Optimizing strategy for repetitive construction projects within multi-mode resources

Author keywords

Cash flow; Construction repetitive projects; Line Of Balance; Mathematical modeling and multi objective optimization; Net present value; Tendering

Indexed keywords

CONTRACTORS; MULTIOBJECTIVE OPTIMIZATION; PRODUCTION CONTROL;

EID: 84873986753     PISSN: 11100168     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.aej.2012.11.003     Document Type: Article
Times cited : (15)

References (51)
  • 1
    • 84877734185 scopus 로고    scopus 로고
    • Pricing Strategy for Best Value Tender
    • Posted ahead of print 31 August
    • W. Yu, K. Wang, M. Wang, Pricing Strategy for Best Value Tender, Journal of Construction Engineering and Management, Posted ahead of print 31 August 2012, http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000635.
    • (2012) Journal of Construction Engineering and Management
    • Yu, W.1    Wang, K.2    Wang, M.3
  • 2
    • 0020138987 scopus 로고
    • Application of cost-flow forecasting models
    • S. Peer Application of cost flow forecasting models Journal of the Construction Division ASCE 108 CO2 1982 226 232 (Pubitemid 12524272)
    • (1982) Journal of the Construction Division , vol.108 , Issue.CO2 , pp. 226-232
    • Peer Shlomo1
  • 4
    • 0004551714 scopus 로고
    • Resource-based model for automatic cash flow forecasting
    • R. Navon Resource-based model for automatic cash flow forecasting Construction Management and Economics 13 6 1995 501 510
    • (1995) Construction Management and Economics , vol.13 , Issue.6 , pp. 501-510
    • Navon, R.1
  • 5
    • 0343248602 scopus 로고    scopus 로고
    • A neural networks approach for cost flow forecasting
    • A. Boussabaine, and A. Kaka A neural networks approach for cost flow forecasting Construction Management and Economics 16 4 1998 471 479 (Pubitemid 128650984)
    • (1998) Construction Management and Economics , vol.16 , Issue.4 , pp. 471-479
    • Boussabaine, A.H.1    Kaka, A.P.2
  • 9
    • 0141931000 scopus 로고    scopus 로고
    • Updating techniques for cumulative cost forecasting on construction projects
    • A. Kaka, and A. Boussabaine Updating techniques for cumulative cost forecasting on construction projects Journal of Construction Procurement. 5 2 1999 141 158
    • (1999) Journal of Construction Procurement. , vol.5 , Issue.2 , pp. 141-158
    • Kaka, A.1    Boussabaine, A.2
  • 10
    • 84873991925 scopus 로고    scopus 로고
    • In-project end-date forecasting: An idiographic, deterministic approach, using cash flow modeling
    • R. Kenley "In-project end-date forecasting: an idiographic, deterministic approach, using cash flow modeling Journal Financial Management of Property and Construction 6 3 2001 209 216
    • (2001) Journal Financial Management of Property and Construction , vol.6 , Issue.3 , pp. 209-216
    • Kenley, R.1
  • 12
    • 79951642894 scopus 로고    scopus 로고
    • A radical approach to risk in project financial management
    • A. Akintoye, Glasgow Caledonian University (September 6-8), pp. 547-556
    • F. Khosrowshahi A radical approach to risk in project financial management A. Akintoye, Procs 16th Annual ARCOM Conference 2000 Glasgow Caledonian University (September 6-8), pp. 547-556
    • (2000) Procs 16th Annual ARCOM Conference
    • Khosrowshahi, F.1
  • 15
    • 33845698987 scopus 로고    scopus 로고
    • An evaluation of methodological issues for assessing risk impacts on construction cash flow forecast
    • A. Akintoye, University of Salford (September 5-7), pp. 381-389
    • H. Odeyinka, and J. Lowe An evaluation of methodological issues for assessing risk impacts on construction cash flow forecast A. Akintoye, Procs 17th Annual ARCOM Conference 2001 University of Salford (September 5-7), pp. 381-389
    • (2001) Procs 17th Annual ARCOM Conference
    • Odeyinka, H.1    Lowe, J.2
  • 16
    • 0344463113 scopus 로고
    • Modeling standard cost commitment curves for contractors' cash flow forecasting
    • A. Kaka, and A. Price Modeling standard cost commitment curves for contractors' cash flow forecasting Construction Management and Economics 11 4 1993 271 283
