메뉴 건너뛰기




Volumn 21, Issue , 2014, Pages 49-60

Estimating the likelihood of pipeline failure in CO2 transmission pipelines: New insights on risks of carbon capture and storage

Author keywords

Carbon capture and storage; Incident rate; Risk analysis

Indexed keywords

CARBON DIOXIDE; DIGITAL STORAGE; FAILURE (MECHANICAL); GASES; NATURAL GAS; NATURAL GAS PIPELINES; PIPE LININGS; RISK ANALYSIS; RISK ASSESSMENT; RISK PERCEPTION; TRANSMISSIONS;

EID: 84890941387     PISSN: 17505836     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijggc.2013.11.005     Document Type: Article
Times cited : (50)

References (63)
  • 5
    • 84890922336 scopus 로고    scopus 로고
    • 2 pipeline integrity: a new evaluation methodology
    • GHGT-10
    • 2 pipeline integrity: a new evaluation methodology. Energy Proc. 2010, GHGT-10.
    • (2010) Energy Proc.
    • Berstad, T.1
  • 6
    • 84890944610 scopus 로고    scopus 로고
    • California Energy Resources Conservation and Development Commission CERCDC
    • CERCDC Geologic Carbon Sequestration Strategies, Committee Workshop 2010, California Energy Resources Conservation and Development Commission. http://www.energy.ca.gov/2007_energypolicy/documents/2007-10-01_workshop/2007-10-01_TRANSCRIPT.PDF.
    • (2010) Geologic Carbon Sequestration Strategies, Committee Workshop
  • 7
  • 9
    • 34548037902 scopus 로고    scopus 로고
    • Fracture control in carbon dioxide pipelines
    • rd quarter
    • Cosham A., Eiber R. Fracture control in carbon dioxide pipelines. J. Pipeline Eng. 2007, (3rd quarter):147-158.
    • (2007) J. Pipeline Eng. , Issue.3 , pp. 147-158
    • Cosham, A.1    Eiber, R.2
  • 11
    • 84890899172 scopus 로고    scopus 로고
    • 2 by pipeline for carbon capture and storage purposes
    • 2 by pipeline for carbon capture and storage purposes. PTC 6th Pipeline Technology Conference 2011, http://www.pipeline-conference.com/abstracts/technical-challenges-facing-transport-anthropogenic-co2-pipeline-carbon-capture-and.
    • (2011) PTC 6th Pipeline Technology Conference
    • Demofonti, G.1    Spinelli, C.M.2
  • 13
    • 84865466296 scopus 로고    scopus 로고
    • Det Norske Veritas, Recommended Practice DNV-RP-J202, April DNV
    • 2 pipelines 2010, Det Norske Veritas, Recommended Practice DNV-RP-J202, April.
    • (2010) 2 pipelines
  • 14
    • 85126163211 scopus 로고    scopus 로고
    • (Chapter 4, IPCC Report)
    • 2 2006, (Chapter 4, IPCC Report).
    • (2006) 2
    • Doctor, R.1
  • 16
    • 79955379989 scopus 로고    scopus 로고
    • 2 migration at candidate CCS sites in the U.S.
    • 2 migration at candidate CCS sites in the U.S. Energy Proc. 2011, 4:2222-2229.
    • (2011) Energy Proc. , vol.4 , pp. 2222-2229
    • Donlana, M.1    Trabucchi, C.2
  • 21
    • 84890944033 scopus 로고    scopus 로고
    • Carbon Capture and Storage - Technologies and Risk Management, Chapter 11. In: S. Khan (Ed.), Fossil Fuel and the Environment.
    • Esteves V., Morgado C., 2012. Carbon Capture and Storage - Technologies and Risk Management, Chapter 11. In: S. Khan (Ed.), Fossil Fuel and the Environment. http://cdn.intechopen.com/pdfs/32337/InTech-Carbon_capture_and_storage_ccs_technologies_and_risk_management.pdf.
    • (2012)
    • Esteves, V.1    Morgado, C.2
  • 22
    • 2642581533 scopus 로고    scopus 로고
    • 2 - safety and economic considerations
    • 2 - safety and economic considerations. Energy 2004, 29(9-10):1319-1328.
    • (2004) Energy , vol.29 , Issue.9-10 , pp. 1319-1328
    • Gale, J.1    Davison, J.2
  • 23
    • 84890965056 scopus 로고    scopus 로고
    • A comparison of inherent risk levels in ASME B31. 8 and UK gas pipeline design codes, IPC2006-10507
