Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice

Author keywords

Cost control; Interview; Practice; Project control; Project management

Indexed keywords

COMMON FACTORS; CONSTRUCTION PROJECTS; CONTROL TECHNIQUES; COST CONTROLS; DESIGN CHANGE; DURING CONSTRUCTION; FACE-TO-FACE INTERVIEW; GOOD PRACTICES; INHIBITING FACTORS; MITIGATING MEASURES; PROJECT CONTROL; PROJECT MANAGERS; TIME CONTROL; TIME OVERRUN;

EID: 77953674695     PISSN: 01446193     EISSN: 1466433X     Source Type: Journal    
DOI: 10.1080/01446191003674519     Document Type: Article
Times cited : (299)

References (43)
  • 1
    • 0036836295 scopus 로고    scopus 로고
    • The effects of construction delays on project delivery in Nigerian construction industry
    • Aibinu, A. and Jagboro, G. (2002) The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8), 593-9.
    • (2002) International Journal of Project Management , vol.20 , Issue.8 , pp. 593-599
    • Aibinu, A.1    Jagboro, G.2
  • 2
  • 7
    • 0037402597 scopus 로고    scopus 로고
    • Modelling global risk factors affecting construction cost performance
    • Baloi, D. and Price, A. (2003) Modelling global risk factors affecting construction cost performance. International Journal of Project Management, 21(4), 261-9.
    • (2003) International Journal of Project Management , vol.21 , Issue.4 , pp. 261-269
    • Baloi, D.1    Price, A.2
  • 8
    • 0031078243 scopus 로고    scopus 로고
    • A comparative study of causes of time overruns in Hong Kong construction projects
    • Chan, D. and Kumaraswamy, M. (1997) A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), 55-63.
    • (1997) International Journal of Project Management , vol.15 , Issue.1 , pp. 55-63
    • Chan, D.1    Kumaraswamy, M.2
  • 10
    • 0036162657 scopus 로고    scopus 로고
    • Reasons for cost and schedule increase for engineering design projects
    • Chang, A. (2002) Reasons for cost and schedule increase for engineering design projects. Journal of Management in Engineering, 18(1), 29-36.
    • (2002) Journal of Management In Engineering , vol.18 , Issue.1 , pp. 29-36
    • Chang, A.1
  • 13
    • 38249017819 scopus 로고
    • Reasons for over-run in public sector construction projects in Nigeria
    • Dlakwa, M.M. and Culpin, M.F. (1990) Reasons for over-run in public sector construction projects in Nigeria. International Journal of Project Management, 8(4), 237-40.
    • (1990) International Journal of Project Management , vol.8 , Issue.4 , pp. 237-240
    • Dlakwa, M.M.1    Culpin, M.F.2
  • 14
    • 12444316997 scopus 로고    scopus 로고
    • Planning and control processes and techniques for refurbishment management
    • Egbu, C., Young, B. and Torrance, V. (1998) Planning and control processes and techniques for refurbishment management. Construction Management and Economics, 16, 315-25.
    • (1998) Construction Management and Economics , vol.16 , pp. 315-325
    • Egbu, C.1    Young, B.2    Torrance, V.3
  • 16
    • 0037242979 scopus 로고    scopus 로고
    • How common and how large are cost overruns in transport infrastructure projects?
    • Flyvbjerg, B., Holm, M. and Buhl, S. (2003) How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71-88.
    • (2003) Transport Reviews , vol.23 , Issue.1 , pp. 71-88
    • Flyvbjerg, B.1    Holm, M.2    Buhl, S.3
  • 17
    • 0038721064 scopus 로고    scopus 로고
    • Causes of delay and cost overruns in construction of groundwater projects in a developing country: Ghana as a case study
    • Frimpong, Y., Oluwoye, J. and Crawford, L. (2003) Causes of delay and cost overruns in construction of groundwater projects in a developing country: Ghana as a case study. International Journal of Project Management, 21(5), 321-6.
    • (2003) International Journal of Project Management , vol.21 , Issue.5 , pp. 321-326
    • Frimpong, Y.1    Oluwoye, J.2    Crawford, L.3
  • 18
    • 14744299396 scopus 로고    scopus 로고
