Volumn 17, Issue 3, 2011, Pages 445-455

Project performance monitoring methods used in Malaysia and perspectives of introducing EVA as a standard approach

Author keywords

Civil engineering; Construction industry; Earned value analysis (EVA); Performance forecasting; Project management; Project monitoring

Indexed keywords

CONSTRUCTION PROJECTS; EARNED VALUE ANALYSIS; FLOWCHART DEVELOPMENT; FUTURE PERFORMANCE; FUZZY LOGIC MODEL; INTERVIEW SURVEY; MALAYSIA; MALAYSIAN CONSTRUCTION INDUSTRY; MALAYSIANS; MANUFACTURING INDUSTRIES; PERFORMANCE FORECASTING; PROJECT CONTROL; PROJECT MANAGEMENT TOOLS; PROJECT MONITORING; PROJECT PERFORMANCE; QUALITATIVE APPROACH; STOCHASTIC METHODS;

EID: 81255188585     PISSN: 13923730     EISSN: 18223605     Source Type: Journal    
DOI: 10.3846/13923730.2011.598331     Document Type: Article
Times cited : (15)

References (52)
  • 1
    • 0037643725 scopus 로고    scopus 로고
    • Earned value management - Reconciling government and commercial practices
    • Abba, W. 1996. Earned Value Management - Reconciling government and commercial practices, Program Manager 26(1): 58-63.
    • (1996) Program Manager , vol.26 , Issue.1 , pp. 58-63
    • Abba, W.1
  • 2
    • 33645957411 scopus 로고    scopus 로고
    • Earned value project management method and extensions
    • Anbari, F. T. 2003. Earned Value Project Management Method and Extensions, Project Management Journal 34(4): 12-23.
    • (2003) Project Management Journal , vol.34 , Issue.4 , pp. 12-23
    • Anbari, F.T.1
  • 3
    • 0033690430 scopus 로고    scopus 로고
    • Probabilistic monitoring of project performance using ss-curves
    • doi:10.1061/(ASCE)0733-9364(2000)126:2(142
    • Barraza, G. A.; Back, W. E.; Mata, F. 2000. Probabilistic Monitoring of Project Performance Using SS-Curves, Journal of Construction Engineering and Management ASCE 126(2): 142-148. doi:10.1061/(ASCE)0733-9364(2000)126:2(142)
    • (2000) Journal of Construction Engineering and Management ASCE , vol.126 , Issue.2 , pp. 142-148
    • Barraza, G.A.1    Back, W.E.2    Mata, F.3
  • 4
    • 13944254406 scopus 로고    scopus 로고
    • Probabilistic forecasting of project performance using stochastic s curves
    • doi:10.1061/(ASCE)0733-9364(2004)130:1(25
    • Barraza, G. A.; Back, W. E.; Mata, F. 2004. Probabilistic Forecasting of Project Performance Using Stochastic S Curves, Journal of Construction Engineering and Management ASCE 130(1): 25-32. doi:10.1061/(ASCE)0733-9364(2004) 130:1(25)
    • (2004) Journal of Construction Engineering and Management ASCE , vol.130 , Issue.1 , pp. 25-32
    • Barraza, G.A.1    Back, W.E.2    Mata, F.3
  • 5
    • 0002382548 scopus 로고    scopus 로고
    • Implementing earned value easily and effectively
    • Brandon, J. D. M. 1998. Implementing Earned Value Easily and Effectively, Project Management Journal 29(2): 11-18.
    • (1998) Project Management Journal , vol.29 , Issue.2 , pp. 11-18
    • Brandon, J.D.M.1
  • 7
    • 81255203793 scopus 로고    scopus 로고
    • A practical guide to earned value project management
    • USA
    • Budd, C. I.; Budd, C. S. 2005. A Practical Guide to Earned Value Project Management. Management Concepts, USA. 314 p.
    • (2005) Management Concepts , pp. 314
    • Budd, C.I.1    Budd, C.S.2
  • 9
    • 70449587321 scopus 로고    scopus 로고
    • A model for updating project s-curve by using neural networks and matching progress
    • doi:10.1016/j.autcon.2009.09.006
    • Chao, L.-C.; Chien, C.-F. 2010. A Model for Updating Project S-curve by Using Neural Networks and Matching Progress, Automation in Construction 19(1): 84-91. doi:10.1016/j.autcon.2009.09.006
    • (2010) Automation in Construction , vol.19 , Issue.1 , pp. 84-91
    • Chao, L.-C.1    Chien, C.-F.2
  • 15
    • 0026840652 scopus 로고
    • An algorithm for tracking labor cost
