Volumn 133, Issue 6, 2007, Pages 417-424

Multiobjective linear programming model for scheduling linear repetitive projects

Author keywords

Computer programming; Project management; Scheduling

Indexed keywords

COMPUTER PROGRAMMING; CONSTRUCTION INDUSTRY; COSTS; DECISION SUPPORT SYSTEMS; MATHEMATICAL MODELS; RESOURCE ALLOCATION;

EID: 34248579316     PISSN: 07339364     EISSN: None     Source Type: Journal    
DOI: 10.1061/(ASCE)0733-9364(2007)133:6(417)     Document Type: Article
Times cited : (91)

References (32)
  • 1
    • 0019030430 scopus 로고
    • Simulation of repetitive-unit construction
    • Ashley, D. B. (1980). " Simulation of repetitive-unit construction.. " J. Constr. Div., 106 (2), 185-194.
    • (1980) J. Constr. Div. , vol.106 , Issue.2 , pp. 185-194
    • Ashley, D.B.1
  • 2
    • 0019064535 scopus 로고
    • Construction planning-Beyond the critical path
    • Birrell, G. S. (1980). " Construction planning-Beyond the critical path.. " J. Constr. Div., 106 (3), 389-407.
    • (1980) J. Constr. Div. , vol.106 , Issue.3 , pp. 389-407
    • Birrell, G.S.1
  • 3
    • 0000981977 scopus 로고
    • Planning construction of repetitive building units
    • Carr, R. I., and Meyer, W. L. (1974). " Planning construction of repetitive building units.. " J. Constr. Div., 100 (3), 403-412.
    • (1974) J. Constr. Div. , vol.100 , Issue.3 , pp. 403-412
    • Carr, R.I.1    Meyer, W.L.2
  • 4
    • 1842587322 scopus 로고    scopus 로고
    • Construction resource scheduling with genetic algorithms
    • Chan, W. T., Chua, D. K. H., and Kannan, C. G. (1996). " Construction resource scheduling with genetic algorithms.. " J. Constr. Eng. Manage., 122 (2), 125-132.
    • (1996) J. Constr. Eng. Manage. , vol.122 , Issue.2 , pp. 125-132
    • Chan, W.T.1    Chua, D.K.H.2    Kannan, C.G.3
  • 5
    • 0016342705 scopus 로고
    • Construction scheduling of linear construction sites
    • Dressler, J. (1974). " Construction scheduling of linear construction sites.. " J. Constr. Div., 100 (4), 571-587.
    • (1974) J. Constr. Div. , vol.100 , Issue.4 , pp. 571-587
    • Dressler, J.1
  • 6
    • 12444344998 scopus 로고    scopus 로고
    • Resource-driven scheduling of repetitive activities
    • El-Rayes, K., and Moselhi, O. (1998). " Resource-driven scheduling of repetitive activities.. " Constr. Manage. Econom., 16, 433-446.
    • (1998) Constr. Manage. Econom. , vol.16 , pp. 433-446
    • El-Rayes, K.1    Moselhi, O.2
  • 7
    • 0036539550 scopus 로고    scopus 로고
    • An object-oriented model for planning and control of housing construction
    • El-Rayes, K., Ramanathan, R., and Moselhi, O. (2002). " An object-oriented model for planning and control of housing construction.. " Constr. Manage. Econom., 20, 201-210.
    • (2002) Constr. Manage. Econom. , vol.20 , pp. 201-210
    • El-Rayes, K.1    Ramanathan, R.2    Moselhi, O.3
  • 8
    • 0035391905 scopus 로고    scopus 로고
    • Linear scheduling model: Float characteristics
    • Harmelink, D. J. (2001). " Linear scheduling model: Float characteristics.. " J. Constr. Eng. Manage., 127 (4), 255-260.
    • (2001) J. Constr. Eng. Manage. , vol.127 , Issue.4 , pp. 255-260
    • Harmelink, D.J.1
  • 9
    • 0000802988 scopus 로고    scopus 로고
    • Linear scheduling model: Development of controlling activity path
    • Harmelink, D. J., and Rowings, J. E. (1998). " Linear scheduling model: Development of controlling activity path.. " J. Constr. Eng. Manage., 124 (4), 263-268.
    • (1998) J. Constr. Eng. Manage. , vol.124 , Issue.4 , pp. 263-268
    • Harmelink, D.J.1    Rowings, J.E.2
  • 10
