A comprehensive scheme for reliability centered maintenance in power distribution systems - Part i: Methodology

Author keywords

Benefit to cost ratio (BCR); corrective maintenance (CM); critical component; preventive maintenance (PM); reliability centered maintenance (RCM)

Indexed keywords

BENEFIT TO COST RATIOS; CORRECTIVE MAINTENANCE; CRITICAL COMPONENT; PREVENTIVE MAINTENANCE (PM); RELIABILITY-CENTERED MAINTENANCE;

EID: 84875682872     PISSN: 08858977     EISSN: None     Source Type: Journal    
DOI: 10.1109/TPWRD.2012.2227832     Document Type: Article
Times cited : (115)

References (29)
  • 2
    • 34548036523 scopus 로고    scopus 로고
    • Security-constrained optimal coordination of generation and transmission maintenance outage scheduling
    • Aug
    • F. Yong et al., "Security-constrained optimal coordination of generation and transmission maintenance outage scheduling," IEEE Trans. Power Syst., vol. 22, no. 3, pp. 1302-1313, Aug. 2007.
    • (2007) IEEE Trans. Power Syst , vol.22 , Issue.3 , pp. 1302-1313
    • Yong, F.1
  • 3
    • 18944379628 scopus 로고    scopus 로고
    • Generation maintenance scheduling in restructured power systems
    • DOI 10.1109/TPWRS.2005.846078
    • A. J. Conejo, R. Garcia-Bertrand, and M. Diaz-Salazar, "Generation maintenance scheduling in restructured power systems," IEEE Trans. Power Syst., vol. 20, no. 2, pp. 984-992, May 2005. (Pubitemid 40699730)
    • (2005) IEEE Transactions on Power Systems , vol.20 , Issue.2 , pp. 984-992
    • Conejo, A.J.1    Garcia-Bertrand, R.2    Diaz-Salazar, M.3
  • 5
    • 84875656424 scopus 로고    scopus 로고
    • Nasa rcm guide for facilities and collateral equipments
    • Sep
    • "NASA RCM Guide for Facilities and Collateral Equipments," National Aeronautics and Space Administration, Sep. 2008.
    • (2008) National Aeronautics and Space Administration
  • 6
    • 0034225828 scopus 로고    scopus 로고
    • Expert system for reliability centered maintenance in the chemical industry
    • D. J. Fonseca and G.M. Knapp, "Expert system for reliability centered maintenance in the chemical industry," Expert Syst. Appl., vol. 19, no. 1, pp. 45-57, 2000.
    • (2000) Expert Syst. Appl , vol.19 , Issue.1 , pp. 45-57
    • Fonseca, D.J.1    Knapp, G.M.2
  • 7
    • 77957891475 scopus 로고    scopus 로고
    • RCM application for availability improvement of gas turbines used in combined cycle power stations
    • Sep
    • F. J. C. Guevara and G. F.M. Souza, "RCM application for availability improvement of gas turbines used in combined cycle power stations," IEEE Latin America Trans., vol. 6, no. 5, pp. 401-407, Sep. 2008.
    • (2008) IEEE Latin America Trans , vol.6 , Issue.5 , pp. 401-407
    • Guevara, F.J.C.1    Souza, G.F.M.2
  • 8
    • 0346076729 scopus 로고    scopus 로고
    • A reliability-based approach to transmission maintenance planning and its application in BC hydro system
    • Jan
    • W. Li and J. Korczynski, "A reliability-based approach to transmission maintenance planning and its application in BC hydro system," IEEE Trans. Power Del., vol. 19, no. 1, pp. 303-308, Jan. 2004.
    • (2004) IEEE Trans. Power Del , vol.19 , Issue.1 , pp. 303-308
    • Li, W.1    Korczynski, J.2
  • 10
    • 0031121412 scopus 로고    scopus 로고
    • Reliability centered maintenance for transmission systems
    • M. Beehler, "Reliability centered maintenance for transmission systems," IEEE Trans. Power Del., vol. 12, no. 2, pp. 1023-1028, Apr. 1997. (Pubitemid 127762408)
