Volumn 29, Issue 5, 2011, Pages 537-546

Developing risk breakdown structure for information technology organizations

Author keywords

Clustering; Content analysis; Lessons learned; Project management; Risk breakdown structure; Risk management

Indexed keywords

BREAKDOWN STRUCTURES; CLUSTERING; CONTENT ANALYSIS; HIERARCHICAL STRUCTURES; IT ORGANIZATIONS; LESSONS LEARNED; MANAGEMENT METHOD; METHOD OF ANALYSIS; POTENTIAL RISKS; PRODUCT DESCRIPTIONS; PRODUCTION REQUIREMENTS; RISK AREAS; RISK IDENTIFICATION;

EID: 79955943686     PISSN: 02637863     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijproman.2010.05.002     Document Type: Article
Times cited : (40)

References (53)
  • 3
    • 84986146417 scopus 로고    scopus 로고
    • A framework for integrated risk management in information technology
    • Bandyopadhyay K., Mykytyn P.P., Mykytyn K. A framework for integrated risk management in information technology. Management Decision 1999, 37(5):437-444.
    • (1999) Management Decision , vol.37 , Issue.5 , pp. 437-444
    • Bandyopadhyay, K.1    Mykytyn, P.P.2    Mykytyn, K.3
  • 5
    • 0025791156 scopus 로고
    • Software risk management: principles and practices
    • Boehm B.W. Software risk management: principles and practices. IEEE Software 1991, 8(1):32-41.
    • (1991) IEEE Software , vol.8 , Issue.1 , pp. 32-41
    • Boehm, B.W.1
  • 8
    • 0035313962 scopus 로고    scopus 로고
    • The controlling influences on effective risk identification and assessment for construction design management
    • Chapman C.B. The controlling influences on effective risk identification and assessment for construction design management. International Journal of Project Management 2001, 19(3):147-160.
    • (2001) International Journal of Project Management , vol.19 , Issue.3 , pp. 147-160
    • Chapman, C.B.1
  • 12
    • 24944518989 scopus 로고    scopus 로고
    • Formalized risk management: vital tool for project- and business-success
    • Cook P. Formalized risk management: vital tool for project- and business-success. Cost Engineering 2005, 47(8):12-13.
    • (2005) Cost Engineering , vol.47 , Issue.8 , pp. 12-13
    • Cook, P.1
  • 14
    • 77952584858 scopus 로고    scopus 로고
    • Does risk management contribute to IT project success? A met-analysis of empirical evidence
    • De Bakker K., Boonstra A., Wortmann H. Does risk management contribute to IT project success? A met-analysis of empirical evidence. International Journal of Project Management 2010, 28(5):493-503.
    • (2010) International Journal of Project Management , vol.28 , Issue.5 , pp. 493-503
    • De Bakker, K.1    Boonstra, A.2    Wortmann, H.3
  • 15
    • 0242662989 scopus 로고    scopus 로고
    • Project risk management: a combined analytic hierarchy process and decision tree approach
    • Dey P.K. Project risk management: a combined analytic hierarchy process and decision tree approach. Cost Engineering 2002, 44(3):13-26.
    • (2002) Cost Engineering , vol.44 , Issue.3 , pp. 13-26
    • Dey, P.K.1
  • 18
    • 0028428854 scopus 로고
    • Risk management for software projects
    • Fairley R. Risk management for software projects. IEEE Software 1994, 11(3):57-67.
    • (1994) IEEE Software , vol.11 , Issue.3 , pp. 57-67
    • Fairley, R.1
  • 19
    • 31344481667 scopus 로고    scopus 로고
    • Content analysis
    • Sage Pub, Beverly Hills, CA, B. Alan, H. Melissa (Eds.)
    • Franzosi R. Content analysis. Handbook of Data Analysis 2004, 547-566. Sage Pub, Beverly Hills, CA. B. Alan, H. Melissa (Eds.).
    • (2004) Handbook of Data Analysis , pp. 547-566
    • Franzosi, R.1
  • 20
    • 9144269130 scopus 로고    scopus 로고
    • Adaptive topological tree structure for document organization and visualization
    • Freeman R.T., Yin H. Adaptive topological tree structure for document organization and visualization. Neural Networks 2004, 17:1255-1271.
    • (2004) Neural Networks , vol.17 , pp. 1255-1271
    • Freeman, R.T.1    Yin, H.2
  • 21
    • 34250173088 scopus 로고    scopus 로고
    • Investigating diversity of clustering methods: an empirical comparison
    • Gelbard R., Goldman O., Spiegler I. Investigating diversity of clustering methods: an empirical comparison. Data & Knowledge Engineering 2007, 63(1):155-166.
    • (2007) Data & Knowledge Engineering , vol.63 , Issue.1 , pp. 155-166
    • Gelbard, R.1    Goldman, O.2    Spiegler, I.3
  • 22
    • 33645591548 scopus 로고    scopus 로고
    • Universal Risk Project - Final Report
    • available at the PMI Risk SIG website: .
    • Hall D.C., Hulett D.T., 2002. Universal Risk Project - Final Report. available at the PMI Risk SIG website: http://www.risksig.com.
    • (2002)
    • Hall, D.C.1    Hulett, D.T.2
  • 23
    • 33751003478 scopus 로고    scopus 로고
    • An empirical analysis of risk components and performance on software projects
    • Han W.M., Huang S.J. An empirical analysis of risk components and performance on software projects. The Journal of Systems and Software 2006, 80(1):42-50.