    • 0000674566 scopus 로고    scopus 로고
    • Scheduling project with repeating activities
    • Harris, R. B., and Ioannou, P. G. (1998). " Scheduling project with repeating activities.. " J. Constr. Eng. Manage., 124 (4), 269-278.
    • (1998) J. Constr. Eng. Manage. , vol.124 , Issue.4 , pp. 269-278
    • Harris, R.B.1    Ioannou, P.G.2
  • 11
    • 0032642926 scopus 로고    scopus 로고
    • Optimization of resource allocation and leveling using genetic algorithms
    • Hegazy, T. (1999). " Optimization of resource allocation and leveling using genetic algorithms.. " J. Constr. Eng. Manage., 125 (3), 167-175.
    • (1999) J. Constr. Eng. Manage. , vol.125 , Issue.3 , pp. 167-175
    • Hegazy, T.1
  • 12
    • 16444380299 scopus 로고    scopus 로고
    • Discussion of algorithm for determining controlling path considering resource continuity
    • Ioannou, P. G., and Harris, R. B. (2003). " Discussion of algorithm for determining controlling path considering resource continuity.. " J. Comput. Civ. Eng., 17 (1), 68-70.
    • (2003) J. Comput. Civ. Eng. , vol.17 , Issue.1 , pp. 68-70
    • Ioannou, P.G.1    Harris, R.B.2
  • 13
    • 34248586377 scopus 로고    scopus 로고
    • Discussion of algorithm for determining controlling path considering resource continuity
    • Ioannou, P. G., and Yang, I. T. (2003). " Discussion of algorithm for determining controlling path considering resource continuity.. " J. Comput. Civ. Eng., 17 (1), 70-72.
    • (2003) J. Comput. Civ. Eng. , vol.17 , Issue.1 , pp. 70-72
    • Ioannou, P.G.1    Yang, I.T.2
  • 14
    • 13944262179 scopus 로고    scopus 로고
    • Discussion of comparison of linear scheduling model and repetitive scheduling method
    • Ioannou, P. G., and Yang, I. T. (2004). " Discussion of comparison of linear scheduling model and repetitive scheduling method.. " J. Compos. Constr., 8 (3), 461-463.
    • (2004) J. Compos. Constr. , vol.8 , Issue.3 , pp. 461-463
    • Ioannou, P.G.1    Yang, I.T.2
  • 15
    • 0019583188 scopus 로고
    • Linear scheduling method for highway construction
    • Johnston, D. W. (1981). " Linear scheduling method for highway construction.. " J. Constr. Div., 107 (2), 247-261.
    • (1981) J. Constr. Div. , vol.107 , Issue.2 , pp. 247-261
    • Johnston, D.W.1
  • 17
    • 2542468807 scopus 로고    scopus 로고
    • Critical path determination by incorporation minimum and maximum time and distance constraints into linear scheduling
    • Kallantzis, A., and Lambropoulos, S. (2004). " Critical path determination by incorporation minimum and maximum time and distance constraints into linear scheduling.. " Eng., Constr., Archit. Manage., 11 (3), 211-222.
    • (2004) Eng., Constr., Archit. Manage. , vol.11 , Issue.3 , pp. 211-222
    • Kallantzis, A.1    Lambropoulos, S.2
  • 18
    • 84993081857 scopus 로고    scopus 로고
    • Linear scheduling: Past efforts and future directions
    • Mattila, K. G., and Abraham, D. M. (1998). " Linear scheduling: Past efforts and future directions.. " Eng., Constr., Archit. Manage., 5 (3), 294-303.
    • (1998) Eng., Constr., Archit. Manage. , vol.5 , Issue.3 , pp. 294-303
    • Mattila, K.G.1    Abraham, D.M.2
  • 19
    • 13944263987 scopus 로고    scopus 로고
    • Accuracy of highway contractor's schedules
    • Mattila, K. G., and Bowman, M. R. (2004). " Accuracy of highway contractor's schedules.. " J. Constr. Eng. Manage., 130 (5), 647-655.
    • (2004) J. Constr. Eng. Manage. , vol.130 , Issue.5 , pp. 647-655
    • Mattila, K.G.1    Bowman, M.R.2
  • 20
    • 13944263588 scopus 로고    scopus 로고
    • Comparison of linear scheduling model and repetitive scheduling method
