Volumn 47, Issue 23, 2009, Pages 6651-6662

Productivity analysis in a robotic cell

Author keywords

Cellular manufacturing; Cycle time; Flow graph; Productivity analysis; Robotic cell; Simulation

Indexed keywords

CYCLE TIME; FLOW GRAPH; LOADING AND UNLOADING; PART SEQUENCING; PHYSICAL LOCATIONS; PROCESS TIME; PROCESSING TIME; PRODUCTIVITY ANALYSIS; ROBOTIC CELL; SINGLE PARTS; VIRTUAL ROBOTICS;

EID: 74549127532     PISSN: 00207543     EISSN: 1366588X     Source Type: Journal    
DOI: 10.1080/00207540802372298     Document Type: Article
Times cited : (21)

References (28)
  • 1
    • 0034315580 scopus 로고    scopus 로고
    • Part sequencing in three-machine no-wait robotic cells
    • Agnetis, A. and Pacciarelli, D., 2000. Part sequencing in three-machine no-wait robotic cells. Operations Research Letter, 27 (4), 185-192.
    • (2000) Operations Research Letter , vol.27 , Issue.4 , pp. 185-192
    • Agnetis, A.1    Pacciarelli, D.2
  • 2
    • 0032791011 scopus 로고    scopus 로고
    • Scheduling of parts and robot activities in a two machine robotic cell
    • Aneja, Y.P. and Kamoun, H., 1999. Scheduling of parts and robot activities in a two machine robotic cell. Computers & Operations Research, 26 (4), 297-312.
    • (1999) Computers & Operations Research , vol.26 , Issue.4 , pp. 297-312
    • Aneja, Y.P.1    Kamoun, H.2
  • 3
    • 0002804434 scopus 로고    scopus 로고
    • On a conjecture about robotic cells: New simplified proof for the three-machine case
    • Brauner, N. and Finke, G., 1999. On a conjecture about robotic cells: new simplified proof for the three-machine case. Journal of Information Systems and Operational Research, 37 (1), 20-36.
    • (1999) Journal of Information Systems and Operational Research , vol.37 , Issue.1 , pp. 20-36
    • Brauner, N.1    Finke, G.2
  • 4
    • 0035546060 scopus 로고    scopus 로고
    • Optimal moves of the material handling system in a robotic cell
    • Brauner, N. and Finke, G., 2001. Optimal moves of the material handling system in a robotic cell. International Journal of Production Economics, 74 (1-3), 269-277.
    • (2001) International Journal of Production Economics , vol.74 , Issue.1-3 , pp. 269-277
    • Brauner, N.1    Finke, G.2
  • 5
    • 0031272146 scopus 로고
    • Cycling scheduling of identical parts in a robotic cell
    • Crama, Y. and Klundert, J.V., 1994. Cycling scheduling of identical parts in a robotic cell. Operations Research, 45 (6), 952-965.
    • (1994) Operations Research , vol.45 , Issue.6 , pp. 952-965
    • Crama, Y.1    Klundert, J.V.2
  • 6
    • 0034367676 scopus 로고    scopus 로고
    • Cyclic scheduling in robotic flowshops
    • Crama, Y., et al., 2000. Cyclic scheduling in robotic flowshops. Annals of Operations Research,96 (1-4), 97-124.
    • (2000) Annals of Operations Research , vol.96 , Issue.1-4 , pp. 97-124
    • Crama, Y.1
  • 7
    • 0037448766 scopus 로고    scopus 로고
    • A polynomial algorithm for 2-degree cyclic robot scheduling
    • Che, A., Chu, C., and Levner, E., 2003. A polynomial algorithm for 2-degree cyclic robot scheduling. European Journal of Operational Research, 145 (1), 31-44.
    • (2003) European Journal of Operational Research , vol.145 , Issue.1 , pp. 31-44
    • Che, A.1    Chu, C.2    Levner, E.3
  • 8
    • 0030393177 scopus 로고    scopus 로고
    • Cyclic part schedule in a robotic cell
    • Man and Cybernetics, 14-17 October
    • Chen, H., Chu, C. and Proth, J., 1996. Cyclic part schedule in a robotic cell. In: IEEE International Conference on Systems, Man and Cybernetics, 14-17 October 2006, 4, 2928-2933.
    • (1996) IEEE International Conference on Systems , vol.4 , pp. 2928-2933
    • Chen, H.1    Chu, C.2    Proth, J.3
  • 11
    • 4043145060 scopus 로고    scopus 로고
    • Robotic cells with parallel machines: Throughput maximisation in constant travel-time cells
    • Geismar, H.N., Dawande, M., and Sriskandarajah, C., 2004. Robotic cells with parallel machines: throughput maximisation in constant travel-time cells. Journal of Scheduling, 7 (5), 375-395.
    • (2004) Journal of Scheduling , vol.7 , Issue.5 , pp. 375-395
    • Geismar, H.N.1    Dawande, M.2    Sriskandarajah, C.3
  • 12
    • 33845316803 scopus 로고    scopus 로고
    • A (10/7)-approximation algorithm for an optimum cyclic solution in additive travel-time robotic cells
    • Geismar, H.N., Dawande, M., and Sriskandarajah, C., 2007. A (10/7)-approximation algorithm for an optimum cyclic solution in additive travel-time robotic cells. IIE Transactions, 39 (2), 217-227.
    • (2007) IIE Transactions , vol.39 , Issue.2 , pp. 217-227
    • Geismar, H.N.1    Dawande, M.2    Sriskandarajah, C.3
  • 13
    • 33846053575 scopus 로고    scopus 로고