    • Goodfellow G., Haswell J. A comparison of inherent risk levels in ASME B31. 8 and UK gas pipeline design codes, IPC2006-10507. International Pipeline Conference, Calgary 2006.
    • (2006) International Pipeline Conference, Calgary
    • Goodfellow, G.1    Haswell, J.2
  • 25
    • 84890931245 scopus 로고    scopus 로고
    • 2 pipeline transport issues
    • 2 Capture, Storage and Utilization 2009, http://rd.tetratech.com/climatechange/projects/doc/SPE_CCS_Conference_2_4_November_2009_V4.pdf.
    • (2009) 2 Capture, Storage and Utilization
    • Grieb, T.1
  • 29
    • 0003743071 scopus 로고    scopus 로고
    • UK Health and Safety Executive, London, Report R2P2 HSE
    • HSE Reducing Risks, Protecting People 2001, UK Health and Safety Executive, London, Report R2P2.
    • (2001) Reducing Risks, Protecting People
  • 38
    • 84890948547 scopus 로고    scopus 로고
    • UK Health and Safety Laboratory
    • 2 Pipelines 2012, UK Health and Safety Laboratory. http://www.sieso.org.uk/Comah18_Lisbona_CO2.ppt.
    • (2012) 2 Pipelines
    • Lisbona, D.1
  • 40
    • 0031272082 scopus 로고    scopus 로고
    • A study of the dynamic response of emergency shutdown valves following full bore rupture of gas pipelines
    • Mahgerefteh H., Saha P., Economou I.G. A study of the dynamic response of emergency shutdown valves following full bore rupture of gas pipelines. Proc. Safety Environ. Protect. 1997, 75(4):201-209.
    • (1997) Proc. Safety Environ. Protect. , vol.75 , Issue.4 , pp. 201-209
    • Mahgerefteh, H.1    Saha, P.2    Economou, I.G.3
  • 42
    • 84890955265 scopus 로고    scopus 로고
    • Simulation-based estimates of safety distances for pipeline transportation of carbon dioxide
    • Mazzoldi A., et al. Simulation-based estimates of safety distances for pipeline transportation of carbon dioxide. Greenh. Gas Sci. Technol. 2012, 2:1-18.
    • (2012) Greenh. Gas Sci. Technol. , vol.2 , pp. 1-18
    • Mazzoldi, A.1
  • 47
    • 84864492020 scopus 로고    scopus 로고
    • Souris Valley Pipeline Limited, Calgary, Canada, MH-1-98 NEB
    • NEB National Engineering Board, Reasons for Decision 1998, October, Souris Valley Pipeline Limited, Calgary, Canada, MH-1-98.
    • (1998) National Engineering Board, Reasons for Decision
  • 50
    • 0004239573 scopus 로고
    • National Academies Press, Washington, DC NRC
    • NRC Improving Risk Communication 1989, National Academies Press, Washington, DC.
    • (1989) Improving Risk Communication
  • 53
    • 84890944899 scopus 로고    scopus 로고
    • U.S. Department of Transportation PHMSA
    • PHMSA The State of the National Pipeline Infrastructure 2010, U.S. Department of Transportation. http://opsweb.phmsa.dot.gov/pipelineforum/docs/Secretarys%20Infrastructure%20Report_Revised%20per%20PHC_103111.pdf.
    • (2010) The State of the National Pipeline Infrastructure
  • 62
    • 67650163916 scopus 로고    scopus 로고
    • Understanding potential GS risk: a multi-disciplinary framework to foster responsible stewardship
    • Wade S., Trabucchi C. Understanding potential GS risk: a multi-disciplinary framework to foster responsible stewardship. Energy Proc. 2009, 1:4567-4573.
    • (2009) Energy Proc. , vol.1 , pp. 4567-4573
    • Wade, S.1    Trabucchi, C.2
  • 63
    • 84890913485 scopus 로고    scopus 로고
    • Causes and consequences of focused leakage and rupture of US natural gas transmission pipelines
    • (submitted for publication)
    • Wang H., Duncan I.J. Causes and consequences of focused leakage and rupture of US natural gas transmission pipelines. J. Loss Prevent. Process Ind. 2013, (submitted for publication).
    • (2013) J. Loss Prevent. Process Ind.
    • Wang, H.1    Duncan, I.J.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.