메뉴 건너뛰기




Volumn 50, Issue 9-12, 2010, Pages 1165-1174

Integrating lotsizing, loading, and scheduling decisions in flexible flow shops

Author keywords

Flexible flow shop; Lotsizing and scheduling; MIP based algorithm; Relax and fix; Sequence dependent

Indexed keywords

FLEXIBLE FLOW SHOP; LOT SIZING; MIP-BASED ALGORITHM; RELAX-AND-FIX; SEQUENCE-DEPENDENT;

EID: 77957875910     PISSN: 02683768     EISSN: 14333015     Source Type: Journal    
DOI: 10.1007/s00170-010-2594-6     Document Type: Article
Times cited : (12)

References (24)
  • 1
    • 34548460398 scopus 로고    scopus 로고
    • Single machine multi-product capacitated lot sizing with sequence-dependent setups
    • DOI 10.1080/00207540601094465, PII 772294284
    • B Almada-Lobo D Klabjan M-A Carravilla J Oliveira 2007 Single machine multi-product capacitated lot sizing with sequence-dependent setups Int J Prod Res 45 20 4873 4894 1126.90018 10.1080/00207540601094465 (Pubitemid 47352796)
    • (2007) International Journal of Production Research , vol.45 , Issue.20 , pp. 4873-4894
    • Almada-Lobo, B.1    Klabjan, D.2    Carravilla, M.A.3    Oliveira, J.F.4
  • 2
    • 34547145422 scopus 로고    scopus 로고
    • Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups
    • DOI 10.1007/s10732-007-9011-9, Special CLAIO XII Issue on Advances and Applications of Heuristics
    • S-A Araujo M-N Arenales A-R Clark 2007 Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups J Heuristics 13 4 337 358 10.1007/s10732-007-9011-9 (Pubitemid 47117880)
    • (2007) Journal of Heuristics , vol.13 , Issue.4 , pp. 337-358
    • De Araujo, S.A.1    Arenales, M.N.2    Clark, A.R.3
  • 3
    • 34548453509 scopus 로고    scopus 로고
    • Lot sizing and furnace scheduling in small foundries
    • DOI 10.1016/j.cor.2006.05.010, PII S0305054806001390
    • S-A Araujo M-N Arenales A-R Clark 2008 Lot sizing and furnace scheduling in small foundries Comput Operat Res 35 3 916 932 05202109 10.1016/j.cor.2006. 05.010 (Pubitemid 47368854)
    • (2008) Computers and Operations Research , vol.35 , Issue.3 , pp. 916-932
    • De Araujo, S.A.1    Arenales, M.N.2    Clark, A.R.3
  • 4
    • 41149118126 scopus 로고    scopus 로고
    • Rolling-horizon and fix-and-relax heuristics for the parallel machine lot-sizing and scheduling problem with sequence-dependent set-up costs
    • DOI 10.1016/j.cor.2007.04.003, PII S0305054807000858
    • P Beraldi G Ghiani A Grieco E Guerriero 2008 Rolling-horizon and fix-and-relax heuristics for the parallel machine lot-sizing and scheduling problem with sequence-dependent set-up costs Comput Operat Res 35 11 3644 3656 1170.90386 10.1016/j.cor.2007.04.003 (Pubitemid 351443068)
    • (2008) Computers and Operations Research , vol.35 , Issue.11 , pp. 3644-3656
    • Beraldi, P.1    Ghiani, G.2    Grieco, A.3    Guerriero, E.4
  • 5
    • 0037432979 scopus 로고    scopus 로고
    • Optimization approximations for capacity constrained material requirements planning
    • 10.1016/S0925-5273(02)00400-0
    • A-R Clark 2003 Optimization approximations for capacity constrained material requirements planning Int J Prod Eco 84 2 115 131 10.1016/S0925- 5273(02)00400-0
    • (2003) Int J Prod Eco , vol.84 , Issue.2 , pp. 115-131
    • Clark, A.-R.1
  • 6
    • 0034631279 scopus 로고    scopus 로고
    • Rolling-horizon lot-sizing when set-up times are sequence-dependent
    • DOI 10.1080/00207540050028106
