메뉴 건너뛰기




Volumn 18, Issue 7, 2009, Pages 903-911

Assessing the impact of materials tracking technologies on construction craft productivity

Author keywords

Construction automation; Materials tracking; Productivity

Indexed keywords

AUTOMATED TRACKING; CONSTRUCTION AUTOMATION; CONSTRUCTION PRODUCTIVITY; ENGINEERED COMPONENTS; FIELD TRIAL; INDUSTRIAL SITES; LABOR PRODUCTIVITY; MATERIALS MANAGEMENT; MATERIALS TRACKING; PLANT PROJECT; PRODUCTIVITY IMPACTS; TRACKING PROCESS;

EID: 68049115666     PISSN: 09265805     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.autcon.2009.04.001     Document Type: Article
Times cited : (121)

References (34)
  • 2
    • 0000869144 scopus 로고
    • An examination of the productivity decline in the construction industry
    • The MIT Press
    • Stokes H. An examination of the productivity decline in the construction industry. The Review of Economics and Statistics 63, 4 (1981), The MIT Press 495-502
    • (1981) The Review of Economics and Statistics , vol.63 , Issue.4 , pp. 495-502
    • Stokes, H.1
  • 3
    • 68049092593 scopus 로고
    • More construction for the money: summary report of the construction industry cost effectiveness project
    • New York, New York
    • Business Roundtable (BRT). More construction for the money: summary report of the construction industry cost effectiveness project. The Business Roundtable (1983), New York, New York
    • (1983) The Business Roundtable
    • Business Roundtable (BRT)1
  • 4
    • 0001296853 scopus 로고
    • Why construction industry productivity is declining
    • The MIT Press
    • Allen S.G. Why construction industry productivity is declining. The Review of Economics and Statistics 117, 4 (1985), The MIT Press 661-665
    • (1985) The Review of Economics and Statistics , vol.117 , Issue.4 , pp. 661-665
    • Allen, S.G.1
  • 6
    • 0036648366 scopus 로고    scopus 로고
    • The divergence in aggregate and activity estimates of U.S. construction productivity
    • Goodrum P., Haas C., and Glover R. The divergence in aggregate and activity estimates of U.S. construction productivity. Journal of Construction Management and Economics 20 5 (2002) 415-423
    • (2002) Journal of Construction Management and Economics , vol.20 , Issue.5 , pp. 415-423
    • Goodrum, P.1    Haas, C.2    Glover, R.3
  • 7
    • 2342443555 scopus 로고    scopus 로고
    • Partial factor productivity and equipment technology change at the activity level in the US construction industry
    • Goodrum P., and Haas C. Partial factor productivity and equipment technology change at the activity level in the US construction industry. Journal of Construction Engineering and Management 128 6 (2002) 463-472
    • (2002) Journal of Construction Engineering and Management , vol.128 , Issue.6 , pp. 463-472
    • Goodrum, P.1    Haas, C.2
  • 11
    • 33745325795 scopus 로고    scopus 로고
    • Using global positioning system to improve materials-locating processes on industrial projects
    • Caldas C.H., Grau D., and Haas C.T. Using global positioning system to improve materials-locating processes on industrial projects. Journal of Construction Engineering and Management 132 7 (2006) 741-749
    • (2006) Journal of Construction Engineering and Management , vol.132 , Issue.7 , pp. 741-749
    • Caldas, C.H.1    Grau, D.2    Haas, C.T.3
  • 12
    • 68049105785 scopus 로고    scopus 로고
    • Leveraging technology to improve construction productivity
    • The Construction Industry Institute
    • CII. Leveraging technology to improve construction productivity. The Construction Industry Institute. Research Summary 240-1 (2008)
    • (2008) Research Summary 240-1
    • CII1
  • 14
    • 27144504102 scopus 로고    scopus 로고
    • Construction technology needs assessment update
    • Construction Industry Institute
    • Vorster M.C., and Lucko G. Construction technology needs assessment update. Construction Industry Institute. Research Report 173-11 (2002)
    • (2002) Research Report 173-11
    • Vorster, M.C.1    Lucko, G.2
  • 18
    • 58149223821 scopus 로고    scopus 로고
    • Real-time tracking and analysis of construction operations
    • ASCE, Grand Bahama Island, Bahamas
    • Su Y.Y., and Liu L.Y. Real-time tracking and analysis of construction operations. Proc., Construction Research Congress (2007), ASCE, Grand Bahama Island, Bahamas
    • (2007) Proc., Construction Research Congress
    • Su, Y.Y.1    Liu, L.Y.2
  • 19
    • 0004551106 scopus 로고
    • Major factors influencing craft productivity in nuclear power plant construction
    • American Association of Cost Engineers, Washington, D.C.
    • Borcherding J.D., and Sebastian S.J. Major factors influencing craft productivity in nuclear power plant construction. Proc., 24th Annual Meeting of the American Association of Cost Engineers (1980), American Association of Cost Engineers, Washington, D.C. I.1.1-I.1.5
    • (1980) Proc., 24th Annual Meeting of the American Association of Cost Engineers
    • Borcherding, J.D.1    Sebastian, S.J.2
  • 21
    • 0026898621 scopus 로고
    • Automated construction field-data management system
    • McCullouch B.G. Automated construction field-data management system. Journal of Transportation Engineering 118 4 (1992) 517-526
    • (1992) Journal of Transportation Engineering , vol.118 , Issue.4 , pp. 517-526
    • McCullouch, B.G.1
  • 22
    • 14744289522 scopus 로고    scopus 로고
    • Labor productivity drivers and opportunities in the construction industry
    • Rojas E.M., and Aramvareekul P. Labor productivity drivers and opportunities in the construction industry. Journal of Management in Engineering 19 2 (2003) 78-82
    • (2003) Journal of Management in Engineering , vol.19 , Issue.2 , pp. 78-82
    • Rojas, E.M.1    Aramvareekul, P.2
  • 27
    • 0012303148 scopus 로고    scopus 로고
    • Managing uncertainty in the piping process
    • The Construction Industry Institute
    • Howell G., and Ballard H.G. Managing uncertainty in the piping process. The Construction Industry Institute. Research Report 47-13 (1996)
    • (1996) Research Report 47-13
    • Howell, G.1    Ballard, H.G.2
  • 28
    • 0000012732 scopus 로고    scopus 로고
    • Pull-driven scheduling for pipe-spool installation: simulation of lean construction technique
    • Tommelein I.D. Pull-driven scheduling for pipe-spool installation: simulation of lean construction technique. Journal of Construction Engineering and Management 124 4 (1998) 279-288
    • (1998) Journal of Construction Engineering and Management , vol.124 , Issue.4 , pp. 279-288
    • Tommelein, I.D.1
  • 33
    • 58149259941 scopus 로고    scopus 로고
    • Methodology for automating the identification and localization of construction components on industrial projects
    • Grau D., and Caldas C.H. Methodology for automating the identification and localization of construction components on industrial projects. Journal of Computing in Civil Engineering 23 1 (2009) 3-13
    • (2009) Journal of Computing in Civil Engineering , vol.23 , Issue.1 , pp. 3-13
    • Grau, D.1    Caldas, C.H.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.