Volumn 38, Issue 7, 2011, Pages 8293-8302

Precast production scheduling using multi-objective genetic algorithms

Author keywords

Buffer; Multi objective genetic algorithms; Precast production; Scheduling

Indexed keywords

BUFFER; BUFFER SIZES; COMPUTATIONAL TECHNIQUE; CURRENT PRACTICES; LEADTIME; MINIMUM MAKESPAN; MULTI OBJECTIVE; MULTI-OBJECTIVE GENETIC ALGORITHM; MULTI-OBJECTIVE GENETIC ALGORITHMS; ON-TIME DELIVERY; OPTIMUM SOLUTION; PRE-CAST; PRODUCTION RESOURCES; PRODUCTION SCHEDULE; PRODUCTION SCHEDULING; RESOURCE UTILIZATIONS; TARDINESS PENALTIES;

EID: 79952449814     PISSN: 09574174     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.eswa.2011.01.013     Document Type: Article
Times cited : (103)

References (45)
  • 1
    • 27844495113 scopus 로고    scopus 로고
    • Coordination of set-ups between two stages of a supply chain using multi-objective genetic algorithms
    • DOI 10.1080/00207540500103821
    • S. Afshin Mansouri Coordination of set-ups between two stages of a supply chain using multi-objective genetic algorithms International Journal of Production Research 43 2005 3163 3180 (Pubitemid 41657431)
    • (2005) International Journal of Production Research , vol.43 , Issue.15 , pp. 3163-3180
    • Afshin Mansouri, S.1
  • 2
    • 0032858697 scopus 로고    scopus 로고
    • Optimal design of aquifer cleanup systems under uncertainty using a neural network and a genetic algorithm
    • A.H. Aly, and R.C. Peralta Optimal design of aquifer cleanup systems under uncertainty using a neural network and a genetic algorithm Water Resources Research 35 8 1999 2523 2532 (Pubitemid 29375380)
    • (1999) Water Resources Research , vol.35 , Issue.8 , pp. 2523-2532
    • Aly, A.H.1    Peralta, R.C.2
  • 3
    • 33646916025 scopus 로고    scopus 로고
    • Multi-objective genetic algorithms: A way to improve the convergence rate
    • DOI 10.1016/j.engappai.2006.01.010, PII S0952197606000145
    • O.B. Augusto, S. Rabeau, P.H. Depince, and F. Bennis Multi-objective genetic algorithms: A way to improve the convergence rate Engineering Applications of Artificial Intelligence 19 2006 501 510 (Pubitemid 43795041)
    • (2006) Engineering Applications of Artificial Intelligence , vol.19 , Issue.5 , pp. 501-510
    • Augusto, O.B.1    Rabeau, S.2    Depince, Ph.3    Bennis, F.4
  • 5
    • 13944259031 scopus 로고    scopus 로고
    • Flowshop scheduling model for bespoke precast concrete production planning
    • DOI 10.1080/0144619042000287732
    • V. Benjaoran, N. Dawood, and B. Hobbs Flowshop scheduling model for bespoke precast concrete production planning Journal of Construction Management and Economics 23 2005 93 105 (Pubitemid 40273715)
    • (2005) Construction Management and Economics , vol.23 , Issue.1 , pp. 93-105
    • Benjaoran, V.1    Dawood, N.2    Hobbs, B.3
  • 7
    • 1842507020 scopus 로고    scopus 로고
    • Flow shop scheduling with earliness, tardiness, and intermediate inventory holding costs
    • K. Bulbul, P. Kaminsky, and C. Yano Flow shop scheduling with earliness, tardiness, and intermediate inventory holding costs Naval Research Logistics 51 2004 407 445
    • (2004) Naval Research Logistics , vol.51 , pp. 407-445
    • Bulbul, K.1    Kaminsky, P.2    Yano, C.3
  • 8
    • 0014807274 scopus 로고
    • A heuristic algorithm for the n job, m machine sequencing problem
    • H.G. Campbell, R.A. Dudek, and M.L. Smith A heuristic algorithm for the n job, m machine sequencing problem Management Science 16 1970 630 637
    • (1970) Management Science , vol.16 , pp. 630-637
    • Campbell, H.G.1    Dudek, R.A.2    Smith, M.L.3
  • 10
    • 13944279904 scopus 로고    scopus 로고
    • Constraint programming approach to precast production scheduling
    • DOI 10.1061/(ASCE)0733-9364(2002)128:6(513)
    • W.T. Chan, and H. Hu Constraint programming approach to precast production scheduling Journal of Construction Engineering and Management 128 2002 513 521 (Pubitemid 40265515)
    • (2002) Journal of Construction Engineering and Management , vol.128 , Issue.6 , pp. 513-521
    • Chan, W.T.1    Hu, H.2
  • 11
    • 79952440941 scopus 로고    scopus 로고
    • Production scheduling for precast plants using a flow shop sequencing model
    • W.T. Chan, and H. Hu Production scheduling for precast plants using a flow shop sequencing model Journal of Computing in Civil Engineering, ASCE 79 17 2002 1605 1616
    • (2002) Journal of Computing in Civil Engineering, ASCE , vol.79 , Issue.17 , pp. 1605-1616
    • Chan, W.T.1    Hu, H.2
  • 12
    • 0037410718 scopus 로고    scopus 로고
    • A multi-population genetic algorithm to solve multi-objective scheduling problems for parallel machines
    • DOI 10.1016/S0305-0548(02)00059-X, PII S030505480200059X
    • J.K. Cochran, S.M. Horng, and J.W. Fowler A multi-population genetic algorithm to solve multi-objective scheduling problems for parallel machines Computers and Operations Research 30 7 2003 1087 1102 (Pubitemid 36270657)
    • (2003) Computers and Operations Research , vol.30 , Issue.7 , pp. 1087-1102