    • Eldin, N. N.; Hughes, R. K. 1992. An Algorithm for Tracking Labor Cost, Cost Engineering 34(4): 17-23.
    • (1992) Cost Engineering , vol.34 , Issue.4 , pp. 17-23
    • Eldin, N.N.1    Hughes, R.K.2
  • 16
    • 4644288237 scopus 로고
    • Cost/schedule control systems criteria under inflation
    • Farid, F.; Karshenas, S. 1988. Cost/Schedule Control Systems Criteria under Inflation, Project Management Journal 19(5): 23-29.
    • (1988) Project Management Journal , vol.19 , Issue.5 , pp. 23-29
    • Farid, F.1    Karshenas, S.2
  • 17
    • 0028733964 scopus 로고
    • The essence of evaluation of earned value
    • Fleming, Q. W.; Koppelman, J. M. 1994. The Essence of Evaluation of Earned Value, Cost Engineering 36(11): 21-27.
    • (1994) Cost Engineering , vol.36 , Issue.11 , pp. 21-27
    • Fleming, Q.W.1    Koppelman, J.M.2
  • 19
    • 57449100285 scopus 로고    scopus 로고
    • Using earned value management
    • Fleming, Q. W.; Koppelman, J. M. 2002. Using Earned Value Management, Cost Engineering 44(9): 32-36.
    • (2002) Cost Engineering , vol.44 , Issue.9 , pp. 32-36
    • Fleming, Q.W.1    Koppelman, J.M.2
  • 21
    • 0036319174 scopus 로고    scopus 로고
    • Underestimating cost in public works project: Error or lie?
    • doi:10.1080/01944360208976273
    • Flyvbjerg, B.; Holm, M. S.; Buhl, S. 2002. Underestimating cost in public works project: Error or Lie?, Journal of the American Planning Association (APA) 68(3): 279-295. doi:10.1080/01944360208976273
    • (2002) Journal of the American Planning Association APA , vol.68 , Issue.3 , pp. 279-295
    • Flyvbjerg, B.1    Holm, M.S.2    Buhl, S.3
  • 22
    • 0041545757 scopus 로고
    • Preliminary cumulative cash flow analysis
    • Gates, M.; Scarpa, A. 1979. Preliminary cumulative cash flow analysis, Cost Engineering 21(6): 243-249.
    • (1979) Cost Engineering , vol.21 , Issue.6 , pp. 243-249
    • Gates, M.1    Scarpa, A.2
  • 23
    • 84992944192 scopus 로고    scopus 로고
    • Improving the performance of earned value analysis as a construction project management tool
    • Howes, R. 2000. Improving the Performance of Earned Value Analysis as a Construction Project Management Tool, Engineering, Construction and Architecture 7(4): 399-411.
    • (2000) Engineering, Construction and Architecture , vol.7 , Issue.4 , pp. 399-411
    • Howes, R.1
  • 24
    • 70449406277 scopus 로고    scopus 로고
    • Designing a progress simulator for estimation of project completion cost and time
    • Petaling Jaya, Malaysia, 18-20 November, 2008
    • Iranmanesh, S. H.; Hojati, Z. T. 2008. Designing a progress simulator for estimation of project completion cost and time, in Proc. of the International Conference on Project Management (ICoPM), Petaling Jaya, Malaysia, 18-20 November, 2008, 120-127.
    • (2008) Proc. of the International Conference on Project Management (ICoPM) , pp. 120-127
    • Iranmanesh, S.H.1    Hojati, Z.T.2
  • 25
    • 0006767477 scopus 로고
    • A construction project cash flow model - An idiographic approach
    • Kenley, R.; Wilson, O. D. 1986. A construction project cash flow model - an idiographic approach, Construction Management and Economics 4(3): 213-232.
    • (1986) Construction Management and Economics , vol.4 , Issue.3 , pp. 213-232
    • Kenley, R.1    Wilson, O.D.2
  • 28
    • 0041059064 scopus 로고
    • Simulation of expenditure patterns of construction projects
    • doi:10.1080/01446199100000011
    • Khosrowshahi, F. 1991. Simulation of expenditure patterns of construction projects, Construction Management and Economics 9(2): 113-132. doi:10.1080/01446199100000011
    • (1991) Construction Management and Economics , vol.9 , Issue.2 , pp. 113-132
    • Khosrowshahi, F.1
  • 29
    • 0038721043 scopus 로고    scopus 로고
    • A model for effective implementation of earned value management methodology
    • doi:10.1016/S0263-7863(02)00049-2
