Volumn 49, Issue 24, 2011, Pages 7315-7335

Synchronisation of scarce resources for a parallel machine lotsizing problem

Author keywords

Lot sizing; Mixed integer linear Programming; Production planning; Scheduling

Indexed keywords

CAPACITATED LOT SIZING PROBLEM; LOT SIZING; LOT SIZING PROBLEMS; MANUFACTURING PROCESS; MIXED INTEGER LINEAR PROGRAMMING; PARALLEL MACHINE; PRODUCTION PLANNING; SCARCE RESOURCES; SCHEDULING PROBLEM; SECONDARY RESOURCES; SEMICONDUCTOR INDUSTRY; SOFT DRINKS; TIME-PERIODS; UNRELATED MACHINES; WAFER TESTING;

EID: 84855790162     PISSN: 00207543     EISSN: 1366588X     Source Type: Journal    
DOI: 10.1080/00207543.2010.535570     Document Type: Article
Times cited : (33)

References (25)
  • 1
    • 0036643163 scopus 로고    scopus 로고
    • Dynamic lot sizing and tool management in automated manufacturing systems
    • DOI 10.1016/S0305-0548(00)00103-9, PII S0305054800001039
    • Akturk, M. and Onen, S., 2002. Dynamic lot sizing and tool management in automated manufacturing systems. Computers & Operations Research, 29 (8), 1059-1079. (Pubitemid 34196081)
    • (2002) Computers and Operations Research , vol.29 , Issue.8 , pp. 1059-1079
    • Akturk M.Selim1    Onen, S.2
  • 3
    • 35248840078 scopus 로고    scopus 로고
    • A note on "the capacitated lot-sizing and scheduling problem with sequence-dependent setup costs and setup times
    • DOI 10.1016/j.cor.2006.08.019, PII S0305054806002012
    • Almada-Lobo, B., Carravilla, M., and Oliveira, J., 2008. A note on 'The capacitated lot-sizing and scheduling problem with sequence-dependent setup costs and setup times'. Computers & Operations Research, 35 (4), 1374-1376. (Pubitemid 47558962)
    • (2008) Computers and Operations Research , vol.35 , Issue.4 , pp. 1374-1376
    • Almada-Lobo, B.1    Oliveira, J.F.2    Antonia Carravilla, M.3
  • 4
  • 5
    • 0020832935 scopus 로고
    • Mathematical programming approaches to capacity-constrained mrp systems: Review, formulation and problem reduction
    • Billington, P., McClain, J., and Thomas, L., 1983. Mathematical programming approach to capacity-constrained MRP systems: Review, formulation and problem reduction. Management Science, 29 (10), 1126-1141. (Pubitemid 14468571)
    • (1983) Management Science , vol.39 , Issue.10 , pp. 1126-1141
    • Billington Peter, J.1    McClain John, O.2    Thomas L.Joseph3
  • 6
    • 77349118693 scopus 로고    scopus 로고
    • Dynamic capacitated lot-sizing problems: A classification and review of solution approaches
    • Buschkü hl, L., et al., 2010. Dynamic capacitated lot-sizing problems: A classification and review of solution approaches. OR Spectrum, 32 (2), 231-261.
    • (2010) OR Spectrum , vol.32 , Issue.2 , pp. 231-261
    • Buschkühl, L.1
  • 7
    • 13844298234 scopus 로고    scopus 로고
    • Scheduling injection molding operations with multiple resource constraints and sequence dependent setup times and costs
    • DOI 10.1016/j.cor.2004.04.012, PII S0305054804000899
    • Dastidar, S. and Nagi, R., 2005. Scheduling injection molding operations with multiple resource constraints and sequence dependent setup times and costs. Computers & Operations Research, 32 (11), 2987-3005. (Pubitemid 40244558)
    • (2005) Computers and Operations Research , vol.32 , Issue.11 , pp. 2987-3005
    • Ghosh Dastidar, S.1    Nagi, R.2
  • 8
    • 0031170482 scopus 로고    scopus 로고
    • Lot sizing and scheduling - Survey and extensions
    • PII S0377221797000301
