Arabia.
    • Ubaid, A. G. (1991). " Factors affecting contractor performance." Master's thesis, Construction Engineering and Management Dept., King Fahd Univ. of Petroleum and Minerals, Dhahran, Saudi Arabia.
    • (1991) Factors Affecting Contractor Performance
    • Ubaid, A.G.1
  • 27
    • 84861017618 scopus 로고    scopus 로고
    • Analyzing the risks affecting construction delay and cost overruns in Indonesia building projects
    • Vol. Rotterdam, The Netherlands.
    • Wiguna, I. P. A., and, Scott, S. (2005). " Analyzing the risks affecting construction delay and cost overruns in Indonesia building projects." Proc., of the 3rd Int. Conf. on Innovation in Architecture, Engineering and Construction, Vol. 3, Rotterdam, The Netherlands, 841-849.
    • (2005) Proc. of the 3rd Int. Conf. on Innovation in Architecture, Engineering and Construction , vol.3 , pp. 841-849
    • Wiguna, I.P.A.1    Scott, S.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.