Volumn 28, Issue 6, 2010, Pages 569-579

Evaluating schedule delay causes for private participating public construction works under the Build-Operate-Transfer model

Author keywords

BOT; Build Operate Transfer; Delay analysis; Public private partnership

Indexed keywords

BOT PROJECT; BUILD OPERATE TRANSFERS; CONSTRUCTION WORKS; POLITICAL ISSUES; PRIVATE INVESTMENT; PROJECT DELIVERY METHOD; PUBLIC PRIVATE PARTNERSHIPS; QUESTIONNAIRE SURVEYS; SCHEDULE DELAY; STRUCTURAL EQUATION MODELING METHOD;

EID: 77953356316     PISSN: 02637863     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijproman.2009.10.005     Document Type: Article
Times cited : (66)

References (26)
  • 2
    • 0032045573 scopus 로고    scopus 로고
    • The five commandments of construction project delay analysis
    • Al-Saggaf H.A. The five commandments of construction project delay analysis. Cost Engineering 1998, 40(4):37-41.
    • (1998) Cost Engineering , vol.40 , Issue.4 , pp. 37-41
    • Al-Saggaf, H.A.1
  • 3
    • 43849107963 scopus 로고    scopus 로고
    • BOT application in China: driving and impeding factors
    • Chen C., Doloi H. BOT application in China: driving and impeding factors. International Journal of Project Management 2008, 26(4):388-398.
    • (2008) International Journal of Project Management , vol.26 , Issue.4 , pp. 388-398
    • Chen, C.1    Doloi, H.2
  • 4
    • 77953357708 scopus 로고    scopus 로고
    • Federal Highway Administration, USDOT, A Final Report of Design-Build Effectiveness Study - as Required by TEA-21 Section 1307(f), Viewed 14 August 2009.
    • Federal Highway Administration, USDOT, 2006. A Final Report of Design-Build Effectiveness Study - as Required by TEA-21 Section 1307(f), Viewed 14 August 2009http://www.fhwa.dot.gov/reports/designbuild/designbuild.pdf.
    • (2006)
  • 5
  • 7
    • 0032072617 scopus 로고    scopus 로고
    • Factors of non excusable delays that influence contractors' performance
    • Majid M.Z.A., McCaffer R. Factors of non excusable delays that influence contractors' performance. Journal of Management in Engineering 1998, 14(3):42-49.
    • (1998) Journal of Management in Engineering , vol.14 , Issue.3 , pp. 42-49
    • Majid, M.Z.A.1    McCaffer, R.2
  • 9
    • 77953362724 scopus 로고    scopus 로고
    • National Council for Public-Private Partnerships, Keys to Successful Public-Private Partnerships, Viewed 21 April 2009.
    • National Council for Public-Private Partnerships, 2008. Keys to Successful Public-Private Partnerships, Viewed 21 April 2009http://www.ncppp.org/howpart/ppptypes.shtml.
    • (2008)
  • 12
    • 77953363587 scopus 로고    scopus 로고
    • Public Construction Commission, The Act for Promotion of Private Participation in Infrastructure Projects. The Executive Yuan, Taiwan, Viewed 14 August 2009.
    • Public Construction Commission, 2000. The Act for Promotion of Private Participation in Infrastructure Projects. The Executive Yuan, Taiwan, Viewed 14 August 2009http://ppp.pcc.gov.tw/pcc_site/english/EN-3.cfm.
    • (2000)
  • 13
    • 77953364059 scopus 로고    scopus 로고
    • Public Construction Commission, Reference Manuals of Schedule and Quality Management for Implementing BOT Projects (in Chinese). The Public Construction Commission, Executive Yuan, Taiwan, Viewed 14 August 2009.
    • Public Construction Commission, 2003. Reference Manuals of Schedule and Quality Management for Implementing BOT Projects (in Chinese). The Public Construction Commission, Executive Yuan, Taiwan, Viewed 14 August 2009http://www.pcc.gov.tw/pccap2/BIZSfront/upload/article/9214.exe.
    • (2003)
  • 14
    • 77953356760 scopus 로고    scopus 로고