    • Scheduling in a two-machine robotic flexible manufacturing cell
    • Gultekin, H., Akturk, M.S., and Karasan, O.E., 2003. Scheduling in a two-machine robotic flexible manufacturing cell. Computers and Operations Research, 34 (8), 2463-2477.
    • (2003) Computers and Operations Research , vol.34 , Issue.8 , pp. 2463-2477
    • Gultekin, H.1    Akturk, M.S.2    Karasan, O.E.3
  • 14
    • 33746239040 scopus 로고    scopus 로고
    • Cyclic scheduling of a 2-machine robotic cell with tooling constraints
    • Gultekin, H., Akturk, M.S., and Karasan, O.E., 2006. Cyclic scheduling of a 2-machine robotic cell with tooling constraints. European Journal of Operational Research, 174 (2), 777-796.
    • (2006) European Journal of Operational Research , vol.174 , Issue.2 , pp. 777-796
    • Gultekin, H.1    Akturk, M.S.2    Karasan, O.E.3
  • 18
    • 0042829284 scopus 로고    scopus 로고
    • Combinatorial optimisation in real-time scheduling: Theory and algorithm
    • Hwang, S. and Cheng, S., 1998. Combinatorial optimisation in real-time scheduling: theory and algorithm. Journal of Combinatorial Optimisation, 5 (3), 345-375.
    • (1998) Journal of Combinatorial Optimisation , vol.5 , Issue.3 , pp. 345-375
    • Hwang, S.1    Cheng, S.2
  • 19
    • 0035418557 scopus 로고    scopus 로고
    • INFOR-Scheduling in Distributed and Cellular Systems Part 2
    • Ioachm, I., Sanlaville, E., and Lefebvre, M., 2001. The basic cyclic scheduling model for robotic flow-shops. INFOR-Scheduling in Distributed and Cellular Systems Part 2, 39 (3), 257-277.
    • (2001) , vol.39 , Issue.3 , pp. 257-277
    • Ioachm, I.1    Sanlaville, E.2    Lefebvre, M.3
  • 20
    • 15544391132 scopus 로고    scopus 로고
    • Stochastic fault tree analysis with self-loop basic events
    • Jenab, K. and Dhillon, B.S., 2005. Stochastic fault tree analysis with self-loop basic events. IEEE Transactions on Reliability, 54 (1), 173-180.
    • (2005) IEEE Transactions on Reliability , vol.54 , Issue.1 , pp. 173-180
    • Jenab, K.1    Dhillon, B.S.2
  • 21
    • 0033312656 scopus 로고
    • Scheduling in robotic cells: Heuristics and cell design
    • Kamoun, H., Hall, N., and Sriskandrajah, C., 1995. Scheduling in robotic cells: heuristics and cell design. Operations Research, 47 (6), 821-835.
    • (1995) Operations Research , vol.47 , Issue.6 , pp. 821-835
    • Kamoun, H.1    Hall, N.2    Sriskandrajah, C.3
  • 22
    • 0031540827 scopus 로고    scopus 로고
    • Minimising the number of robots to meet a given cyclic schedule
    • Kats, V. and Levner, E., 1997. Minimising the number of robots to meet a given cyclic schedule. Annals of Operations Research, 69 (1), 209-226.
    • (1997) Annals of Operations Research , vol.69 , Issue.1 , pp. 209-226
    • Kats, V.1    Levner, E.2
  • 23
    • 11844251167 scopus 로고    scopus 로고
    • Minimising cycle time in large robotic cells
    • Kumar, S., Ramanan, N., and Sriskandarajah, C., 2005. Minimising cycle time in large robotic cells. IIE Transactions, 37 (2), 123-136.
    • (2005) IIE Transactions , vol.37 , Issue.2 , pp. 123-136
    • Kumar, S.1    Ramanan, N.2    Sriskandarajah, C.3
  • 24
    • 0031492360 scopus 로고    scopus 로고
    • Current trends in deterministic scheduling
    • Lee, C., Lei, L., and Pinedo, M., 1997. Current trends in deterministic scheduling. Annals of Operations Research, 70 (1), 1-41.
    • (1997) Annals of Operations Research , vol.70 , Issue.1 , pp. 1-41
    • Lee, C.1    Lei, L.2    Pinedo, M.3
  • 25
    • 0027660753 scopus 로고
    • Dynamic sequence of robotic moves in manufacturing cell
    • Liu, S. and Lin, L., 1993. Dynamic sequence of robotic moves in manufacturing cell. European Journal of Operational Research, 69 (3), 482-497.
    • (1993) European Journal of Operational Research , vol.69 , Issue.3 , pp. 482-497
    • Liu, S.1    Lin, L.2
  • 26
    • 33750048735 scopus 로고    scopus 로고
    • Optimization of the product transfer with constraint in robotic cell using simulation
    • Masmoudi, F. and Maalej, Y.A., 2006. Optimization of the product transfer with constraint in robotic cell using simulation. International Journal of Simulation, 5, 89-100.
    • (2006) International Journal of Simulation , vol.5 , pp. 89-100
    • Masmoudi, F.1    Maalej, Y.A.2
  • 28
    • 9644286254 scopus 로고    scopus 로고
    • Scheduling multiple parts in a robotic cell served by a dual-gripper robot
    • Sriskandarajah, C., et al., 2004. Scheduling multiple parts in a robotic cell served by a dual-gripper robot. Operations Research, 52 (1), 65-82.
    • (2004) Operations Research , vol.52 , Issue.1 , pp. 65-82
    • Sriskandarajah, C.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.