Volumn 27, Issue 5, 2014, Pages 488-499

An improved particle swarm optimisation with a linearly decreasing disturbance term for flow shop scheduling with limited buffers

Author keywords

flow shop scheduling; limited buffers; linearly decreasing disturbance term; particle swarm optimisation; premature convergence

Indexed keywords

MACHINE SHOP PRACTICE; PARTICLE SWARM OPTIMIZATION (PSO); PROBABILITY; SCHEDULING;

EID: 84897749108     PISSN: 0951192X     EISSN: 13623052     Source Type: Journal    
DOI: 10.1080/0951192X.2013.814165     Document Type: Article
Times cited : (31)

References (44)
  • 1
    • 84855645015 scopus 로고    scopus 로고
    • Bi-Objective Hybrid Flow Shop Scheduling with Sequence-Dependent Setup Times and Limited Buffers."
    • Abyaneh, S. H., and, Zandieh, M. 2012. Bi-Objective Hybrid Flow Shop Scheduling with Sequence-Dependent Setup Times and Limited Buffers.". International Journal of Advanced Manufacturing Technology, 58 (1-4): 309-325.
    • (2012) International Journal of Advanced Manufacturing Technology , vol.58 , Issue.14 , pp. 309-325
    • Abyaneh, S.H.1    Zandieh, M.2
  • 2
    • 0000698815 scopus 로고    scopus 로고
    • Batch Scheduling in a Two-Machine Flow Shop with Limited Buffer."
    • Agnetis, A., Pacciarelli, D., and, Rossi, F. 1997. Batch Scheduling in a Two-Machine Flow Shop with Limited Buffer.". Discrete Applied Mathematics, 72 (3): 243-260.
    • (1997) Discrete Applied Mathematics , vol.72 , Issue.3 , pp. 243-260
    • Agnetis, A.1    Pacciarelli, D.2    Rossi, F.3
  • 3
    • 33845458698 scopus 로고    scopus 로고
    • Two Metaheuristic Methods for the Common Cycle Economic Lot Sizing and Scheduling in Flexible Flow Shops with Limited Intermediate Buffers: The Finite Horizon Case."
    • Akrami, B., Karimi, B., and, Hosseini, S. M. Moattar. 2006. Two Metaheuristic Methods for the Common Cycle Economic Lot Sizing and Scheduling in Flexible Flow Shops with Limited Intermediate Buffers: The Finite Horizon Case.". Applied Mathematics and Computation (New York), 183 (1): 634-645.
    • (2006) Applied Mathematics and Computation (New York) , vol.183 , Issue.1 , pp. 634-645
    • Akrami, B.1    Karimi, B.2    Hosseini, S.M.M.3
  • 4
    • 74249099017 scopus 로고    scopus 로고
    • Constrained Scheduling of the Inspection Activities on Semiconductor Wafers Grouped in Families with Sequence-Dependent Set-Up Times."
    • Celano, G., Costa, A., and, Fichera, S. 2010. Constrained Scheduling of the Inspection Activities on Semiconductor Wafers Grouped in Families with Sequence-Dependent Set-Up Times.". International Journal of Advanced Manufacturing Technology, 46 (5-8): 695-705.
    • (2010) International Journal of Advanced Manufacturing Technology , vol.46 , Issue.58 , pp. 695-705
    • Celano, G.1    Costa, A.2    Fichera, S.3
  • 6
    • 23344434757 scopus 로고    scopus 로고
    • Nonlinear Inertia Weight Variation for Dynamic Adaptation in Particle Swarm Optimization."
    • Chatterjee, A., and, Siarry, P. 2006. Nonlinear Inertia Weight Variation for Dynamic Adaptation in Particle Swarm Optimization.". Computers & Operations Research, 33 (3): 859-871.
    • (2006) Computers & Operations Research , vol.33 , Issue.3 , pp. 859-871
    • Chatterjee, A.1    Siarry, P.2
  • 7
    • 0036464756 scopus 로고    scopus 로고
    • The Particle Swarm - Explosion, Stability, and Convergence in a Multidimensional Complex Space."
    • Clerc, M., and, Kennedy, J. 2002. The Particle Swarm-Explosion, Stability, and Convergence in a Multidimensional Complex Space.". IEEE Transactions on Evolutionary Computation, 6 (1): 58-73.