    • Budget and schedule success for small capital-facility projects
    • Gao, Z., Smith, G. and Minchin, R. (2002) Budget and schedule success for small capital-facility projects. Journal of Management in Engineering, 18(4), 186-93.
    • (2002) Journal of Management In Engineering , vol.18 , Issue.4 , pp. 186-193
    • Gao, Z.1    Smith, G.2    Minchin, R.3
  • 19
    • 5444225548 scopus 로고    scopus 로고
    • Statistical analysis of causes for change orders in metropolitan public works
    • Hsieh, T., Lu, S. and Wu, C. (2004) Statistical analysis of causes for change orders in metropolitan public works. International Journal of Project Management, 22(8), 679-86.
    • (2004) International Journal of Project Management , vol.22 , Issue.8 , pp. 679-686
    • Hsieh, T.1    Lu, S.2    Wu, C.3
  • 20
    • 18144374111 scopus 로고    scopus 로고
    • Factors affecting cost performance: Evidence from Indian construction projects
    • Iyer, K. and Jha, K. (2005) Factors affecting cost performance: evidence from Indian construction projects. International Journal of Project Management, 23(4), 283-95.
    • (2005) International Journal of Project Management , vol.23 , Issue.4 , pp. 283-295
    • Iyer, K.1    Jha, K.2
  • 21
    • 0039997969 scopus 로고    scopus 로고
    • Factors influencing construction time and cost overruns on high-rise projects in Indonesia
    • Kaming, P., Olomolaiye, P., Holt, G. and Harris, F. (1997) Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83-94.
    • (1997) Construction Management and Economics , vol.15 , Issue.1 , pp. 83-94
    • Kaming, P.1    Olomolaiye, P.2    Holt, G.3    Harris, F.4
  • 22
    • 0033905829 scopus 로고    scopus 로고
    • Professional project management practices in Kuwait: Issues, difficulties and recommendations
    • Kartam, N., Al-Daihani, T. and Bahar, J. (2000) Professional project management practices in Kuwait: issues, difficulties and recommendations. International Journal of Project Management, 18(4), 281-96.
    • (2000) International Journal of Project Management , vol.18 , Issue.4 , pp. 281-296
    • Kartam, N.1    Al-Daihani, T.2    Bahar, J.3
  • 25
    • 16444365584 scopus 로고    scopus 로고
    • Delays and cost increases in the construction of private residential projects in Kuwait
    • Koushki, P., Al-Rashid, K. and Kartam, N. (2005) Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), 285-94.
    • (2005) Construction Management and Economics , vol.23 , Issue.3 , pp. 285-294
    • Koushki, P.1    Al-Rashid, K.2    Kartam, N.3
  • 27
    • 77953676271 scopus 로고    scopus 로고
    • Paper presented at the 2nd International Conference on Construction in Developing Countries: Challenges Facing the Construction Industry in Developing Countries, Gabarone, Botswana, 15-17 November
    • Kuruooglu, M. and Ergen, E. (2000) The effects of economic development on project management in developing countries. Paper presented at the 2nd International Conference on Construction in Developing Countries: Challenges Facing the Construction Industry in Developing Countries, Gabarone, Botswana, 15-17 November.
    • (2000) The Effects of Economic Development On Project Management In Developing Countries
    • Kuruooglu, M.1    Ergen, E.2
  • 28
    • 22144498504 scopus 로고    scopus 로고
    • The relative impacts of selected practices on project cost and schedule
    • Lee, S., Thomas, S. and Tucker, R. (2005) The relative impacts of selected practices on project cost and schedule. Construction Management and Economics, 23(5), 545-53.
    • (2005) Construction Management and Economics , vol.23 , Issue.5 , pp. 545-553
    • Lee, S.1    Thomas, S.2    Tucker, R.3
  • 30
    • 2442471669 scopus 로고    scopus 로고
    • How project managers can better control the performance of design-build projects
    • Ling, F. (2004) How project managers can better control the performance of design-build projects. International Journal of Project Management, 22(6), 477-88.