    • Kim, E. H.; Wells, J. W. G.; Duffey, M. R. 2003. A model for effective implementation of earned value management methodology, International Journal of Project Management 21(5): 375-382. doi:10.1016/S0263-7863(02)00049-2
    • (2003) International Journal of Project Management , vol.21 , Issue.5 , pp. 375-382
    • Kim, E.H.1    Wells, J.W.G.2    Duffey, M.R.3
  • 30
    • 12744251343 scopus 로고    scopus 로고
    • Use of fuzzy logic for predicting design cost overruns on building projects
    • doi:10.1061/(ASCE)0733-9364(2002)128:6(503
    • Knight, K.; Fayek, A. R. 2002. Use of Fuzzy Logic for Predicting Design Cost Overruns on Building Projects, Journal of Construction Engineering and Management ASCE 128(6): 503-512. doi:10.1061/(ASCE)0733-9364(2002)128:6(503)
    • (2002) Journal of Construction Engineering and Management ASCE , vol.128 , Issue.6 , pp. 503-512
    • Knight, K.1    Fayek, A.R.2
  • 31
    • 81255207349 scopus 로고    scopus 로고
    • Improving traditional earned value management by incorporating statistical process charts
    • Tokyo, Japan
    • Leu, S.-S.; Lin, Y.-C.; Chen, T.-A.; Ho, Y.-Y. 2006. Improving traditional earned value management by incorporating statistical process charts, in Proc. of the 23rd ISARC 2006, Tokyo, Japan, 275-280.
    • (2006) Proc. of the 23rd ISARC 2006 , pp. 275-280
    • Leu, S.-S.1    Lin, Y.-C.2    Chen, T.-A.3    Ho, Y.-Y.4
  • 35
    • 64449085007 scopus 로고    scopus 로고
    • Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes
    • doi:10.1016/j.ijproman.2008.02.009
    • Lipke, W.; Zwikael, O.; Henderson, K.; Anbari, F. 2009. Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes, International Journal of Project Management 27(4): 400-107. doi:10.1016/j.ijproman.2008.02.009
    • (2009) International Journal of Project Management , vol.27 , Issue.4 , pp. 400-107
    • Lipke, W.1    Zwikael, O.2    Henderson, K.3    Anbari, F.4
  • 36
    • 81255205087 scopus 로고    scopus 로고
    • The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners
    • Marshall, R. A. 2007. The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners, Journal of Contract Management 4: 21-33.
    • (2007) Journal of Contract Management , vol.4 , pp. 21-33
    • Marshall, R.A.1
  • 37
    • 81255207350 scopus 로고
    • Momentum theory: A new technique for cost analysis
    • AACE International, Morgantown, WV
    • Mazzini, R. A. 1991. Momentum Theory: A New Technique for Cost Analysis. RACE Transactions, 1.4, AACE International, Morgantown, WV. 10 p.
    • (1991) RACE Transactions , vol.1 , Issue.4 , pp. 10
    • Mazzini, R.A.1
  • 38
    • 0022043393 scopus 로고
    • Earned value technique for performance measurements
    • doi: 10.1061/(ASCE)9742-597X(1985)1:2(79)
    • McConnell, D. R. 1985. Earned Value Technique for Performance Measurements, Journal of Management in Engineering ASCE 1(2): 79-94. doi: 10.1061/(ASCE)9742-597X(1985)1:2(79)
    • (1985) Journal of Management in Engineering ASCE , vol.1 , Issue.2 , pp. 79-94
    • McConnell, D.R.1
  • 39
    • 0041059063 scopus 로고
    • An S-curve equation for project control
    • Miskawi, Z. 1989. An S-curve equation for project control, Construction Management and Economics 7(2): 115-124.
    • (1989) Construction Management and Economics , vol.7 , Issue.2 , pp. 115-124
    • Miskawi, Z.1
  • 40
    • 0041545758 scopus 로고    scopus 로고
    • Cash flow forecasting and updating for building projects
    • Navon, R. 1996. Cash flow forecasting and updating for building projects, Project Management Journal 27(2):14-23
    • (1996) Project Management Journal , vol.27 , Issue.2 , pp. 14-23
    • Navon, R.1
  • 42
    • 0020138987 scopus 로고
    • Application of cost-flow forecasting models
    • Peer, S. 1982. Application of cost-flow forecasting models, Journal of the Construction Division ASCE 108(2): 226-232.
