Incorporating geological and market uncertainties and operational flexibility into open pit mine design

Author keywords

Economic evaluation; Mine design; Monte Carlo simulation; Real options

Indexed keywords

COPPER MINES; INTELLIGENT SYSTEMS; MONTE CARLO METHODS; UNCERTAINTY ANALYSIS;

EID: 80855138603     PISSN: 10627391     EISSN: None     Source Type: Journal    
DOI: 10.1134/S1062739147020067     Document Type: Article
Times cited : (38)

References (26)
  • 2
    • 33750463056 scopus 로고    scopus 로고
    • The new fundamental tree algorithm for production scheduling of open pit mines
    • S. Ramazan, "The new fundamental tree algorithm for production scheduling of open pit mines," European Journal of Operations Research, 177 (2007).
    • (2007) European Journal of Operations Research , vol.177
    • Ramazan, S.1
  • 3
    • 67649229013 scopus 로고    scopus 로고
    • Stochastic integer programming for optimizing long-term production schedules of open pit mines: Methods, application and value of stochastic solutions
    • R. Dimitrakopoulos and S. Ramazan, "Stochastic integer programming for optimizing long-term production schedules of open pit mines: Methods, application and value of stochastic solutions," IMM Transactions, Mining Technology, 117 (2008).
    • (2008) IMM Transactions, Mining Technology , vol.117
    • Dimitrakopoulos, R.1    Ramazan, S.2
  • 4
    • 58149247670 scopus 로고    scopus 로고
    • Multi-period quarry production planning through sequencing techniques and sequencing algorithm
    • M. W. A. Asad, "Multi-period quarry production planning through sequencing techniques and sequencing algorithm," Journal of Mining Science, 44 (2008).
    • (2008) Journal of Mining Science , vol.44
    • Asad, M.W.A.1
  • 6
    • 0034021292 scopus 로고    scopus 로고
    • Mineral resource + engineering, economic and legal feasibility = ore reserve
    • M. Vallee, "Mineral resource + engineering, economic and legal feasibility = ore reserve," CIM Bulletin, 93 (2000).
    • (2000) CIM Bulletin , vol.93
    • Vallee, M.1
  • 8
    • 33750463822 scopus 로고    scopus 로고
    • Managing risk and waste mining in long-term production scheduling
    • M. C. Godoy and R. Dimitrakopoulos, "Managing risk and waste mining in long-term production scheduling," SME Transactions, 316 (2004).
    • (2004) SME Transactions , vol.316
    • Godoy, M.C.1    Dimitrakopoulos, R.2
  • 10
    • 34250173438 scopus 로고    scopus 로고
    • A maximum upside/minimum downside approach to the traditional optimization of open pit mine design
    • R. Dimitrakopoulos, L. S. Martinez, and S. Ramazan, "A maximum upside/minimum downside approach to the traditional optimization of open pit mine design," Journal of Mining Science, 43 (2007).
    • (2007) Journal of Mining Science , vol.43
    • Dimitrakopoulos, R.1    Martinez, L.S.2    Ramazan, S.3
  • 11
    • 68049137575 scopus 로고    scopus 로고
    • Stope design and geological uncertainty: Quantification of risk in conventional designs and a probabilistic alternative
    • R. Dimitrakopoulos and N. Grieco, "Stope design and geological uncertainty: Quantification of risk in conventional designs and a probabilistic alternative," Journal of Mining Science, 45 (2009).
    • (2009) Journal of Mining Science , vol.45
    • Dimitrakopoulos, R.1    Grieco, N.2
  • 12
    • 80855164935 scopus 로고    scopus 로고
    • A risk analysis based framework for strategic mine planning and design method and application
    • M. Godoy and R. Dimitrakopoulos, "A risk analysis based framework for strategic mine planning and design method and application," Journal of Mining Science, 47 (2011).
    • (2011) Journal of Mining Science , vol.47
    • Godoy, M.1    Dimitrakopoulos, R.2
  • 14
    • 1642581349 scopus 로고    scopus 로고
    • Decision making under uncertainty-real options to the rescue?
    • L.T. Miller and C.S. Park, "Decision making under uncertainty-real options to the rescue?" The Engineering Economist, 47, No 2 (2002).