    • Mattila, K. G., and Park, A. (2003). " Comparison of linear scheduling model and repetitive scheduling method.. " J. Constr. Eng. Manage., 129 (1), 56-64.
    • (2003) J. Constr. Eng. Manage. , vol.129 , Issue.1 , pp. 56-64
    • Mattila, K.G.1    Park, A.2
  • 21
    • 0016643558 scopus 로고
    • VPM scheduling for high-rise buildings
    • O'Brien, J. J. (1975). " VPM scheduling for high-rise buildings.. " J. Constr. Div., 101 (4), 895-905.
    • (1975) J. Constr. Div. , vol.101 , Issue.4 , pp. 895-905
    • O'Brien, J.J.1
  • 22
    • 2142649813 scopus 로고
    • Network analysis and construction planning
    • Peer, S. (1974). " Network analysis and construction planning.. " J. Constr. Div., 100 (3), 203-210.
    • (1974) J. Constr. Div. , vol.100 , Issue.3 , pp. 203-210
    • Peer, S.1
  • 23
    • 0025447970 scopus 로고
    • RPM: Repetitive project modeling
    • Reda, R. B. (1990). " RPM: Repetitive project modeling.. " J. Constr. Eng. Manage., 116 (2), 316-330.
    • (1990) J. Constr. Eng. Manage. , vol.116 , Issue.2 , pp. 316-330
    • Reda, R.B.1
  • 24
    • 0023984188 scopus 로고
    • Extensions to linear schedule optimization
    • Russell, A. D., and Ceselton, W. F. (1988). " Extensions to linear schedule optimization.. " J. Constr. Eng. Manage., 114 (4), 36-52.
    • (1988) J. Constr. Eng. Manage. , vol.114 , Issue.4 , pp. 36-52
    • Russell, A.D.1    Ceselton, W.F.2
  • 25
    • 0027607475 scopus 로고
    • New generation of planning structures
    • Russell, A. D., and Wong, W. C. M. (1993). " New generation of planning structures.. " J. Constr. Eng. Manage., 119 (2), 196-214.
    • (1993) J. Constr. Eng. Manage. , vol.119 , Issue.2 , pp. 196-214
    • Russell, A.D.1    Wong, W.C.M.2
  • 26
    • 0019030431 scopus 로고
    • Construction planning for linear projects
    • Selinger, S. (1980). " Construction planning for linear projects.. " J. Constr. Div., 106 (2), 195-205.
    • (1980) J. Constr. Div. , vol.106 , Issue.2 , pp. 195-205
    • Selinger, S.1
  • 27
    • 0020178299 scopus 로고
    • Time space scheduling method
    • Stradal, O., and Cacha, J. (1982). " Time space scheduling method.. " J. Constr. Div., 108 (3), 445-457.
    • (1982) J. Constr. Div. , vol.108 , Issue.3 , pp. 445-457
    • Stradal, O.1    Cacha, J.2
  • 30
    • 34248549089 scopus 로고    scopus 로고
    • Stochastic analysis on project duration under the requirement of continuous resource utilization
    • Yang, I. T. (2002b). " Stochastic analysis on project duration under the requirement of continuous resource utilization.. " Proc., 10th Int. Conf. Group for Lean Construction, Gramado, Brazil, 527-540.
    • (2002) Proc., 10th Int. Conf. Group for Lean Construction , pp. 527-540
    • Yang, I.T.1
  • 31
    • 4043118882 scopus 로고    scopus 로고
    • Resource-driven scheduling for repetitive projects: A pull-system approach
    • Yang, I. T., and Ioannou, P. G. (2001). " Resource-driven scheduling for repetitive projects: A pull-system approach.. " Proc., 9th Int. Conf. Group for Lean Construction, Singapore, 365-377.
    • (2001) Proc., 9th Int. Conf. Group for Lean Construction , pp. 365-377
    • Yang, I.T.1    Ioannou, P.G.2
  • 32
    • 4043093611 scopus 로고    scopus 로고
    • Scheduling with focus on practical concerns in repetitive projects
    • Yang, I. T., and Ioannou, P. G. (2004). " Scheduling with focus on practical concerns in repetitive projects.. " Constr. Manage. Econom., 22, 619-630.
    • (2004) Constr. Manage. Econom. , vol.22 , pp. 619-630
    • Yang, I.T.1    Ioannou, P.G.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.