Volumn 213, Issue 1, 2011, Pages 66-72

Two-machine flow shop scheduling problem with an outsourcing option

Author keywords

Computational complexity; Ordered flow shop; Outsourcing; Scheduling

Indexed keywords

CHARACTERISTIC VALUE; FLOW SHOP PROBLEMS; FLOW SHOP SCHEDULING PROBLEM; IN-HOUSE SYSTEMS; MAKESPAN; NP-HARD; OPTIMALITY CONDITIONS; ORDERED FLOW SHOP; POLYNOMIAL-TIME ALGORITHMS; SET-UP TIME;

EID: 79955614863     PISSN: 03772217     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ejor.2011.03.017     Document Type: Article
Times cited : (40)

References (26)
  • 2
    • 0030270129 scopus 로고    scopus 로고
    • Two-machine proportionate flowshop scheduling with breakdown to minimize maximum lateness
    • A. Allahverdi Two-machine proportionate flowshop scheduling with breakdown to minimize maximum lateness Computers and Operations Research 23 1996 909 916
    • (1996) Computers and Operations Research , vol.23 , pp. 909-916
    • Allahverdi, A.1
  • 4
    • 0036815272 scopus 로고    scopus 로고
    • Competition and outsourcing with scale economies
    • G.P. Cachon, and P.T. Harker Competition and outsourcing with scale economies Management Science 48 2002 1314 1333 (Pubitemid 35427816)
    • (2002) Management Science , vol.48 , Issue.10 , pp. 1314-1333
    • Cachon, G.P.1    Harker, P.T.2
  • 5
    • 55049137385 scopus 로고    scopus 로고
    • Scheduling with subcontracting options
    • Z.L. Chen, and C.L. Li Scheduling with subcontracting options IIE Transactions 40 2008 1171 1184
    • (2008) IIE Transactions , vol.40 , pp. 1171-1184
    • Chen, Z.L.1    Li, C.L.2
  • 7
    • 83555172646 scopus 로고    scopus 로고
    • Minimizing makespan in an ordered flow shop with machine-dependent processing times
    • press doi:10.1007/s10878-010-9330-x
    • Choi, B.C.; Leung, J.Y.T.; Pinedo, M.L.; in press. Minimizing makespan in an ordered flow shop with machine-dependent processing times. Journal of Combinatorial Optimization. doi:10.1007/s10878-010-9330-x.
    • Journal of Combinatorial Optimization
    • Choi, B.C.1    Leung, J.Y.T.2    Pinedo, M.L.3
  • 8
    • 33749558671 scopus 로고    scopus 로고
    • Minimizing maximum completion time in a proportionate flow shop with one machine of different speed
    • B.C. Choi, S.H. Yoon, and S.J. Chung Minimizing maximum completion time in a proportionate flow shop with one machine of different speed European Journal of Operational Research 176 2007 964 974
    • (2007) European Journal of Operational Research , vol.176 , pp. 964-974
    • Choi, B.C.1    Yoon, S.H.2    Chung, S.J.3
  • 9
    • 26044467346 scopus 로고    scopus 로고
    • A new approach to job shop scheduling problems with due date constraints considering operation subcontracts
    • DOI 10.1016/j.ijpe.2004.05.023, PII S0925527305000149, Production Research: Facing the Challenges in the New Millenium
    • D. Chung, K. Lee, K. Shin, and J. Park A new approach to job shop scheduling problems with due date constraints considering operation subcontracts International Journal of Production Economics 98 2005 238 250 (Pubitemid 41406184)
    • (2005) International Journal of Production Economics , vol.98 , Issue.2 , pp. 238-250
    • Chung, D.1    Lee, K.2    Shin, K.3    Park, J.4
  • 12
    • 27844512878 scopus 로고    scopus 로고
    • Flowshop-scheduling problems with makespan criterion: A review
    • DOI 10.1080/0020754050056417
    • S.R. Hejazi, and S. Saghafian Flowshop-scheduling problems with makespan criterion: A review International Journal of Production Research 43 2005 2895 2929 (Pubitemid 41657440)
    • (2005) International Journal of Production Research , vol.43 , Issue.14 , pp. 2895-2929
    • Reza Hejazi, S.1    Saghafian, S.2
  • 13
    • 0037402799 scopus 로고    scopus 로고
    • The three-machine proportionate flow shop with unequal machine speeds
    • S. Hou, and H. Hoogeveen The three-machine proportionate flow shop with unequal machine speeds Operations Research Letters 31 2003 225 231
    • (2003) Operations Research Letters , vol.31 , pp. 225-231