    • (2002) The Engineering Economist , vol.47 , Issue.2
    • Miller, L.T.1    Park, C.S.2
  • 15
    • 0036116622 scopus 로고    scopus 로고
    • When are real options exercised? An empirical study of mine closings
    • A. Moel and P. Tufano, "When are real options exercised? An empirical study of mine closings," Review Financial Studies, 15, No. 1 (2002).
    • (2002) Review Financial Studies , vol.15 , Issue.1
    • Moel, A.1    Tufano, P.2
  • 16
    • 33646749499 scopus 로고    scopus 로고
    • Valuing uncertain asset cash flows when there are no options: A real options approach
    • M. Samis, G. A. Davis, D. Laughton, and R. Poulin, "Valuing uncertain asset cash flows when there are no options: A real options approach," Resources Policy, 30 (2006).
    • (2006) Resources Policy , vol.30
    • Samis, M.1    Davis, G.A.2    Laughton, D.3    Poulin, R.4
  • 17
    • 0035708319 scopus 로고    scopus 로고
    • Valuing managerial flexibility: An application of real option theory to mining investments
    • M. E. Slade, "Valuing managerial flexibility: an application of real option theory to mining investments," Journal of Environmental Economics and Management, 41 (2001).
    • (2001) Journal of Environmental Economics and Management , vol.41
    • Slade, M.E.1
  • 18
    • 59649089555 scopus 로고    scopus 로고
    • Block-support simulation of multiple correlated variables
    • A. Boucher and R. Dimitrakopoulos, "Block-support simulation of multiple correlated variables," Mathematical Geosciences, 41 (2009).
    • (2009) Mathematical Geosciences , vol.41
    • Boucher, A.1    Dimitrakopoulos, R.2
  • 19
    • 67349161808 scopus 로고    scopus 로고
    • Representing spatial uncertainty using distances and kernels
    • C. Scheidt and J. Caers, "Representing spatial uncertainty using distances and kernels," Mathematical Geosciences, 41 (2009).
    • (2009) Mathematical Geosciences , vol.41
    • Scheidt, C.1    Caers, J.2
  • 20
    • 0000792991 scopus 로고    scopus 로고
    • The stochastic behaviour of commodity prices: Implications for valuation and hedging
    • E. S. Schwartz, "The stochastic behaviour of commodity prices: implications for valuation and hedging," Journal of Finance, 52 (1997).
    • (1997) Journal of Finance , vol.52
    • Schwartz, E.S.1
  • 21
    • 0035578679 scopus 로고    scopus 로고
    • Valuing American options by simulation: A simple least-squares approach
    • F. A. Longstaff and E. S. Schwartz, "Valuing American options by simulation: a simple least-squares approach," The Review of Financial Studies, 14 (2001).
    • (2001) The Review of Financial Studies , vol.14
    • Longstaff, F.A.1    Schwartz, E.S.2
  • 22
    • 33744962817 scopus 로고    scopus 로고
    • Valuing real capital investments using the least-squares Monte Carlo method
    • S. A. Abdel Sabour and R. Poulin, "Valuing real capital investments using the least-squares Monte Carlo method," The Engineering Economist, 51 (2006).
    • (2006) The Engineering Economist , vol.51
    • Poulin, R.1
  • 23
    • 35448937145 scopus 로고    scopus 로고
    • Evaluating mine plans under uncertainty: Can the real options make a difference?
    • R. Dimitrakopoulos and S. A. Abdel Sabour, "Evaluating mine plans under uncertainty: Can the real options make a difference?" Resources Policy, 32 (2007).
    • (2007) Resources Policy , vol.32
    • Dimitrakopoulos, R.1    Abdel Sabour, S.A.2
  • 26
    • 0005695679 scopus 로고    scopus 로고
    • A decade of open pit mine planning and optimization-The craft of turning algorithms into packages
    • Colorado School of Mines, Golden
    • J. Whittle, "A decade of open pit mine planning and optimization-The craft of turning algorithms into packages," in: APCOM'99 Computer Applications in the Minerals Industries 28th International Symposium, Colorado School of Mines, Golden (1999).
    • (1999) APCOM'99 Computer Applications in the Minerals Industries 28th International Symposium
    • Whittle, J.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.