    • (1997) IEEE Transactions on Power Delivery , vol.12 , Issue.2 , pp. 1023-1028
    • Beehler, M.E.1
  • 11
    • 67349193859 scopus 로고    scopus 로고
    • Reliability centered asset management for MV deteriorating electrical equipment based on Germany failure statistics
    • May
    • X. Zhang, J. Zhang, and E. Gockenbach, "Reliability centered asset management for MV deteriorating electrical equipment based on Germany failure statistics," IEEE Trans. Power Syst., vol. 24, no. 2, pp. 721-728, May 2009.
    • (2009) IEEE Trans. Power Syst , vol.24 , Issue.2 , pp. 721-728
    • Zhang, X.1    Zhang, J.2    Gockenbach, E.3
  • 13
    • 74949140210 scopus 로고    scopus 로고
    • Mathematical model of reliability centered, maintenance (RCM). Power transm. and dist. networks applic
    • Jun. 28-Jul
    • D. Sarchiz, D. Bika, and O. Georgescu, "Mathematical model of reliability centered, maintenance (RCM). Power transm. and dist. networks applic.," in Proc. IEEE Bucharest Power Tech, Jun. 28-Jul. 2, 2009, pp. 1-4.
    • (2009) Proc IEEE Bucharest Power Tech , vol.2 , pp. 1-4
    • Sarchiz, D.1    Bika, D.2    Georgescu, O.3
  • 14
    • 84870551896 scopus 로고    scopus 로고
    • Critical component identification in reliability centered assetmanagement of power distribution systems via fuzzy AHP
    • Dec
    • P. Dehghanian, M. Fotuhi-Firuzabad, S. Bagheri-Shouraki, and A. A. R. Kazemi, "Critical component identification in reliability centered assetmanagement of power distribution systems via fuzzy AHP," IEEE Syst. J., vol. 6, no. 4, pp. 593-602, Dec. 2012.
    • (2012) IEEE Syst. J , vol.6 , Issue.4 , pp. 593-602
    • Dehghanian, P.1    Fotuhi-Firuzabad, M.2    Bagheri-Shouraki, S.3    Kazemi, A.A.R.4
  • 15
    • 48749101226 scopus 로고    scopus 로고
    • Reliability centered maintenance study on voltage regulators presented at the
    • Live-Line Maintenance, ESMO 2006, Albuquerque, NM, Oct. 15-19, 2006
    • D.W. Holladay, B. D. Dallman, and C. H. Grigg, "Reliability centered maintenance study on voltage regulators," presented at the IEEE 11th Int. Conf. Transm. Distrib. Construct., Oper, Live-Line Maintenance, ESMO 2006, Albuquerque, NM, Oct. 15-19, 2006.
    • IEEE 11th Int. Conf. Transm. Distrib. Construct., Oper
    • Holladay, D.W.1    Dallman, B.D.2    Grigg, C.H.3
  • 16
    • 0038681012 scopus 로고    scopus 로고
    • Reliability centered maintenance for distribution underground systems
    • W. Reder and D. Flaten, "Reliability centered maintenance for distribution underground systems," in Proc. IEEE Power Eng. Soc. Summer Meeting, 2000, vol. 1, pp. 551-556.
    • (2000) Proc IEEE Power Eng. Soc. Summer Meeting , vol.1 , pp. 551-556
    • Reder, W.1    Flaten, D.2
  • 17
    • 0038154388 scopus 로고    scopus 로고
    • Applying reliability centered maintenance (RCM) to overhead electric utility distribution systems
    • J. W. Goodfellow, "Applying reliability centered maintenance (RCM) to overhead electric utility distribution systems," in Proc. IEEE Power Eng. Soc. Summer Meeting, 2000, vol. 1, pp. 566-569.
    • (2000) Proc IEEE Power Eng. Soc. Summer Meeting , vol.1 , pp. 566-569
    • Goodfellow, J.W.1
  • 18
    • 27144510324 scopus 로고    scopus 로고
    • Implementation of reliability- centered maintenance for circuit breakers
    • Jun. 12-16
    • C. Ting, L. Chen-Ching, and C. Jong-Woong, "Implementation of reliability- centered maintenance for circuit breakers," in Proc. IEEE Power Eng. Soc. Gen. Meeting, Jun. 12-16, 2005, vol. 1, pp. 684-690.