    • Hou, S.1    Hoogeveen, H.2
  • 14
    • 0003075019 scopus 로고
    • Optimal two and three-stage production schedules with set-up times included
    • S.M. Johnson Optimal two and three-stage production schedules with set-up times included Naval Research Logistics Quarterly 1 1954 61 68
    • (1954) Naval Research Logistics Quarterly , vol.1 , pp. 61-68
    • Johnson, S.M.1
  • 16
    • 35548956964 scopus 로고    scopus 로고
    • Minimizing due date related measures for a single machine scheduling problem with outsourcing allowed
    • DOI 10.1016/j.ejor.2007.02.015, PII S0377221707002342
    • I.S. Lee, and C.S. Sung Minimizing due date related measures for a single machine scheduling problem with outsourcing allowed European Journal of Operational Research 186 2008 931 952 (Pubitemid 350016640)
    • (2008) European Journal of Operational Research , vol.186 , Issue.3 , pp. 931-952
    • Lee, I.S.1    Sung, C.S.2
  • 17
    • 37349027573 scopus 로고    scopus 로고
    • Single machine scheduling with outsourcing allowed
    • DOI 10.1016/j.ijpe.2007.02.036, PII S0925527307001053
    • I.S. Lee, and C.S. Sung Single machine scheduling with outsourcing allowed International Journal of Production Economics 101 2008 623 634 (Pubitemid 350299157)
    • (2008) International Journal of Production Economics , vol.111 , Issue.2 , pp. 623-634
    • Lee, I.S.1    Sung, C.S.2
  • 18
    • 0022093883 scopus 로고
    • Focused scheduling in proportionate flow shops
    • P.S. Ow Focused scheduling in proportionate flow shops Management Science 31 1985 852 869
    • (1985) Management Science , vol.31 , pp. 852-869
    • Ow, P.S.1
  • 19
    • 0016993158 scopus 로고
    • An ordered flow shop sequencing problem with mean completion time criterion
    • S.S. Panwalkar, and A.W. Khan An ordered flow shop sequencing problem with mean completion time criterion International Journal of Production Research 14 1976 631 635
    • (1976) International Journal of Production Research , vol.14 , pp. 631-635
    • Panwalkar, S.S.1    Khan, A.W.2
  • 21
    • 38149033826 scopus 로고    scopus 로고
    • Coordinated logistics scheduling for in-house production and outsourcing
    • X. Qi Coordinated logistics scheduling for in-house production and outsourcing IEEE Transactions on Automation Science and Engineering 5 2008 188 192
    • (2008) IEEE Transactions on Automation Science and Engineering , vol.5 , pp. 188-192
    • Qi, X.1
  • 22
    • 58149121493 scopus 로고    scopus 로고
    • Two-stage production scheduling with an option of outsourcing from a remote supplier
    • X. Qi Two-stage production scheduling with an option of outsourcing from a remote supplier Journal of System Science and System Engineering 18 2009 1 15
    • (2009) Journal of System Science and System Engineering , vol.18 , pp. 1-15
    • Qi, X.1
  • 23
    • 78649316983 scopus 로고    scopus 로고
    • Outsourcing and production scheduling for a two-stage flow shop
    • X. Qi Outsourcing and production scheduling for a two-stage flow shop International Journal of Production Economics 129 2011 43 50
    • (2011) International Journal of Production Economics , vol.129 , pp. 43-50
    • Qi, X.1
  • 24
    • 0000660478 scopus 로고
    • Flow shop sequencing problem with ordered processing time matrices
    • M.L. Smith, S.S. Panwalkar, and R.A. Dudek Flow shop sequencing problem with ordered processing time matrices Management Science 21 1975 544 549
    • (1975) Management Science , vol.21 , pp. 544-549
    • Smith, M.L.1    Panwalkar, S.S.2    Dudek, R.A.3
  • 25
    • 0017001721 scopus 로고
    • Flow shop sequencing problem with ordered processing time matrices: A general case
    • M.L. Smith, S.S. Panwalkar, and R.A. Dudek Flow shop sequencing problem with ordered processing time matrices: A general case Naval Research Logistics Quarterly 23 1976 481 486
    • (1976) Naval Research Logistics Quarterly , vol.23 , pp. 481-486
    • Smith, M.L.1    Panwalkar, S.S.2    Dudek, R.A.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.