    • (2002) IEEE Transactions on Evolutionary Computation , vol.6 , Issue.1 , pp. 58-73
    • Clerc, M.1    Kennedy, J.2
  • 9
    • 70449567536 scopus 로고    scopus 로고
    • Minimising the Weighted Number of Tardy Jobs in a Hybrid Flow Shop with Genetic Algorithm."
    • Desprez, C., Chu, F., and, Chu, C. 2009. Minimising the Weighted Number of Tardy Jobs in a Hybrid Flow Shop with Genetic Algorithm.". International Journal of Computer Integrated Manufacturing, 22 (8): 745-757.
    • (2009) International Journal of Computer Integrated Manufacturing , vol.22 , Issue.8 , pp. 745-757
    • Desprez, C.1    Chu, F.2    Chu, C.3
  • 10
    • 0016510092 scopus 로고
    • Sequencing Two-Machine Flow-Shops with Finite Intermediate Storage."
    • Dutta, S. K., and, Cunningham, A. A. 1975. Sequencing Two-Machine Flow-Shops with Finite Intermediate Storage.". Management Science, 21: 989-996.
    • (1975) Management Science , vol.21 , pp. 989-996
    • Dutta, S.K.1    Cunningham, A.A.2
  • 12
    • 22344432656 scopus 로고    scopus 로고
    • Comparison among Five Evolutionary-Based Optimization Algorithms."
    • Elbeltagi, E., Hegazy, T., and, Grierson, D. 2005. Comparison Among Five Evolutionary-Based Optimization Algorithms.". Advanced Engineering Informatics, 19 (1): 43-53.
    • (2005) Advanced Engineering Informatics , vol.19 , Issue.1 , pp. 43-53
    • Elbeltagi, E.1    Hegazy, T.2    Grierson, D.3
  • 13
    • 84861362807 scopus 로고    scopus 로고
    • Optimisation of Flow-Shop Scheduling with Batch Processor and Limited Buffer."
    • Fu, Q., Sivakumar, A. I., and, Li, K. 2012. Optimisation of Flow-Shop Scheduling with Batch Processor and Limited Buffer.". International Journal of Production Research, 50 (8): 2267-2285.
    • (2012) International Journal of Production Research , vol.50 , Issue.8 , pp. 2267-2285
    • Fu, Q.1    Sivakumar, A.I.2    Li, K.3
  • 14
    • 70349866696 scopus 로고    scopus 로고
    • A Note of Using Effective Immune Based Approach for the Flow Shop Scheduling with Buffers."
    • Hsieh, Y. C., You, P. S., and, Liou, C. D. 2009. A Note of Using Effective Immune Based Approach for the Flow Shop Scheduling with Buffers.". Applied Mathematics and Computation, 215 (5): 1984-1989.
    • (2009) Applied Mathematics and Computation , vol.215 , Issue.5 , pp. 1984-1989
    • Hsieh, Y.C.1    You, P.S.2    Liou, C.D.3
  • 15
    • 55749090380 scopus 로고    scopus 로고
    • June1-6. June1-6, Hong Kong, China: Proceedings of 2008 IEEE Congress on Evolutionary Computation, CEC 2008, Institute of Electrical and Electronics Engineers Computer Society
    • Hu, R., Wang, L., Qian, B., and, Huang, F.-Z. June1-6 2008. Differential Evolution Method for Stochastic Flow Shop Scheduling with Limited Buffersed.", June1-6, 1295-1301. Hong Kong, China: Proceedings of 2008 IEEE Congress on Evolutionary Computation, CEC 2008, Institute of Electrical and Electronics Engineers Computer Society.
    • (2008) Differential Evolution Method for Stochastic Flow Shop Scheduling with Limited Buffersed." , pp. 1295-1301
    • Hu, R.1    Wang, L.2    Qian, B.3    Huang, F.-Z.4
  • 18
    • 33744730797 scopus 로고    scopus 로고
    • Comprehensive Learning Particle Swarm Optimizer for Global Optimization of Multimodal Functions."
    • Liang, J. J., Qin, A. K., Suganthan, P. N., and, Baskar, S. 2006. Comprehensive Learning Particle Swarm Optimizer for Global Optimization of Multimodal Functions.". Ieee Transactions on Evolutionary Computation, 10 (3): 281-295.