    • A-R Clark S-J Clark 2000 Rolling-horizon lot-sizing when setup times are sequence-dependent Int J Prod Res 38 10 2287 2308 0973.90517 10.1080/00207540050028106 (Pubitemid 35401851)
    • (2000) International Journal of Production Research , vol.38 , Issue.10 , pp. 2287-2307
    • Clark, A.R.1    Clark, S.J.2
  • 8
    • 0028769399 scopus 로고
    • On practical resource allocation for production planning and scheduling with period overlapping setups
    • 0806.90055 10.1016/0377-2217(94)90074-4
    • C Dillenberger L-F Escudero A Wollensak W Zhang 1994 On practical resource allocation for production planning and scheduling with period overlapping setups Eur Oper Res 75 2 275 286 0806.90055 10.1016/0377-2217(94) 90074-4
    • (1994) Eur Oper Res , vol.75 , Issue.2 , pp. 275-286
    • Dillenberger, C.1    Escudero, L.-F.2    Wollensak, A.3    Zhang, W.4
  • 9
    • 0031170482 scopus 로고    scopus 로고
    • Lot sizing and scheduling, survey and extensions
    • 0923.90067 10.1016/S0377-2217(97)00030-1
    • A Drexl A Kimms 1997 Lot sizing and scheduling, survey and extensions Eur J Oper Res 99 2 221 235 0923.90067 10.1016/S0377-2217(97)00030-1
    • (1997) Eur J Oper Res , vol.99 , Issue.2 , pp. 221-235
    • Drexl, A.1    Kimms, A.2
  • 10
    • 0023456043 scopus 로고
    • Solving multi-item capacitated lot-sizing problems using variable redefinition
    • 0639.90046 10.1287/opre.35.6.832
    • G-D Eppen R-K Martin 1987 Solving multi-item capacitated lot-sizing problems using variable redefinition Operat Res 35 6 832 848 0639.90046 10.1287/opre.35.6.832
    • (1987) Operat Res , vol.35 , Issue.6 , pp. 832-848
    • Eppen, G.-D.1    Martin, R.-K.2
  • 11
    • 33748884885 scopus 로고    scopus 로고
    • Simultaneous lot sizing and scheduling for multi-product multi-level production
    • DOI 10.1016/j.ijpe.2005.04.011, PII S0925527305002240
    • G Fandel C Stammen-Hegene 2006 Simultaneous lot sizing and scheduling for multi-product multi-level production Int J Prod Eco 104 2 308 316 10.1016/j.ijpe.2005.04.011 (Pubitemid 44425413)
    • (2006) International Journal of Production Economics , vol.104 , Issue.2 , pp. 308-316
    • Fandel, G.1    Stammen-Hegene, C.2
  • 12
    • 0008655177 scopus 로고    scopus 로고
    • The general lotsizing and scheduling problem
    • 10.1007/BF01539800
    • B Fleischmannand H Meyr 1997 The general lotsizing and scheduling problem OR Spekt 19 2 11 21 10.1007/BF01539800
    • (1997) OR Spekt , vol.19 , Issue.2 , pp. 11-21
    • Fleischmannand, B.1    Meyr, H.2
  • 13
    • 33750728882 scopus 로고    scopus 로고
    • Meta-heuristics for dynamic lot sizing: A review and comparison of solution approaches
    • DOI 10.1016/j.ejor.2005.12.008, PII S0377221705008416
    • R Jans Z Degraeve 2007 Meta-heuristics for dynamic lot sizing: a review and comparison of solution approaches Eur J Oper Res 177 3 1851 1875 10.1016/j.ejor.2005.12.008 (Pubitemid 44709458)
    • (2007) European Journal of Operational Research , vol.177 , Issue.3 , pp. 1855-1875
    • Jans, R.1    Degraeve, Z.2
  • 14
    • 52049090864 scopus 로고    scopus 로고
    • A comparison of scheduling algorithms for flexible flow shop problems with unrelated parallel machines, setup times, and dual criteria
    • 1157.90417 10.1016/j.cor.2007.10.004
    • J Jungwattanakit M Reodecha P Chaovalitwonges F Werner 2009 A comparison of scheduling algorithms for flexible flow shop problems with unrelated parallel machines, setup times, and dual criteria Comput Operat Res 36 2 358 378 1157.90417 10.1016/j.cor.2007.10.004
