Volumn 23, Issue 3, 2012, Pages 575-585

A project scheduling approach to production and material requirement planning in Manufacturing-to-Order environments

Author keywords

Aggregate planning; Material requirement planning; Production planning

Indexed keywords

AGGREGATE PLANNING; AGGREGATE PRODUCTION; MANUFACTURING OPERATIONS; MANUFACTURING-TO-ORDER; MATERIAL PROCUREMENT; MATERIAL REQUIREMENT PLANNING; MATERIAL REQUIREMENTS PLANNING; PRODUCTION ORDER; PRODUCTION PLANNING; PRODUCTION PLANS; PRODUCTION PROCESS; PROJECT SCHEDULING; RESOURCE CAPACITY; SCHEDULING INFORMATION; SUPPORT MATERIALS;

EID: 84862300001     PISSN: 09565515     EISSN: 15728145     Source Type: Journal    
DOI: 10.1007/s10845-010-0396-1     Document Type: Article
Times cited : (27)

References (23)
  • 1
    • 0019584719 scopus 로고
    • Aggregation of product data for hierarchical production planning
    • Axsater, S. (1981). Aggregation of product data for hierarchical production planning. Operations Research, 29(4), 744-756. (Pubitemid 12471861)
    • (1981) Operations Research , vol.29 , Issue.4 , pp. 744-756
    • Axsater Sven1
  • 2
    • 0022782156 scopus 로고
    • On the feasibility of aggregate production plans
    • Axsater, S. (1986). On the feasibility of aggregate production plans. Operations Research, 34(5), 796-800.
    • (1986) Operations Research , vol.34 , Issue.5 , pp. 796-800
    • Axsater, S.1
  • 3
    • 0021494719 scopus 로고
    • Aggregation and disaggregation in hierarchical production planning
    • DOI 10.1016/0377-2217(84)90129-2
    • Axster, S., & Jonsson, H. (1984). Aggregation and disaggregation in hierarchical production planning. European Journal of Operational Research, 17(3), 338-350. (Pubitemid 14625138)
    • (1984) European Journal of Operational Research , vol.17 , Issue.3 , pp. 338-350
    • Axsater Sven1    Jonsson Henrik2
  • 4
    • 33751515856 scopus 로고    scopus 로고
    • Project-driven planning and scheduling support for virtual manufacturing
    • DOI 10.1007/s10845-006-0034-0, Special Issue on E-Manufacturing and Web-Based Technology for Intelligent Manufacturing and Networked Enterprise Interoperability
    • Banaszak, Z., & Zaremba, M. (2006). Project-driven planning and scheduling support for virtual manufacturing. Journal of Intelligent Manufacturing, 17(6), 641-651. (Pubitemid 44833170)
    • (2006) Journal of Intelligent Manufacturing , vol.17 , Issue.6 , pp. 641-651
    • Banaszak, Z.A.1    Zaremba, M.B.2
  • 6
    • 0001215033 scopus 로고
    • The analysis of activity networks under Generalized Precedence Relations (gprs)
    • Elmaghraby, S. E., & Kamburowski, J. (1992). The analysis of activity networks under Generalized Precedence Relations (gprs). Management Science, 38(9), 1245-1263.
    • (1992) Management Science , vol.38 , Issue.9 , pp. 1245-1263
    • Elmaghraby, S.E.1    Kamburowski, J.2
  • 8
    • 0036681925 scopus 로고    scopus 로고
    • A matrix formulation for integrating assembly trees and manufacturing resource planning with capacity constraints
    • DOI 10.1023/A:1016060009229
    • Harris, B., Lewis, F., & Cook, D. J. (2002). A matrix formulation for integrating assembly trees and manufacturing resource planning with capacity constraints. Journal of Intelligent Manufacturing, 13(4), 239-252. (Pubitemid 34830272)
    • (2002) Journal of Intelligent Manufacturing , vol.13 , Issue.4 , pp. 239-252
    • Harris, B.1    Lewis, F.2    Cook, D.J.3
  • 9
    • 79954416697 scopus 로고
    • logistics, North-Holland, chap hierarchical integration of production planning and scheduling
    • Hax, A. C., & Meal, H. C. (1975). Studies in the management sciences, vol. logistics, North-Holland, chap hierarchical integration of production planning and scheduling.
    • (1975) Studies in the Management Sciences, Vol.
    • Hax, A.C.1    Meal, H.C.2
  • 11
    • 21644447132 scopus 로고    scopus 로고