    • (1993) Construction Management and Economics , vol.11 , Issue.4 , pp. 271-283
    • Kaka, A.1    Price, A.2
  • 18
    • 84864564737 scopus 로고
    • Cash flow and the construction client: A theoretical approach
    • P. Lansley, P. Harlow, Spon London
    • J. Lowe Cash flow and the construction client: a theoretical approach P. Lansley, P. Harlow, Managing Construction Worldwide vol. 1 1987 Spon London 27 336
    • (1987) Managing Construction Worldwide , vol.1 VOL. , pp. 27-336
    • Lowe, J.1
  • 19
    • 77951660469 scopus 로고    scopus 로고
    • Systems analysis of project cash flow management strategies
    • Q. Cui, M. Hastak, and D. Halpin Systems analysis of project cash flow management strategies Construction Management and Economics 28 4 2010 361 376
    • (2010) Construction Management and Economics , vol.28 , Issue.4 , pp. 361-376
    • Cui, Q.1    Hastak, M.2    Halpin, D.3
  • 21
    • 15944391749 scopus 로고    scopus 로고
    • Finance-based scheduling: Tool to maximize project profit using improved genetic algorithms
    • DOI 10.1061/(ASCE)0733-9364(2005)131:4(400)
    • A. Elazouni, and F. Metwally Finance-based scheduling: Tool to maximize project profit using improved genetic algorithms Journal of Construction Engineering and Management 131 4 2005 400 412 (Pubitemid 40430136)
    • (2005) Journal of Construction Engineering and Management , vol.131 , Issue.4 , pp. 400-412
    • Elazouni, A.M.1    Metwally, F.G.2
  • 22
    • 33845769935 scopus 로고    scopus 로고
    • Expanding finance-based scheduling to devise overall-optimized project schedules
    • DOI 10.1061/(ASCE)0733-9364(2007)133:1(86)
    • A. Elazouni, and F. Metwally Expanding finance-based scheduling to devise overall-optimized project schedules Journal of Construction Engineering and Management 133 1 2007 86 90 (Pubitemid 44975053)
    • (2007) Journal of Construction Engineering and Management , vol.133 , Issue.1 , pp. 86-90
    • Elazouni, A.M.1    Metwally, F.G.2
  • 23
    • 67650294079 scopus 로고    scopus 로고
    • Heuristic method for multi-project finance-based scheduling
    • A. Elazouni Heuristic method for multi-project finance-based scheduling Construction Management and Economics 27 2 2009 199 211
    • (2009) Construction Management and Economics , vol.27 , Issue.2 , pp. 199-211
    • Elazouni, A.1
  • 24
    • 45849109552 scopus 로고    scopus 로고
    • Resource-constrained construction project scheduling model for profit maximization considering cash flow
    • S. Liu, and C. Wang Resource-constrained construction project scheduling model for profit maximization considering cash flow Automation in Construction 17 8 2008 966 974
    • (2008) Automation in Construction , vol.17 , Issue.8 , pp. 966-974
    • Liu, S.1    Wang, C.2
  • 25
    • 0024764770 scopus 로고    scopus 로고
    • Developing a computer model for cash flow planning
    • S. Singh Developing a computer model for cash flow planning Cost Engineering 31 11 2001 7 11
    • (2001) Cost Engineering , vol.31 , Issue.11 , pp. 7-11
    • Singh, S.1
  • 27
    • 0000318873 scopus 로고    scopus 로고
    • The theory and practice of corporate finance: Evidence from the field
    • DOI 10.1016/S0304-405X(01)00044-7, PII S0304405X01000447
    • J. Graham, and C. Harvey The theory and practice of corporate finance. evidence from the field Journal Financial Economics 60 2001 187 243 (Pubitemid 33623432)
    • (2001) Journal of Financial Economics , vol.60 , Issue.2-3 , pp. 187-243
    • Graham, J.R.1    Harvey, C.R.2
  • 28
    • 0742289215 scopus 로고    scopus 로고
    • International financial management: 35 years later - What has changed?
    • DOI 10.1016/j.ibusrev.2003.08.003, PII S0969593103001343
    • L. Remmers International financial management: 35 years later-what has changed? International Business Review 13 2004 155 180 (Pubitemid 38156839)
    • (2004) International Business Review , vol.13 , Issue.2 , pp. 155-180
    • Remmers, L.1
  • 29
    • 22544471963 scopus 로고    scopus 로고
    • Capital budgeting practices of the Fortune 1000: How have things changed?