    • (2006) The Journal of Systems and Software , vol.80 , Issue.1 , pp. 42-50
    • Han, W.M.1    Huang, S.J.2
  • 26
    • 85007163464 scopus 로고    scopus 로고
    • Using a risk breakdown structure in project management
    • Hillson D. Using a risk breakdown structure in project management. Journal of Facilities management 2003, 2(1):85-97.
    • (2003) Journal of Facilities management , vol.2 , Issue.1 , pp. 85-97
    • Hillson, D.1
  • 36
    • 24744451624 scopus 로고    scopus 로고
    • A new paradigm for risk analysis
    • Macgill S.M., Siu Y.L. A new paradigm for risk analysis. Futures 2005, 37:1105-1131.
    • (2005) Futures , vol.37 , pp. 1105-1131
    • Macgill, S.M.1    Siu, Y.L.2
  • 37
    • 74549178599 scopus 로고    scopus 로고
    • Profiling enterprise risks in large computer companies using the Leximancer software tool
    • Martin N.J., Rice J.L. Profiling enterprise risks in large computer companies using the Leximancer software tool. Risk Management 2007, 9:188-206.
    • (2007) Risk Management , vol.9 , pp. 188-206
    • Martin, N.J.1    Rice, J.L.2
  • 38
    • 0035501151 scopus 로고    scopus 로고
    • Understanding and managing risks in large engineering projects
    • Miller R., Lessard D. Understanding and managing risks in large engineering projects. International Journal of Project Management 2001, 19(8):437-443.
    • (2001) International Journal of Project Management , vol.19 , Issue.8 , pp. 437-443
    • Miller, R.1    Lessard, D.2
  • 40
    • 31844439633 scopus 로고    scopus 로고
    • Risk management for pharmaceutical project schedules
    • Nalewaik A. Risk management for pharmaceutical project schedules. AACE International Transactions. Risk 2005, 07:71-75.
    • (2005) AACE International Transactions. Risk , vol.7 , pp. 71-75
    • Nalewaik, A.1
  • 41
    • 19744376660 scopus 로고    scopus 로고
    • Managing corporate risk through better knowledge management
    • Neef D. Managing corporate risk through better knowledge management. The Learning Organization 2005, 12(2):112-124.
    • (2005) The Learning Organization , vol.12 , Issue.2 , pp. 112-124
    • Neef, D.1
  • 43
    • 58049139009 scopus 로고    scopus 로고
    • Project Management Institute, Newtown Square, PA, PMI (Project Management Institute) Standards Committee
    • PMI (Project Management Institute) Standards Committee A guide to the project management body of knowledge (PMBOK® Guide) 2008, Project Management Institute, Newtown Square, PA. 4th ed.
    • (2008) A guide to the project management body of knowledge (PMBOK® Guide)
  • 45
    • 0036522380 scopus 로고    scopus 로고
    • Risk management, project success, and technological uncertainty
    • Raz T., Shenhar A.J., Dvir D. Risk management, project success, and technological uncertainty. R&D Management 2002, 32(2):101-110.
    • (2002) R&D Management , vol.32 , Issue.2 , pp. 101-110
    • Raz, T.1    Shenhar, A.J.2    Dvir, D.3
  • 46
    • 42149128329 scopus 로고    scopus 로고
    • Managing knowledge and learning in IT projects: a conceptual framework and guidelines for practice
    • Reich B.H. Managing knowledge and learning in IT projects: a conceptual framework and guidelines for practice. Project Management Journal 2007, 38(2):5-17.
    • (2007) Project Management Journal , vol.38 , Issue.2 , pp. 5-17
    • Reich, B.H.1
  • 48
    • 0037411136 scopus 로고    scopus 로고
    • Technology and knowledge: bridging a 'generating' gap
    • Spiegler I. Technology and knowledge: bridging a 'generating' gap. Information & Management 2003, 40(6):533-539.
    • (2003) Information & Management , vol.40 , Issue.6 , pp. 533-539
    • Spiegler, I.1
  • 49
    • 0035476223 scopus 로고    scopus 로고
    • Towards a framework for project risk knowledge management in the construction supply chain
    • Tah J.H.M., Carr V. Towards a framework for project risk knowledge management in the construction supply chain. Advances in Engineering Software 2001, 32:835-846.
    • (2001) Advances in Engineering Software , vol.32 , pp. 835-846
    • Tah, J.H.M.1    Carr, V.2
  • 50
    • 15744400789 scopus 로고    scopus 로고
    • Risk identification-basic stage in risk management
    • Tchankova L. Risk identification-basic stage in risk management. Environmental Management and Health 2002, 13(2/3):290-297.
    • (2002) Environmental Management and Health , vol.13 , Issue.2-3 , pp. 290-297
    • Tchankova, L.1
  • 51
    • 0033177429 scopus 로고    scopus 로고
    • Applying a risk management process (RMP) to manage cost risk for an EHV transmission line project
    • Tummala V.M.R., Burchett J.F. Applying a risk management process (RMP) to manage cost risk for an EHV transmission line project. International Journal of Project Management 1999, 17(4):223-235.
    • (1999) International Journal of Project Management , vol.17 , Issue.4 , pp. 223-235
    • Tummala, V.M.R.1    Burchett, J.F.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.