Factors affecting the performance of Construction projects in the Gaza Strip

Author keywords

Consultants; Contractors; Owners; Performance; Projects

Indexed keywords

CONSTRUCTION PROJECTS; CONSULTANTS; GAZA STRIP; LEADERSHIP SKILLS; LITERATURE REVIEWS; LOW LEVEL; OWNERS; PALESTINE; PERFORMANCE; PROJECT LIFE CYCLE; PROJECT OWNERS; PROJECT PARTICIPANTS; PROJECT PERFORMANCE; PROJECTS; QUALIFIED PERSONNEL; RELATIVE IMPORTANCE;

EID: 70349589625     PISSN: 13923730     EISSN: None     Source Type: Journal    
DOI: 10.3846/1392-3730.2009.15.269-280     Document Type: Article
Times cited : (234)

References (33)
  • 2
    • 0033729893 scopus 로고    scopus 로고
    • Measuring the effect of project management on construction outputs: A new approach
    • Brown, A.; Adams, J. 2000. Measuring the effect of project management on construction outputs: a new approach, International Journal of Project Management 18: 327-335.
    • (2000) International Journal of Project Management , vol.18 , pp. 327-335
    • Brown, A.1    Adams, J.2
  • 3
    • 34447307395 scopus 로고    scopus 로고
    • A Benchmarking service for the evaluation and comparison of scheduling techniques
    • DOI 10.1016/j.compind.2007.05.004, PII S016636150700070X
    • (Pubitemid 47058183) Cavalieri, S.; Terzi, S.; Macchi, M. 2007. A benchmarking service for the evaluation and comparison of scheduling techniques, Computers in Industry 58: 656-666. doi:10.1016/j.compind.2007.05.004
    • (2007) Computers in Industry , vol.58 , Issue.7 , pp. 656-666
    • Cavalieri, S.1    Terzi, S.2    Macchi, M.3
  • 4
    • 0035040471 scopus 로고    scopus 로고
    • Time-cost relationship of public sector projects in Malaysia
    • doi:10.1016/S0263-7863 99 00072-1
    • Chan, A. P. C. 2001. Time-cost relationship of public sector projects in Malaysia, International Journal of Project Management 19: 223-229. doi:10.1016/S0263-7863 (99) 00072-1
    • (2001) International Journal of Project Management , vol.19 , pp. 223-229
    • Chan, A.P.C.1
  • 5
    • 0346911951 scopus 로고    scopus 로고
    • Developing a benchmark model for project construction time performance in Hong Kong
    • doi:10.1016/j.buildenv. 2003.08.012
    • Chan, A. P. C.; Chan, D. W. M. 2004. Developing a benchmark model for project construction time performance in Hong Kong, Building and Environment 39: 339-349. doi:10.1016/j.buildenv. 2003.08.012
    • (2004) Building and Environment , vol.39 , pp. 339-349
    • Chan, A.P.C.1    Chan, D.W.M.2
  • 6
    • 0036132114 scopus 로고    scopus 로고
    • Compressing construction durations: Lessons learned from Hong Kong building projects
    • doi:10.1016/S0263-7863 00 00032-6
    • Chan, D. W. M.; Kumaraswamy, M. M. 2002. Compressing construction durations: lessons learned from Hong Kong building projects, International Journal of Project Management 20: 23-35. doi:10.1016/S0263-7863 (00) 00032-6
    • (2002) International Journal of Project Management , vol.20 , pp. 23-35
    • Chan, D.W.M.1    Kumaraswamy, M.M.2
  • 7
    • 1642587217 scopus 로고    scopus 로고
    • PPMS: A web-based construction project performance monitoring system
    • doi:10.1016/j.autcon. 2003.12.001
    • Cheung, S.-O.; Suen, H. C. H.; Cheung, K. K. W. 2004. PPMS: a Web-based construction project performance monitoring system, Automation in Construction 13: 361-376. doi:10.1016/j.autcon. 2003.12.001
    • (2004) Automation in Construction , vol.13 , pp. 361-376
    • Cheung, S.-O.1    Suen, H.C.H.2    Cheung, K.K.W.3
  • 10
    • 34547232601 scopus 로고    scopus 로고
    • Performance evaluating model for construction companies: Egyptian case study
    • doi:10.1061/ASCE 0733-9364 2007 133:8 574
    • Elyamany, A.; Ismail, B.; Zayed, T. 2007. Performance evaluating model for construction companies: Egyptian case study, Journal of Construction Engineering and Management 133(8):574-581. doi:10.1061/(ASCE) 0733-9364 (2007) 133:8 (574)