    • (1982) Journal of the Construction Division ASCE , vol.108 , Issue.2 , pp. 226-232
    • Peer, S.1
  • 43
    • 58049139009 scopus 로고    scopus 로고
    • Project Management Institute (PMI). 3rd ed. Newton Square PA: Project Management Institute
    • Project Management Institute (PMI). 2004a. A Guide to the Project Management Body of Knowledge. 3rd ed. Newton Square, PA: Project Management Institute. 380 p.
    • (2004) A Guide to the Project Management Body of Knowledge , pp. 380
  • 44
    • 81255207347 scopus 로고    scopus 로고
    • Project Management Institute (PMI) Newton Square, PA: Project Management Institute
    • Project Management Institute (PMI). 2004b. Practice Standard for Earned Value Management. Newton Square, PA: Project Management Institute. 51 p.
    • (2004) Standard for Earned Value Management , pp. 51
  • 45
    • 46549101788 scopus 로고
    • Cost and schedule data analysis and forecasting
    • doi:10.1016/0263-7863(85)90042-0
    • Seiler, J. 1985. Cost and schedule data analysis and forecasting, International Journal of Project Management 3(1): 45-49. doi:10.1016/0263- 7863(85)90042-0
    • (1985) International Journal of Project Management , vol.3 , Issue.1 , pp. 45-49
    • Seiler, J.1
  • 46
    • 0003480493 scopus 로고
    • Technology and Implementation Prentice Hall Inc., Englewood Cliffs, N.J
    • Shtub, A.; Bard, J. F.; Globerson, S. 1994. Project Manage-ment: Engineering, Technology and Implementation. Prentice Hall, Inc., Englewood Cliffs, N.J. 656 p.
    • (1994) Project Manage-ment:Engineering , pp. 656
    • Shtub, A.1    Bard, J.F.2    Globerson, S.3
  • 47
    • 0038604047 scopus 로고    scopus 로고
    • Forecast model for actual construction time and cost
    • doi:10.1016/S0360-1323(03)00067-2
    • Skitmore, R. M.; Ng, S. T. 2003. Forecast Model for Actual Construction Time and Cost, Building and Environment 38(8): 1075-1083. doi:10.1016/S0360- 1323(03)00067-2
    • (2003) Building and Environment , vol.38 , Issue.8 , pp. 1075-1083
    • Skitmore, R.M.1    Ng, S.T.2
  • 48
    • 0013337442 scopus 로고    scopus 로고
    • A proposal for construction project risk assessment using fuzzy logic
    • doi:10.1080/01446190050024905
    • Tah, J. H. M.; Carr, V. 2000. A proposal for construction project risk assessment using fuzzy logic, Construction Management and Economics 18(4): 491-500. doi:10.1080/01446190050024905
    • (2000) Construction Management and Economics , vol.18 , Issue.4 , pp. 491-500
    • Tah, J.H.M.1    Carr, V.2
  • 49
    • 0004551332 scopus 로고
    • A single alternative formula for department of health and social security s-curves
    • Tucker, S. N. 1988. A single alternative formula for Department of Health and Social Security S-curves, Construction Management and Economics 6(1): 13-23.
    • (1988) Construction Management and Economics , vol.6 , Issue.1 , pp. 13-23
    • Tucker, S.N.1
  • 50
    • 33645967441 scopus 로고    scopus 로고
    • A comparison of different project duration forecasting methods using earned value metrics
    • doi:10.1016/j.ijproman.2005.10.004
    • Vandevoorde, S.; Vanhoucke M. 2006. A comparison of different project duration forecasting methods using earned value metrics, International Journal of Project Management 24(4): 289-302. doi:10.1016/j.ijproman.2005.10.004
    • (2006) International Journal of Project Management , vol.24 , Issue.4 , pp. 289-302
    • Vandevoorde, S.1    Vanhoucke, M.2
  • 52
    • 9444236531 scopus 로고    scopus 로고
    • Evaluation of models for forecasting the final cost of a project
    • Zwikael, O.; Globerson, S.; Raz, T. 2000. Evaluation of Models for Forecasting the Final Cost of a Project, Project Management Journal 31(1): 53-57.
    • (2000) Project Management Journal , vol.31 , Issue.1 , pp. 53-57
    • Zwikael, O.1    Globerson, S.2    Raz, T.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.