    • G. Ryan, and P. Ryan Capital budgeting practices of the Fortune 1000: How have things changed? Journal Business Manage 8 4 2002 355 364
    • (2002) Journal Business Manage , vol.8 , Issue.4 , pp. 355-364
    • Ryan, G.1    Ryan, P.2
  • 30
    • 84873997440 scopus 로고    scopus 로고
    • The capital budgeting decision of small business
    • M. Danielson, J. Scott, The capital budgeting decision of small business, Working paper presented at the FMA 2005 annual meeting, 2005.
    • (2005) FMA 2005 Annual Meeting
    • Danielson, M.1    Scott, J.2
  • 31
    • 0038721047 scopus 로고    scopus 로고
    • The process of investment appraisal: The experience of 10 large British and Dutch companies
    • M. Mekonnen The process of investment appraisal: the experience of 10 large British and Dutch companies International Journal of Project Management 21 2003 355 362
    • (2003) International Journal of Project Management , vol.21 , pp. 355-362
    • Mekonnen, M.1
  • 32
    • 0037432507 scopus 로고    scopus 로고
    • Capital budgeting methods among Sweden's largest groups of companies: The state of the art and a comparison with earlier studies
    • G. Sandahl, and S. Sjogren Capital budgeting methods among Sweden's largest groups of companies: the state of the art and a comparison with earlier studies International Journal Production Economics 84 2003 51 69
    • (2003) International Journal Production Economics , vol.84 , pp. 51-69
    • Sandahl, G.1    Sjogren, S.2
  • 33
    • 79951640819 scopus 로고    scopus 로고
    • Derivation and assessment of interest in cash flow calculations for time-cost optimizations in construction project management
    • G. Lucko, R. Thompson, Derivation and assessment of interest in cash flow calculations for time-cost optimizations in construction project management in: Proceedings of the Winter Simulation Conference, 2010, pp. 3037-3048.
    • (2010) Proceedings of the Winter Simulation Conference , pp. 3037-3048
    • Lucko, G.1    Thompson, R.2
  • 34
    • 14044266312 scopus 로고    scopus 로고
    • Analysis of the United States Department of Transportation prompt pay provisions
    • DOI 10.1061/(ASCE)0733-9364(2004)130:5(719)
    • A. Touran, M. Atgun, and I. Bhurisith Analysis of the United States department of transportation prompt pay provisions Journal of Construction Engineering and Management 130 5 2004 719 725 (Pubitemid 40274290)
    • (2004) Journal of Construction Engineering and Management , vol.130 , Issue.5 , pp. 719-725
    • Touran, A.1    Atgun, M.2    Bhurisith, I.3
  • 35
    • 34548274425 scopus 로고    scopus 로고
    • A decision support model for construction cash flow management
    • DOI 10.1111/j.1467-8667.2007.00508.x, Decision Making in Urban and Civil Engineering
    • F. Khosrowshahi, and A. Kaka A decision support model for construction cash flow management Computer-Aided Civil and Infrastructure Engineering 22 7 2007 527 539 (Pubitemid 47316314)
    • (2007) Computer-Aided Civil and Infrastructure Engineering , vol.22 , Issue.7 , pp. 527-539
    • Khosrowshahi, F.1    Kaka, A.P.2
  • 36
    • 67349224016 scopus 로고    scopus 로고
    • Evolutionary support vector machine inference system for construction management
    • M. Cheng, and Y. Wu Evolutionary support vector machine inference system for construction management Automation in Construction 18 5 2009 597 604
    • (2009) Automation in Construction , vol.18 , Issue.5 , pp. 597-604
    • Cheng, M.1    Wu, Y.2
  • 37
    • 78049278760 scopus 로고    scopus 로고
    • Evolutionary fuzzy decision model for cash flow prediction using time-dependent support vector machines
    • M. Cheng, and A. Roy Evolutionary fuzzy decision model for cash flow prediction using time-dependent support vector machines International Journal of Project Management 29 2011 56 65
    • (2011) International Journal of Project Management , vol.29 , pp. 56-65
    • Cheng, M.1    Roy, A.2
  • 38
    • 84873987748 scopus 로고    scopus 로고
    • Financing-scheduling optimization for construction projects by using genetic algorithms
    • Engineering Management and Technology World Academy of Science, Engineering and Technology WASET Paris, France