    • (2007) Journal of Construction Engineering and Management , vol.133 , Issue.8 , pp. 574-581
    • Elyamany, A.1    Ismail, B.2    Zayed, T.3
  • 12
    • 33751295266 scopus 로고    scopus 로고
    • Significant factors causing delay in the UAE construction industry
    • DOI 10.1080/01446190600827033, PII X777131V25X87046
    • (Pubitemid 44794993) Faridi, A.; El-Sayegh, S. 2006. Significant factors causing delay in the UAE construction industry, Construction Management and Economics 24(11):1167-1176. doi:10.1080/01446190600827033
    • (2006) Construction Management and Economics , vol.24 , Issue.11 , pp. 1167-1176
    • Faridi, A.S.1    El-Sayegh, S.M.2
  • 13
    • 0038721064 scopus 로고    scopus 로고
    • Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
    • doi:10.1016/S0263-7863 02 00055-8
    • Frimpong Yaw; Oluwoye, J.; Crawford, L. 2003. Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study, International Journal of Project Management 21: 321-326. doi:10.1016/S0263-7863 (02) 00055-8
    • (2003) International Journal of Project Management , vol.21 , pp. 321-326
    • Yaw, F.1    Oluwoye, J.2    Crawford, L.3
  • 14
    • 70349594888 scopus 로고    scopus 로고
    • Causes of client dissatisfaction in the south African building industry and ways of improvement: The contractors' perspectives
    • South Africa
    • Hanson, D.; Mbachu, J.; Nkando, R. 2003. Causes of client dissatisfaction in the South African building industry and ways of improvement: the contractors' perspectives, in CIDB, South Africa.
    • (2003) CIDB
    • Hanson, D.1    Mbachu, J.2    Nkando, R.3
  • 15
    • 18144374111 scopus 로고    scopus 로고
    • Factors affecting cost performance: Evidence from Indian construction projects
    • doi:10.1016/j.ijproman. 2004.10.003
    • Iyer, K. C.; Jha, K. N. 2005. Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management 23: 283-295. doi:10.1016/j.ijproman. 2004.10.003
    • (2005) International Journal of Project Management , vol.23 , pp. 283-295
    • Iyer, K.C.1    Jha, K.N.2
  • 17
    • 1542493572 scopus 로고    scopus 로고
    • Project management actions to improve design phase cost performance
    • doi:10.1061/ASCE 0742-597X 2003 19:1 25
    • Kuprenas, J. A. 2003. Project management actions to improve design phase cost performance, Journal of Management in Engineering 19(1):25-32. doi:10.1061/(ASCE) 0742-597X (2003) 19:1 (25)
    • (2003) Journal of Management in Engineering , vol.19 , Issue.1 , pp. 25-32
    • Kuprenas, J.A.1
  • 19
    • 0035157687 scopus 로고    scopus 로고
    • Performance measurement in construction logistics
    • doi:10.1016/S0925-5273 00 00034-7
    • Lehtonen Tutu Wegelius. 2001. Performance measurement in construction logistics, International Journal of Production Economics 69: 107-116. doi:10.1016/S0925-5273 (00) 00034-7
    • (2001) International Journal of Production Economics , vol.69 , pp. 107-116
    • Wegelius, L.T.1
  • 20
    • 12744250283 scopus 로고    scopus 로고
    • Time-cost relationships in australian building construction projects
    • doi:10.1061/ASCE 0733-9364 2005 131:2 187
    • Love, P. E. D.; Tse, R. Y. C.; Edwards, D. J. 2005. Time-cost relationships in australian building construction projects, Journal of Construction Engineering and Management 131(2):187-194. doi:10.1061/(ASCE) 0733-9364 (2005) 131:2 (187)
    • (2005) Journal of Construction Engineering and Management , vol.131 , Issue.2 , pp. 187-194
    • Love, P.E.D.1    Tse, R.Y.C.2    Edwards, D.J.3
  • 21
    • 34250838802 scopus 로고    scopus 로고
    • Factors constraining successful building project implementation in South Africa
    • DOI 10.1080/01446190600601297, PII 769170315, Construction in Developing Countries