    • Drexl, A. and Kimms, A., 1997. Lot sizing and scheduling - survey and extensions. European Journal of Operational Research, 99 (2), 221-235. (Pubitemid 127418431)
    • (1997) European Journal of Operational Research , vol.99 , Issue.2 , pp. 221-235
    • Drexl, A.1    Kimms, A.2
  • 9
    • 1342287292 scopus 로고    scopus 로고
    • Scheduling of wafer test processes in semiconductor manufacturing
    • Ellis, K.P., Lu, Y., and Bish, E.K., 2004. Scheduling of wafer test processes in semiconductor manufacturing. International Journal of Production Research, 42 (2), 215-242.
    • (2004) International Journal of Production Research , vol.42 , Issue.2 , pp. 215-242
    • Ellis, K.P.1    Lu, Y.2    Bish, E.K.3
  • 10
    • 58149250389 scopus 로고    scopus 로고
    • Solution approaches for the soft drink integrated production lot sizing and scheduling problem
    • Ferreira, D., Morabito, R., and Rangel, S., 2009. Solution approaches for the soft drink integrated production lot sizing and scheduling problem. European Journal of Operational Research, 196 (2), 697-706.
    • (2009) European Journal of Operational Research , vol.196 , Issue.2 , pp. 697-706
    • Ferreira, D.1    Morabito, R.2    Rangel, S.3
  • 11
    • 0008655177 scopus 로고    scopus 로고
    • The general lotsizing and scheduling problem
    • Fleischmann, B. and Meyr, H., 1997. The general lotsizing and scheduling problem. OR Spektrum, 19, 11-21.
    • (1997) OR Spektrum , vol.19 , pp. 11-21
    • Fleischmann, B.1    Meyr, H.2
  • 12
    • 0010775487 scopus 로고    scopus 로고
    • Capacitated lot-sizing with sequence dependent setup costs
    • Haase, K., 1996. Capacitated lot-sizing with sequence dependent setup costs. Operations Research Spektrum, 18, 51-59.
    • (1996) Operations Research Spektrum , vol.18 , pp. 51-59
    • Haase, K.1
  • 13
    • 0347899318 scopus 로고    scopus 로고
    • An industrial extension of the discrete lot-iszing and scheduling problem
    • Jans, R. and Degraeve, Z., 2004. An industrial extension of the discrete lot-iszing and scheduling problem. IIE Transactions, 36 (1), 47-58.
    • (2004) IIE Transactions , vol.36 , Issue.1 , pp. 47-58
    • Jans, R.1    Degraeve, Z.2
  • 14
    • 36448995797 scopus 로고    scopus 로고
    • Modeling industrial lot sizing problems: A review
    • DOI 10.1080/00207540600902262, PII 770289062
    • Jans, R. and Degraeve, Z., 2008. Modeling industrial lot sizing problems: A review. International Journal of Production Research, 46 (6), 1619-1643. (Pubitemid 350161679)
    • (2008) International Journal of Production Research , vol.46 , Issue.6 , pp. 1619-1643
    • Jans, R.1    Degraeve, Z.2
  • 15
    • 0032652235 scopus 로고    scopus 로고
    • Lotsizing and scheduling on parallel machines with sequence-dependent setup cost
    • Kang, S., Malik, K., and Thomas, L., 1999. Lotsizing and scheduling on parallel machines with sequence-dependent setup cost. Management Science, 45 (2), 273-289.
    • (1999) Management Science , vol.45 , Issue.2 , pp. 273-289
    • Kang, S.1    Malik, K.2    Thomas, L.3
  • 16
    • 0041511823 scopus 로고    scopus 로고
    • The capacitated lot sizing problem: A review of models and algorithms
    • DOI 10.1016/S0305-0483(03)00059-8, PII S0305048303000598
    • Karimi, B., Fatemi Ghomi, S., and Wilson, J., 2003. The capacitated lot sizing problem: Review of models and algorithms. OMEGA, 31 (5), 365-378. (Pubitemid 37007074)
    • (2003) Omega , vol.31 , Issue.5 , pp. 365-378
    • Karimi, B.1    Fatemi Ghomi, S.M.T.2    Wilson, J.M.3