    • (2009) Comput Operat Res , vol.36 , Issue.2 , pp. 358-378
    • Jungwattanakit, J.1    Reodecha, M.2    Chaovalitwonges, P.3    Werner, F.4
  • 15
    • 0041511823 scopus 로고    scopus 로고
    • The capacitated lot sizing problem: A review of models and algorithms
    • DOI 10.1016/S0305-0483(03)00059-8, PII S0305048303000598
    • B Karimi S-M-T Fatemi Ghomi J-M Wilson 2003 The capacitated lot sizing problem: a review of models and algorithms Omega 31 5 365 378 10.1016/S0305-0483(03)00059-8 (Pubitemid 37007074)
    • (2003) Omega , vol.31 , Issue.5 , pp. 365-378
    • Karimi, B.1    Fatemi Ghomi, S.M.T.2    Wilson, J.M.3
  • 17
    • 0042824640 scopus 로고    scopus 로고
    • Multi-level, single-machine lotsizing and scheduling (with initial inventory)
    • 0913.90135 10.1016/S0377-2217(96)90056-9
    • A Kimms 1996 Multi-level, single-machine lotsizing and scheduling (with initial inventory) Eur J Oper Res 89 1 86 99 0913.90135 10.1016/S0377-2217(96) 90056-9
    • (1996) Eur J Oper Res , vol.89 , Issue.1 , pp. 86-99
    • Kimms, A.1
  • 19
    • 1642335464 scopus 로고    scopus 로고
    • MIP-based heuristics for capacitated lotsizing problems
    • 10.1016/S0925-5273(03)00090-2
    • C Merece G Fonton 2003 MIP-based heuristics for capacitated lotsizing problems Int J Prod Eco 85 1 97 111 10.1016/S0925-5273(03)00090-2
    • (2003) Int J Prod Eco , vol.85 , Issue.1 , pp. 97-111
    • Merece, C.1    Fonton, G.2
  • 20
    • 77955661126 scopus 로고    scopus 로고
    • Rolling-horizon and fix-and-relax heuristics for the multi-product multi-level capacitated lotsizing problem with sequence-dependent setups
    • doi: 10.1007/s10845-008-0207-0
    • Mohammadi M, Fatemi Ghomi S-M-T, Karimi B, Torabi S-A (2008) Rolling-horizon and fix-and-relax heuristics for the multi-product multi-level capacitated lotsizing problem with sequence-dependent setups. J Intell Manuf. doi: 10.1007/s10845-008-0207-0
    • (2008) J Intell Manuf
    • Mohammadi, M.1    Ghomi S-M-T, F.2    Karimi, B.3    Torabi, S.-A.4
  • 21
    • 77951134643 scopus 로고    scopus 로고
    • MIP-based heuristics for lotsizing in capacitated pure flow shop with sequence-dependent setups
    • doi: 10.1080/00207540902796016
    • Mohammadi M, Fatemi Ghomi S-M-T, Karimi B, Torabi S-A (2009) MIP-based heuristics for lotsizing in capacitated pure flow shop with sequence-dependent setups. Int J Prod Res. doi: 10.1080/00207540902796016
    • (2009) Int J Prod Res
    • Mohammadi, M.1    Ghomi S-M-T, F.2    Karimi, B.3    Torabi, S.-A.4
  • 22
    • 41549111411 scopus 로고    scopus 로고
    • Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource
    • DOI 10.1016/j.ijpe.2007.10.001, PII S092552730700299X
    • H Tempelmeier L Buschkuhl 2008 Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource Int J Prod Eco 13 1 401 412 10.1016/j.ijpe.2007.10.001 (Pubitemid 351467151)
    • (2008) International Journal of Production Economics , vol.113 , Issue.1 , pp. 401-412
    • Tempelmeier, H.1    Buschkuhl, L.2
  • 24
    • 33748492325 scopus 로고    scopus 로고
    • Scheduling and lot sizing with sequence-dependent setup: A literature review
    • DOI 10.1080/07408170600559706, PII J784373L461611VQ
    • X Zhu WE Wilhelm 2006 Scheduling and lotsizing with sequence-dependent setup: a literature review IIE Trans 38 987 1007 10.1080/07408170600559706 (Pubitemid 44355862)
    • (2006) IIE Transactions (Institute of Industrial Engineers) , vol.38 , Issue.11 , pp. 987-1007
    • Zhu, X.1    Wilhelm, W.E.2