    • (Pubitemid 46978674) Mbachu, J.; Nkando, R. 2007. Factors constraining successful building project implementation in South Africa, Construction Management and Economics 25(1):39-54. doi:10.1080/01446190600601297
    • (2007) Construction Management and Economics , vol.25 , Issue.1 , pp. 39-54
    • Mbachu, J.1    Nkado, R.2
  • 23
    • 14544298805 scopus 로고    scopus 로고
    • Automated project performance control of construction projects
    • doi:10.1016/j.autcon. 2004.09.006
    • Navon, R. 2005. Automated project performance control of construction projects, Automation in Construction 14: 467-476. doi:10.1016/j.autcon. 2004.09.006
    • (2005) Automation in Construction , vol.14 , pp. 467-476
    • Navon, R.1
  • 24
    • 22844445211 scopus 로고    scopus 로고
    • Improving performance of construction industry in Singapore: Motivators, enablers and lessons for developing countries
    • DOI 10.1142/S1609945104000188
    • (Pubitemid 41036911) Ofori, G.; Dulaimi, M. F.; Ling, F. Y. 2004. Improving performance of construction industry in Singapore: motivators, enablers and lessons for developing countries, Journal of Construction Research 5(2):267-289. doi:10.1142/S1609945104000188
    • (2004) Journal of Construction Research , vol.5 , Issue.2 , pp. 267-289
    • Ofori, G.1    Dulaimi, M.F.2    Ling, F.Y.3
  • 25
    • 0032431968 scopus 로고    scopus 로고
    • Cost-time performance of public sector housing projects in Nigeria
    • doi:10.1016/S0197-3975 98 00014-9
    • Okuwoga, A. A. 1998. Cost-time performance of public sector housing projects in Nigeria, Habitat Intl. 22(4):389-395. doi:10.1016/S0197-3975 (98) 00014-9
    • (1998) Habitat Intl , vol.22 , Issue.4 , pp. 389-395
    • Okuwoga, A.A.1
  • 26
    • 30744448143 scopus 로고    scopus 로고
    • Environmental factors and work performance of project managers in the construction industry
    • doi:10.1016/j.ijproman. 2005.06.001
    • Pheng, L. S.; Chuan, Q. T. 2006. Environmental factors and work performance of project managers in the construction industry, International Journal of Project Management 24: 24-37. doi:10.1016/j.ijproman. 2005.06.001
    • (2006) International Journal of Project Management , vol.24 , pp. 24-37
    • Pheng, L.S.1    Chuan, Q.T.2
  • 27
    • 0033114449 scopus 로고    scopus 로고
    • The dynamic of project performance: Benchmarking the drivers of cost and schedule overrun
    • doi:10.1016/S0263-2373 98 00073-5
    • Reichelt, K.; Lyneis, J. 1999. The dynamic of project performance: Benchmarking the drivers of cost and schedule overrun, European Management Journal 17(2):135-150. doi:10.1016/S0263-2373 (98) 00073-5
    • (1999) European Management Journal , vol.17 , Issue.2 , pp. 135-150
    • Reichelt, K.1    Lyneis, J.2
  • 29
    • 33748942478 scopus 로고    scopus 로고
    • Key performance indicators and assessment methods for infrastructure sustainability - A South African Construction industry perspective
    • doi:10.1016/j.buildenv. 2005.10.018
    • Ugwu, O. O.; Haupt, T. C. 2007. Key performance indicators and assessment methods for infrastructure sustainability - a South African construction industry perspective, Building and Environment 42: 665-680. doi:10.1016/j. buildenv. 2005.10.018
    • (2007) Building and Environment , vol.42 , pp. 665-680
    • Ugwu, O.O.1    Haupt, T.C.2
  • 33
    • 70349607155 scopus 로고    scopus 로고
    • The impact of service quality on project performance: A case study of building maintenance services in Zambia
    • Association of Schools of Construction of Southern Africa, Cape Town, South Africa
    • rd Built Environment Conference, Association of Schools of Construction of Southern Africa, Cape Town, South Africa.
    • (2008) rd Built Environment Conference
    • Zulu, S.1    Chileshe, N.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.