  • 17
    • 79958772189 scopus 로고    scopus 로고
    • Capacitated lotsizing and scheduling with sequence-dependentperiod overlapping and non-triangular setups
    • Menezes, A.A., Clark, A., and Almada-Lobo, B., 2011. Capacitated lotsizing and scheduling with sequence-dependentperiod overlapping and non-triangular setups. Journal of Scheduling, 14 (2), 209-219.
    • (2011) Journal of Scheduling , vol.14 , Issue.2 , pp. 209-219
    • Menezes, A.A.1    Clark, A.2    Almada-Lobo, B.3
  • 18
    • 0036604813 scopus 로고    scopus 로고
    • Simultaneous lotsizing and scheduling on parallel machines
    • DOI 10.1016/S0377-2217(01)00373-3, PII S0377221701003733
    • Meyr, H., 2002. Simultaneous lotsizing and scheduling on parallel machines. European Journal of Operational Research, 139 (2), 277-292. (Pubitemid 34201239)
    • (2002) European Journal of Operational Research , vol.139 , Issue.2 , pp. 277-292
    • Meyr, H.1
  • 19
    • 11144322231 scopus 로고    scopus 로고
    • Scheduling-Framework für Jobs auf parallelen Maschinen in komplexen Produktionssystemen
    • Mönch, L., 2004. Scheduling-Framework fü r Jobs auf parallelen Maschinen in komplexen Produktionssystemen. Wirtschaftsinformatik, 46 (6), 470-480. (Pubitemid 40030836)
    • (2004) Wirtschaftsinformatik , vol.46 , Issue.6 , pp. 470-480
    • Monch, L.1
  • 21
    • 27944503347 scopus 로고    scopus 로고
    • Conceptual framework for lot-sizing and scheduling of flexible flow lines
    • DOI 10.1080/00207540500066762
    • Quadt, D. and Kuhn, H., 2005. Conceptual framework for lot-sizing and scheduling of flexible flow lines. International Journal of Production Research, 43 (11), 2291-2308. (Pubitemid 41663551)
    • (2005) International Journal of Production Research , vol.43 , Issue.11 , pp. 2291-2308
    • Quadt, D.1    Kuhn, H.2
  • 22
    • 39449098494 scopus 로고    scopus 로고
    • Capacitated lot-sizing with extensions: A review
    • Quadt, D. and Kuhn, H., 2008. Capacitated lot-sizing with extensions: A review. 4OR, 6 (1), 61-83.
    • (2008) 4OR , vol.6 , Issue.1 , pp. 61-83
    • Quadt, D.1    Kuhn, H.2
  • 23
    • 0141675994 scopus 로고    scopus 로고
    • The capacitated lot-sizing problems with linked lot sizes
    • Suerie, C. and Stadtler, H., 2003. The capacitated lot-sizing problems with linked lot sizes. Management Science, 49 (8), 1039-1054.
    • (2003) Management Science , vol.49 , Issue.8 , pp. 1039-1054
    • Suerie, C.1    Stadtler, H.2
  • 24
    • 41549111411 scopus 로고    scopus 로고
    • Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource
    • DOI 10.1016/j.ijpe.2007.10.001, PII S092552730700299X
    • Tempelmeier, H. and Buschkü hl, L., 2008. Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource. International Journal of Production Economics, 113 (1), 401-412. (Pubitemid 351467151)
    • (2008) International Journal of Production Economics , vol.113 , Issue.1 , pp. 401-412
    • Tempelmeier, H.1    Buschkuhl, L.2
  • 25
    • 68949180552 scopus 로고    scopus 로고
    • Multi-population genetic algorithm to solve the synchronized and integrated two-level lot sizing and scheduling problem
    • Toledo, C., et al., 2009. Multi-population genetic algorithm to solve the synchronized and integrated two-level lot sizing and scheduling problem. International Journal of Production Research, 47 (11), 3097-3119.
    • (2009) International Journal of Production Research , vol.47 , Issue.11 , pp. 3097-3119
    • Toledo, C.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.