    • A branch-And-cut algorithm for scheduling of projects with variable-intensity activities
    • Kis, T. (2005). A branch-And-cut algorithm for scheduling of projects with variable-intensity activities. Mathematical Programming.
    • (2005) Mathematical Programming
    • Kis, T.1
  • 12
    • 73549085432 scopus 로고    scopus 로고
    • Rcps with variable intensity activities and feeding precedence constraint
    • New York: Springer
    • Kis, T. (2006). Rcps with variable intensity activities and feeding precedence constraint. In Perspectives in modern project scheduling (pp. 105-129). New York: Springer.
    • (2006) Perspectives in Modern Project Scheduling , pp. 105-129
    • Kis, T.1
  • 13
    • 0347600419 scopus 로고    scopus 로고
    • Partitioning of trees for minimizing height and cardinality
    • Kovács, A., & Kis, T. (2004). Partitioning of trees for minimizing height and cardinality. Information Processing Letters, 89, 181-185.
    • (2004) Information Processing Letters , vol.89 , pp. 181-185
    • Kovács, A.1    Kis, T.2
  • 15
    • 0042343670 scopus 로고    scopus 로고
    • Project scheduling approach for production planning
    • Márkus, A., Váncza, J., Kis, T., & Kovács, A. (2003). Project scheduling approach for production planning. Annals of the CIRP, 52(1), 359-362.
    • (2003) Annals of the CIRP , vol.52 , Issue.1 , pp. 359-362
    • Márkus, A.1    Váncza, J.2    Kis, T.3    Kovács, A.4
  • 16
    • 0000647152 scopus 로고
    • Heuristics for the minimum project-duration problem with minimal and maximal time lags under fixed resource constraints
    • Neumann, K., & Zhan, J. (1995). Heuristics for the minimum project-duration problem with minimal and maximal time lags under fixed resource constraints. Journal of Intelligent Manufacturing, 6(2), 145-154.
    • (1995) Journal of Intelligent Manufacturing , vol.6 , Issue.2 , pp. 145-154
    • Neumann, K.1    Zhan, J.2
  • 17
    • 4344620927 scopus 로고    scopus 로고
    • A linearized polynomial mixed integer programming model for the integration of process planning and scheduling
    • Tan, W., & Khoshnevis, B. (2004). A linearized polynomial mixed integer programming model for the integration of process planning and scheduling. Journal of IntelligentManufacturing, 15(5), 593-605.
    • (2004) Journal of IntelligentManufacturing , vol.15 , Issue.5 , pp. 593-605
    • Tan, W.1    Khoshnevis, B.2
  • 18
    • 0344638324 scopus 로고
    • Restrictive aggregation of items in multi-stage production systems
    • Toczylowski, E., & Pienkosz, K. (1991). Restrictive aggregation of items in multi-stage production systems. Operations Research Letters, 10(3), 159-163.
    • (1991) Operations Research Letters , vol.10 , Issue.3 , pp. 159-163
    • Toczylowski, E.1    Pienkosz, K.2
  • 19
    • 70349093586 scopus 로고    scopus 로고
    • Planning of machining centres production: The role of precedence modelling
    • Tolio, T., & Urgo, M. (2007). Planning of machining centres production: the role of precedence modelling. In Proceedings of the 7th AITeM congress.
    • (2007) Proceedings of the 7th AITeM Congress
    • Tolio, T.1    Urgo, M.2
  • 21
    • 3142757956 scopus 로고    scopus 로고
    • Aggregation: The key to integrating production planning and scheduling
    • Váncza, J., Kis, T., & Kovács, A. (2004). Aggregation: The key to integrating production planning and scheduling. Annals of the CIRP, 53(1), 374-376.
    • (2004) Annals of the CIRP , vol.53 , Issue.1 , pp. 374-376
    • Váncza, J.1    Kis, T.2    Kovács, A.3
  • 23
    • 4744362917 scopus 로고    scopus 로고
    • A continuous-time algorithm for disaggregation of hierarchical production plans
    • Yalcin, A., & Boucher, T. O. (2004). A continuous-time algorithm for disaggregation of hierarchical production plans. IIE Transactions, 36(11), 1023-1035.
    • (2004) IIE Transactions , vol.36 , Issue.11 , pp. 1023-1035
    • Yalcin, A.1    Boucher, T.O.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.