    • (2004) International Journal of Project Management , vol.22 , Issue.6 , pp. 477-488
    • Ling, F.1
  • 31
    • 56749097044 scopus 로고    scopus 로고
    • Key project management practices affecting Singaporean firms' project performance in China
    • Ling, Y., Low, S., Wang, S. and Lim, H. (2009) Key project management practices affecting Singaporean firms' project performance in China. International Journal of Project Management, 27(1), 59-71.
    • (2009) International Journal of Project Management , vol.27 , Issue.1 , pp. 59-71
    • Ling, Y.1    Low, S.2    Wang, S.3    Lim, H.4
  • 32
  • 34
    • 0030074893 scopus 로고    scopus 로고
    • Construction delays in a fast-growing economy: Comparing Thailand with other economies
    • Ogunlana, S., Promkuntong, K. and Jearkjirm, V. (1996) Construction delays in a fast-growing economy: comparing Thailand with other economies. International Journal of Project Management, 14(1), 37-45.
    • (1996) International Journal of Project Management , vol.14 , Issue.1 , pp. 37-45
    • Ogunlana, S.1    Promkuntong, K.2    Jearkjirm, V.3
  • 35
    • 77953657510 scopus 로고    scopus 로고
    • in Smith, N. (ed.), Black-well, Oxford
    • Smith, N. (2002) Project appraisal and risk management, in Smith, N. (ed.) Engineering Project Management, Black-well, Oxford, pp. 156-72.
    • (2002) Project Appraisal and Risk Management , pp. 156-172
    • Smith, N.1
  • 36
    • 0036834343 scopus 로고    scopus 로고
    • Developing monitoring indicators for urban micro contracts in South Asia
    • Sohail, M., Miles, D. and Cotton, A. (2002) Developing monitoring indicators for urban micro contracts in South Asia. International Journal of Project Management, 20(8), 583-91.
    • (2002) International Journal of Project Management , vol.20 , Issue.8 , pp. 583-591
    • Sohail, M.1    Miles, D.2    Cotton, A.3
  • 37
    • 0036834348 scopus 로고    scopus 로고
    • Particular barriers and issues associated with projects in a developing and emerging economy. Case study of some abandoned water and irrigation projects in Nigeria
    • Sonuga, F., Aliboh, O. and Oloke, D. (2002) Particular barriers and issues associated with projects in a developing and emerging economy. Case study of some abandoned water and irrigation projects in Nigeria. International Journal of Project Management, 20(8), 611-16.
    • (2002) International Journal of Project Management , vol.20 , Issue.8 , pp. 611-616
    • Sonuga, F.1    Aliboh, O.2    Oloke, D.3
  • 40
    • 77953674337 scopus 로고    scopus 로고
    • Factors of complexity in construction projects
    • in Dainty, A. (ed.), Nottingham, UK, 7-9 September, Association of Researchers in Construction Management, Reading
    • Wood, H. and Ashton, P. (2009) Factors of complexity in construction projects, in Dainty, A. (ed.) Procs 25th Annual ARCOM Conference, Nottingham, UK, 7-9 September, Association of Researchers in Construction Management, Reading, pp. 857-66.
    • (2009) Procs 25th Annual ARCOM Conference , pp. 857-866
    • Wood, H.1    Ashton, P.2
  • 41
    • 77953682107 scopus 로고    scopus 로고
    • Cost and time control of construction projects: A survey of contractors and consultants in the UK
    • Yakubu, O. and Sun, M. (2009) Cost and time control of construction projects: a survey of contractors and consultants in the UK. Construction Information Quarterly, 11(2), 53-9.
    • (2009) Construction Information Quarterly , vol.11 , Issue.2 , pp. 53-59
    • Yakubu, O.1    Sun, M.2
  • 43
    • 42049119234 scopus 로고    scopus 로고
    • The impacts of change management practices on project change cost performance
    • Zou, Y. and Lee, S. (2008) The impacts of change management practices on project change cost performance. Construction Management and Economics, 26(4), 387-93.
    • (2008) Construction Management and Economics , vol.26 , Issue.4 , pp. 387-393
    • Zou, Y.1    Lee, S.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.