    • (2006) Ieee Transactions on Evolutionary Computation , vol.10 , Issue.3 , pp. 281-295
    • Liang, J.J.1    Qin, A.K.2    Suganthan, P.N.3    Baskar, S.4
  • 19
    • 38749118677 scopus 로고    scopus 로고
    • An Effective Hybrid pso-Based Algorithm for Flow Shop Scheduling with Limited Buffers."
    • Liu, B., Wang, L., and, Jin, Y.-H. 2008. An Effective Hybrid pso-Based Algorithm for Flow Shop Scheduling with Limited Buffers.". Computers and Operations Research, 35 (9): 2791-2806.
    • (2008) Computers and Operations Research , vol.35 , Issue.9 , pp. 2791-2806
    • Liu, B.1    Wang, L.2    Jin, Y.-H.3
  • 20
    • 58949084435 scopus 로고    scopus 로고
    • Scheduling a Flow Shop with Combined Buffer Conditions."
    • Liu, S. Q., and, Kozan, E. 2009. Scheduling a Flow Shop with Combined Buffer Conditions.". International Journal of Production Economics, 117 (2): 371-380.
    • (2009) International Journal of Production Economics , vol.117 , Issue.2 , pp. 371-380
    • Liu, S.Q.1    Kozan, E.2
  • 21
  • 22
    • 0032649738 scopus 로고    scopus 로고
    • Permutation Flow Shop with Buffers: A Tabu Search Approach."
    • Nowicki, E. 1999. Permutation Flow Shop With Buffers: A Tabu Search Approach.". European Journal of Operational Research, 116 (1): 205-219.
    • (1999) European Journal of Operational Research , vol.116 , Issue.1 , pp. 205-219
    • Nowicki, E.1
  • 23
    • 80053560487 scopus 로고    scopus 로고
    • A Chaotic Harmony Search Algorithm for the Flow Shop Scheduling Problem with Limited Buffers."
    • Pan, Q.-K., Wang, L., and, Gao, L. 2011. A Chaotic Harmony Search Algorithm for the Flow Shop Scheduling Problem with Limited Buffers.". Applied Soft Computing Journal, 11 (8): 5270-5280.
    • (2011) Applied Soft Computing Journal , vol.11 , Issue.8 , pp. 5270-5280
    • Pan, Q.-K.1    Wang, L.2    Gao, L.3
  • 24
    • 58549115678 scopus 로고    scopus 로고
    • A Novel Differential Evolution Algorithm for bi-Criteria No-Wait Flow Shop Scheduling Problems."
    • Pan, Q.-K., Wang, L., and, Qian, B. 2009. A Novel Differential Evolution Algorithm for bi-Criteria No-Wait Flow Shop Scheduling Problems.". Computers and Operations Research, 36 (8): 2498-2511.
    • (2009) Computers and Operations Research , vol.36 , Issue.8 , pp. 2498-2511
    • Pan, Q.-K.1    Wang, L.2    Qian, B.3
  • 25
    • 73649137542 scopus 로고    scopus 로고
    • A Genetic Algorithmic Approach to Multi-Objective Scheduling in a Kanban-Controlled Flowshop with Intermediate Buffer and Transport Constraints."
    • Prasad, S. D., Rajendran, C., and, Chetty, O. V. K. 2006. A Genetic Algorithmic Approach to Multi-Objective Scheduling in a Kanban-Controlled Flowshop with Intermediate Buffer and Transport Constraints.". International Journal of Advanced Manufacturing Technology, 29 (5-6): 564-576.
    • (2006) International Journal of Advanced Manufacturing Technology , vol.29 , Issue.56 , pp. 564-576
    • Prasad, S.D.1    Rajendran, C.2    Chetty, O.V.K.3
  • 26
    • 44849083459 scopus 로고    scopus 로고
    • An Effective Hybrid de-Based Algorithm for Multi-Objective Flow Shop Scheduling with Limited Buffers."
    • Qian, B., Wang, L., Huang, D. X., Wang, W.-L., and, Wang, X. 2009. An Effective Hybrid de-Based Algorithm for Multi-Objective Flow Shop Scheduling with Limited Buffers.". Computers and Operations Research, 36 (1): 209-233.
    • (2009) Computers and Operations Research , vol.36 , Issue.1 , pp. 209-233
    • Qian, B.1    Wang, L.2    Huang, D.X.3    Wang, W.-L.4    Wang, X.5
  • 27
    • 56349108521 scopus 로고    scopus 로고
    • An Effective Hybrid de-Based Algorithm for Flow Shop Scheduling with Limited Buffers."