    • H. Abdel-Khalek, S. Hafez, A. Lakany, and Y. Abuel-Magd Financing-scheduling optimization for construction projects by using genetic algorithms International Conference on Innovation Engineering Management and Technology vol. 59 2011 World Academy of Science, Engineering and Technology WASET Paris, France 289 297
    • (2011) International Conference on Innovation , vol.59 VOL. , pp. 289-297
    • Abdel-Khalek, H.1    Hafez, S.2    Lakany, A.3    Abuel-Magd, Y.4
  • 39
    • 78650349618 scopus 로고    scopus 로고
    • Optimization of project time-cost trade-off problem with discounted cash flows
    • M. Ammar Optimization of project time-cost trade-off problem with discounted cash flows Journal of Construction Engineering and Management 137 1 2011 65 71
    • (2011) Journal of Construction Engineering and Management , vol.137 , Issue.1 , pp. 65-71
    • Ammar, M.1
  • 40
    • 79960255024 scopus 로고    scopus 로고
    • Optimizing cash flows for linear schedules modeled with singularity functions by simulated annealing
    • G. Lucko optimizing cash flows for linear schedules modeled with singularity functions by simulated annealing Journal of Construction Engineering and Management 137 7 2011 523 535
    • (2011) Journal of Construction Engineering and Management , vol.137 , Issue.7 , pp. 523-535
    • Lucko, G.1
  • 41
    • 78649279880 scopus 로고    scopus 로고
    • Profit optimization for multiproject scheduling problems considering cash flow
    • S. Liu, and C. Wang Profit optimization for multiproject scheduling problems considering cash flow Journal of Construction Engineering and Management 136 12 2010 1268 1278
    • (2010) Journal of Construction Engineering and Management , vol.136 , Issue.12 , pp. 1268-1278
    • Liu, S.1    Wang, C.2
  • 42
  • 43
    • 84856607630 scopus 로고    scopus 로고
    • Project cash flow analysis in the presence of uncertainty in activity duration and cost
    • A. Maravas, and J. Pantouvakis Project cash flow analysis in the presence of uncertainty in activity duration and cost International Journal of Project Management 30 2012 374 384
    • (2012) International Journal of Project Management , vol.30 , pp. 374-384
    • Maravas, A.1    Pantouvakis, J.2
  • 44
    • 79955955101 scopus 로고    scopus 로고
    • An empirical examination of project contractors' supply-chain cash flow performance and owners' payment patterns
    • L. Hong An empirical examination of project contractors' supply-chain cash flow performance and owners' payment patterns International Journal of Project Management 29 2011 604 614
    • (2011) International Journal of Project Management , vol.29 , pp. 604-614
    • Hong, L.1
  • 46
    • 84873356253 scopus 로고    scopus 로고
    • Analyzing the Impact of Negative Cash Flow on Construction Performance in the Dubai Area
    • Posted ahead of print 18 February
    • K. Al-Joburi, R. Al-Aomar, M. Bahri, Analyzing the Impact of Negative Cash Flow on Construction Performance in the Dubai Area, Journal of Management in Engineering, Posted ahead of print 18 February 2012, http://dx.doi.org/10. 1061/(ASCE)ME.1943-5479.0000123.
    • (2012) Journal of Management in Engineering
    • Al-Joburi, K.1    Al-Aomar, R.2    Bahri, M.3
  • 47
    • 0041509528 scopus 로고
    • Construction of present value tables for use in evaluation of capital investment opportunities
    • C. Christenson Construction of present value tables for use in evaluation of capital investment opportunities The Accounting Review 1955 666 673
    • (1955) The Accounting Review , pp. 666-673
    • Christenson, C.1
  • 48
    • 0007202087 scopus 로고
    • Measuring the Productivity of Capital
    • J. Dean Measuring the Productivity of Capital Harvard Business Review 1954 120 130
    • (1954) Harvard Business Review , pp. 120-130
    • Dean, J.1
  • 51
    • 0043012329 scopus 로고
    • Contracts and Payment Structures
    • D. Lock, (Ed.) (Chapter 5)
    • P. Marsh, Contracts and Payment Structures, in: D. Lock, (Ed.), Project Management Handbook, 1987, pp. 93-118, (Chapter 5).
    • (1987) Project Management Handbook , pp. 93-118
    • Marsh, P.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.