    • Public Construction Commission, a. International Development Trend and Domestic Status of Promotion of Private Participation in Infrastructure Projects. Public Construction E-paper No. 9, Viewed 1 April 2009.
    • Public Construction Commission, 2009a. International Development Trend and Domestic Status of Promotion of Private Participation in Infrastructure Projects. Public Construction E-paper No. 9, Viewed 1 April 2009http://www.pcc.gov.tw/epaper/9804/face03.html.
    • (2009)
  • 15
    • 77953356510 scopus 로고    scopus 로고
    • Public Construction Commission, b. Promotion of Private Participation, Viewed 14 August 2009.
    • Public Construction Commission, 2009b. Promotion of Private Participation, Viewed 14 August 2009http://ppp.pcc.gov.tw/pcc_site/english/index.cfm.
    • (2009)
  • 16
    • 77953359055 scopus 로고    scopus 로고
    • Public Construction Commission, c. List of Signed PPP Projects (in Chinese), Viewed 14 August 2009.
    • Public Construction Commission, 2009c. List of Signed PPP Projects (in Chinese), Viewed 14 August 2009http://ppp.pcc.gov.tw/pcc_site/a4-0-1.cfml.
    • (2009)
  • 17
    • 77953359477 scopus 로고    scopus 로고
    • Scientific Software International Inc., LISREL 8.72 for Windows. Lincolnwood, IL, Viewed 14 August 2009.
    • Scientific Software International Inc., 2004. LISREL 8.72 for Windows. Lincolnwood, IL, Viewed 14 August 2009http://www.ssicentral.com/lisrel/.
    • (2004)
  • 18
    • 77953358533 scopus 로고    scopus 로고
    • SPSS Inc., SPSS Version 14.0 for Windows. Chicago, IL, Viewed 14 August 2009.
    • SPSS Inc., 2006. SPSS Version 14.0 for Windows. Chicago, IL, Viewed 14 August 2009http://www.spss.com/.
    • (2006)
  • 19
    • 0032711692 scopus 로고    scopus 로고
    • Build-operate-transfer model for infrastructure developments in Asia: reasons for successes and failures
    • Tam C.M. Build-operate-transfer model for infrastructure developments in Asia: reasons for successes and failures. International Journal of Project Management 1999, 17(6):377-382.
    • (1999) International Journal of Project Management , vol.17 , Issue.6 , pp. 377-382
    • Tam, C.M.1
  • 21
    • 85001576951 scopus 로고    scopus 로고
    • CSFs in competitive tendering and negotiation model for BOT projects
    • Tiong R.L.K. CSFs in competitive tendering and negotiation model for BOT projects. Journal of Construction Engineering and Management 1996, 122(3):205-211.
    • (1996) Journal of Construction Engineering and Management , vol.122 , Issue.3 , pp. 205-211
    • Tiong, R.L.K.1
  • 23
    • 77953357511 scopus 로고    scopus 로고
    • United States General Accounting Office, Public-Private Partnerships: Terms Related to Building and Facility Partnerships, Viewed 21 April 2009.
    • United States General Accounting Office, 1999. Public-Private Partnerships: Terms Related to Building and Facility Partnerships, Viewed 21 April 2009http://www.gao.gov/special.pubs/Gg99071.pdf.
    • (1999)
  • 25
    • 44649091201 scopus 로고    scopus 로고
    • Using structural equation modeling to analyze relationships among key causes of delay in construction
    • Yang J.B., Ou S.F. Using structural equation modeling to analyze relationships among key causes of delay in construction. Canadian Journal of Civil Engineering 2008, 35(4):321-332.
    • (2008) Canadian Journal of Civil Engineering , vol.35 , Issue.4 , pp. 321-332
    • Yang, J.B.1    Ou, S.F.2
  • 26
    • 41549093344 scopus 로고    scopus 로고
    • Identifying risk factors of BOT for water supply projects
    • Zeng S.X., Wan T.W., Tam C.M., Liu D. Identifying risk factors of BOT for water supply projects. Water Management 2008, 161(2):73-81.
    • (2008) Water Management , vol.161 , Issue.2 , pp. 73-81
    • Zeng, S.X.1    Wan, T.W.2    Tam, C.M.3    Liu, D.4


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.