    • Qian, B., Wang, L., Huang, D. X., and, Wang, X. 2009. An Effective Hybrid de-Based Algorithm for Flow Shop Scheduling with Limited Buffers.". International Journal of Production Research, 47 (1): 1-24.
    • (2009) International Journal of Production Research , vol.47 , Issue.1 , pp. 1-24
    • Qian, B.1    Wang, L.2    Huang, D.X.3    Wang, X.4
  • 28
    • 3142768423 scopus 로고    scopus 로고
    • Self-Organizing Hierarchical Particle Swarm Optimizer with Time-Varying Acceleration Coefficients."
    • Ratnaweera, A., Halgamuge, S. K., and, Watson, H. C. 2004. Self-Organizing Hierarchical Particle Swarm Optimizer with Time-Varying Acceleration Coefficients.". IEEE Transactions on Evolutionary Computation, 8 (3): 240-55.
    • (2004) IEEE Transactions on Evolutionary Computation , vol.8 , Issue.3 , pp. 240-255
    • Ratnaweera, A.1    Halgamuge, S.K.2    Watson, H.C.3
  • 29
    • 0001753858 scopus 로고
    • Sequencing with Finite Intermediate Storage."
    • Reddi, S. 1976. Sequencing with Finite Intermediate Storage.". Management Science, 23: 216-217.
    • (1976) Management Science , vol.23 , pp. 216-217
    • Reddi, S.1
  • 30
    • 0030072218 scopus 로고    scopus 로고
    • Combinatorial Evaluation of Six Dispatching Rules in a Dynamic Two-Machine Flow Shop."
    • Sarper, H., and, Henry, M. C. 1996. Combinatorial Evaluation of Six Dispatching Rules in a Dynamic Two-Machine Flow Shop.". Omega, 24 (1): 73-81.
    • (1996) Omega , vol.24 , Issue.1 , pp. 73-81
    • Sarper, H.1    Henry, M.C.2
  • 31
    • 80053387597 scopus 로고    scopus 로고
    • An Adaptive Neuro Fuzzy Inference System for Makespan Estimation in Multiprocessor No-Wait Two Stage Flow Shop."
    • Shafaei, R., Rabiee, M., and, Mirzaeyan, M. 2011. An Adaptive Neuro Fuzzy Inference System for Makespan Estimation in Multiprocessor No-Wait Two Stage Flow Shop.". International Journal of Computer Integrated Manufacturing, 24 (10): 888-889.
    • (2011) International Journal of Computer Integrated Manufacturing , vol.24 , Issue.10 , pp. 888-889
    • Shafaei, R.1    Rabiee, M.2    Mirzaeyan, M.3
  • 33
    • 54549127964 scopus 로고    scopus 로고
    • A Two-Machine Permutation Flow Shop Scheduling Problem with Buffers."
    • Smutnicki, C. 1998. A Two-Machine Permutation Flow Shop Scheduling Problem with Buffers.". OR Spectrum, 20 (4): 229-235.
    • (1998) OR Spectrum , vol.20 , Issue.4 , pp. 229-235
    • Smutnicki, C.1
  • 34
    • 79952076295 scopus 로고    scopus 로고
    • A Tabu Search Approach for Group Scheduling in Buffer-Constrained Flow Shop Cells."
    • Solimanpur, M., and, Elmi, A. 2011. A Tabu Search Approach for Group Scheduling in Buffer-Constrained Flow Shop Cells.". International Journal of Computer Integrated Manufacturing, 24 (3): 257-268.
    • (2011) International Journal of Computer Integrated Manufacturing , vol.24 , Issue.3 , pp. 257-268
    • Solimanpur, M.1    Elmi, A.2
  • 35
    • 5144221178 scopus 로고    scopus 로고
    • Complexity of Flow Shop Scheduling Problems with Transportation Constraints."
    • Soukhal, A., Oulamara, A., and, Martineau, P. 2005. Complexity of Flow Shop Scheduling Problems with Transportation Constraints.". European Journal of Operational Research, 161 (1): 32-41.
    • (2005) European Journal of Operational Research , vol.161 , Issue.1 , pp. 32-41
    • Soukhal, A.1    Oulamara, A.2    Martineau, P.3
  • 37
    • 12844261681 scopus 로고    scopus 로고
    • A Tight Flow Control for Job-Shop Fabrication Lines with Finite Buffers."