    • (2005) Proc IEEE Power Eng. Soc. Gen. Meeting , vol.1 , pp. 684-690
    • Ting, C.1    Chen-Ching, L.2    Jong-Woong, C.3
  • 19
  • 20
    • 1542267538 scopus 로고    scopus 로고
    • Reliability centeredmaintenance for electric power distribution systems
    • Ph.D. dissertation., Stockholm, Sweden
    • L. Bertling, "Reliability centeredmaintenance for electric power distribution systems," Ph.D. dissertation, KTH, Sch. Elect. Eng., Stockholm, Sweden, 2002.
    • (2002) KTH, Sch. Elect. Eng
    • Bertling, L.1
  • 21
    • 13844313055 scopus 로고    scopus 로고
    • A reliability-centered asset maintenance method for assessing the impact of maintenance in power distribution systems
    • DOI 10.1109/TPWRS.2004.840433
    • L. Bertling, R. Allan, and R. Eriksson, "A reliability-centered asset maintenance method for assessing the impact of maintenance in power distribution systems," IEEE Trans. Power Syst., vol. 20, no. 1, pp. 75-82, Feb 2005. (Pubitemid 40259422)
    • (2005) IEEE Transactions on Power Systems , vol.20 , Issue.1 , pp. 75-82
    • Bertling, L.1    Allan, R.2    Eriksson, R.3
  • 22
    • 77956443687 scopus 로고    scopus 로고
    • Maintenance optimization for power distribution systems
    • Stockholm, Sweden
    • P. Hilber, "Maintenance Optimization for Power Distribution Systems," Doctoral dissertation, KTH, Sch. Elect. Eng., Stockholm, Sweden, 2008.
    • (2008) Doctoral Dissertation, KTH, Sch. Elect. Eng
    • Hilber, P.1
  • 24
    • 18844367688 scopus 로고    scopus 로고
    • Time management for assets: Chronological strategies for power system asset management
    • May/Jun
    • M. Shahidehpour and R. Ferrero, "Time management for assets: Chronological strategies for power system asset management," IEEE Power Energy, vol. 3, no. 3, pp. 32-38, May/Jun. 2005.
    • (2005) IEEE Power Energy , vol.3 , Issue.3 , pp. 32-38
    • Shahidehpour, M.1    Ferrero, R.2
  • 25
    • 35348916607 scopus 로고    scopus 로고
    • Power distribution asset management presented at the IEEE Power Eng
    • Montreal, QC, Canada
    • O. Tor and M. Shahidehpour, "Power distribution asset management," presented at the IEEE Power Eng. Soc. Gen. Meeting, Montreal, QC, Canada, 2006.
    • (2006) Soc. Gen. Meeting
    • Tor, O.1    Shahidehpour, M.2
  • 26
    • 51449085361 scopus 로고    scopus 로고
    • Phasing in the technology
    • Se/Oct
    • K. Martin and J. Carroll, "Phasing in the technology," IEEE Power Energy Mag., vol. 6, no. 5, pp. 24-33, Sep./Oct. 2008.
    • (2008) IEEE Power Energy Mag , vol.6 , Issue.5 , pp. 24-33
    • Martin, K.1    Carroll, J.2
  • 27
    • 2542531519 scopus 로고    scopus 로고
    • Failure rate modeling using equipment inspection data
    • May
    • R. E. Brown, G. Frimpong, and H. L. Willis, "Failure rate modeling using equipment inspection data," IEEE Trans. Power Syst., vol. 19, no. 2, pp. 782-787, May 2004.
    • (2004) IEEE Trans. Power Syst , vol.19 , Issue.2 , pp. 782-787
    • Brown, R.E.1    Frimpong, G.2    Willis, H.L.3
  • 28
    • 77956426316 scopus 로고    scopus 로고
    • Risk based resource allocation for distribution system maintenance
    • Aug
    • W. Jewell, J. Warner, J. McCalley, Y. Li, and S. R. Kumar-Yeddanapudi, Risk based resource allocation for distribution system maintenance. PSERC Publ. 06-26, Aug. 2006. [Online]. Available: www. pserc.org
    • (2006) PSERC Publ , pp. 06-26
    • Jewell, W.1    Warner, J.2    McCalley, J.3    Li, Y.4    Kumar-Yeddanapudi, R.S.5