    • Toba, H. 2005. A Tight Flow Control for Job-Shop Fabrication Lines with Finite Buffers.". IEEE Transactions on Automation Science and Engineering, 2 (1): 78-83.
    • (2005) IEEE Transactions on Automation Science and Engineering , vol.2 , Issue.1 , pp. 78-83
    • Toba, H.1
  • 38
    • 84859717538 scopus 로고    scopus 로고
    • Heuristics and Metaheuristics for Mixed Blocking Constraints Flowshop Scheduling Problems."
    • Trabelsi, W., Sauvey, C., and, Sauer, N. 2012. Heuristics and Metaheuristics for Mixed Blocking Constraints Flowshop Scheduling Problems.". Computers and Operations Research, 39 (11): 2520-2527.
    • (2012) Computers and Operations Research , vol.39 , Issue.11 , pp. 2520-2527
    • Trabelsi, W.1    Sauvey, C.2    Sauer, N.3
  • 39
    • 70349273953 scopus 로고    scopus 로고
    • A Novel Hybrid Discrete Differential Evolution Algorithm for Blocking Flow Shop Scheduling Problems."
    • Wang, L., Pan, Q.-K., Suganthan, P. N., Wang, W.-H., and, Wang, Y.-M. 2010. A Novel Hybrid Discrete Differential Evolution Algorithm for Blocking Flow Shop Scheduling Problems.". Computers and Operations Research, 37 (3): 509-520.
    • (2010) Computers and Operations Research , vol.37 , Issue.3 , pp. 509-520
    • Wang, L.1    Pan, Q.-K.2    Suganthan, P.N.3    Wang, W.-H.4    Wang, Y.-M.5
  • 40
    • 32044464100 scopus 로고    scopus 로고
    • An Effective Hybrid Genetic Algorithm for Flow Shop Scheduling with Limited Buffers."
    • Wang, L., Zhang, L., and, Zheng, D.-Z. 2006. An Effective Hybrid Genetic Algorithm for Flow Shop Scheduling With Limited Buffers.". Computers and Operations Research, 33 (10): 2960-2971.
    • (2006) Computers and Operations Research , vol.33 , Issue.10 , pp. 2960-2971
    • Wang, L.1    Zhang, L.2    Zheng, D.-Z.3
  • 41
    • 0036722157 scopus 로고    scopus 로고
    • Minimizing the Mean Weighted Absolute Deviation from Due Dates in Lot-Streaming Flow Shop Scheduling."
    • Yoon, S.-H., and, Ventura, J. A. 2002. Minimizing the Mean Weighted Absolute Deviation from Due Dates in Lot-Streaming Flow Shop Scheduling.". Computers and Operations Research, 29 (10): 1301-1315.
    • (2002) Computers and Operations Research , vol.29 , Issue.10 , pp. 1301-1315
    • Yoon, S.-H.1    Ventura, J.A.2
  • 42
    • 38649118854 scopus 로고    scopus 로고
    • Evolving Artificial Neural Networks Using an Improved pso and dpso."
    • Yu, J., Wang, S., and, Xi, L. 2008. Evolving Artificial Neural Networks Using an Improved pso and dpso.". Neurocomputing, 71 (4-6): 1054-1060.
    • (2008) Neurocomputing , vol.71 , Issue.46 , pp. 1054-1060
    • Yu, J.1    Wang, S.2    Xi, L.3
  • 44
    • 74949126533 scopus 로고    scopus 로고
    • A Hybrid Particle Swarm Optimisation Algorithm and Fuzzy Logic for Process Planning and Production Scheduling Integration in Holonic Manufacturing Systems."
    • Zhao, F., Hong, Y., Yu, D., Yang, Y., and, Zhang, Q. 2010. A Hybrid Particle Swarm Optimisation Algorithm and Fuzzy Logic for Process Planning and Production Scheduling Integration in Holonic Manufacturing Systems.". International Journal of Computer Integrated Manufacturing, 23 (1): 20-39.
    • (2010) International Journal of Computer Integrated Manufacturing , vol.23 , Issue.1 , pp. 20-39
    • Zhao, F.1    Hong, Y.2    Yu, D.3    Yang, Y.4    Zhang, Q.5


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.