    • Cochran, J.K.1    Horng, S.-M.2    Fowler, J.W.3
  • 14
    • 58149319062 scopus 로고
    • Scheduling in the precast concrete industry using the simulation modelling approach
    • N.N. Dawood Scheduling in the precast concrete industry using the simulation modelling approach Journal of Building and Environment 30 1995 197 207
    • (1995) Journal of Building and Environment , vol.30 , pp. 197-207
    • Dawood, N.N.1
  • 15
    • 0030100995 scopus 로고    scopus 로고
    • A simulation model for eliciting scheduling knowledge: An application to the precast manufacturing process
    • N.N. Dawood A simulation model for eliciting scheduling knowledge: An application to the precast manufacturing process Journal of Advances in Engineering Software 25 1996 215 223 (Pubitemid 126397527)
    • (1996) Advances in Engineering Software , vol.25 , Issue.2-3 , pp. 215-223
    • Dawood, N.N.1
  • 16
    • 0027147695 scopus 로고
    • Capacity planning model for precast concrete building products
    • DOI 10.1016/0360-1323(93)90009-R
    • N.N. Dawood, and R.H. Neale Capacity planning model for precast concrete building products Journal of Building and Environment 28 1993 81 95 (Pubitemid 23619688)
    • (1993) Building and Environment , vol.28 , Issue.1 , pp. 81-95
    • Dawood, N.N.1    Neale, R.H.2
  • 19
    • 0002629429 scopus 로고
    • An overview of evolutionary algorithms in multiobjective optimization
    • C.M. Fonsecay, and P.J. Flemingz An overview of evolutionary algorithms in multiobjective optimization Evolutionary Computation 3 1 1995 1 16
    • (1995) Evolutionary Computation , vol.3 , Issue.1 , pp. 1-16
    • Fonsecay, C.M.1    Flemingz, P.J.2
  • 22
    • 0022559425 scopus 로고
    • Optimization of control parameters for genetic algorithms
    • DOI 10.1109/TSMC.1986.289288
    • J.J. Grefenstette Optimization of control parameters for genetic algorithms IEEE Transactions on Systems, Man and Cybernetics 16 1 1986 122 128 (Pubitemid 16187857)
    • (1986) IEEE Transactions on Systems, Man and Cybernetics , vol.16 , Issue.1 , pp. 122-128
    • Grefenstette, J.J.1
  • 23
    • 0015033601 scopus 로고
    • A functional heuristic algorithm for the flowshop scheduling problem
    • J.N.D. Gupta A functional heuristic algorithm for the flowshop scheduling problem Operational Research Quarterly 22 1971 39 47
    • (1971) Operational Research Quarterly , vol.22 , pp. 39-47
    • Gupta, J.N.D.1
  • 25
    • 0242409617 scopus 로고    scopus 로고
    • Performance evaluation of memetic EMO algorithms using dominance relation-based replacement rules on MOO test problem
    • S. Kaige, T. Murata, and H. Ishibuchi Performance evaluation of memetic EMO algorithms using dominance relation-based replacement rules on MOO test problem IEEE International Conference on System, Man and Cybernetics 1 2003 14 19
    • (2003) IEEE International Conference on System, Man and Cybernetics , vol.1 , pp. 14-19
    • Kaige, S.1    Murata, T.2    Ishibuchi, H.3
  • 26
    • 31144461382 scopus 로고    scopus 로고
    • Adaptive weighted sum method for multiobjective optimization: A new method for Pareto front generation
    • DOI 10.1007/s00158-005-0557-6
    • I.Y. Kim, and O.L.de. Weck Adaptive weighted sum method for multiobjective optimization: A new method for Pareto Structural and Multidisciplinary Optimization 31 2006 105 116 (Pubitemid 43130322)
    • (2006) Structural and Multidisciplinary Optimization , vol.31 , Issue.2 , pp. 105-116
    • Kim, I.Y.1    De Weck, O.L.2
  • 28
    • 33750734287 scopus 로고    scopus 로고
    • A multi-objective genetic algorithm for robust flight scheduling using simulation
    • DOI 10.1016/j.ejor.2005.12.014, PII S0377221705008465
    • L.H. Lee, C.U. Lee, and Y.P. Tan A multi-objective genetic algorithm for robust flight scheduling using simulation European Journal of Operational Research 177 2007 1948 1968 (Pubitemid 44709461)
    • (2007) European Journal of Operational Research , vol.177 , Issue.3 , pp. 1948-1968
    • Lee, L.H.1    Lee, C.U.2    Tan, Y.P.3
  • 30
    • 0036605006 scopus 로고    scopus 로고
    • GA-based resource-constrained flow-shop scheduling model for mixed precast production
    • S.S. Leu, and S.T. Hwang GA-based resource-constrained flow-shop scheduling model for mixed precast production Automation in Construction 11 2002 439 452
    • (2002) Automation in Construction , vol.11 , pp. 439-452
    • Leu, S.S.1    Hwang, S.T.2
  • 31
    • 33744522186 scopus 로고    scopus 로고
    • A simulated annealing approach to a bi-criteria sequencing problem in a two-stage supply chain
    • DOI 10.1016/j.cie.2006.01.002, PII S0360835206000064
    • S.A. Mansouri A simulated annealing approach to a bi-criteria sequencing problem in a two-stage supply chain Computers and Industrial Engineering 50 2006 105 119 (Pubitemid 43816791)
    • (2006) Computers and Industrial Engineering , vol.50 , Issue.1-2 , pp. 105-119
    • Mansouri, S.A.1
  • 33
    • 0001393583 scopus 로고
    • Sequencing jobs through a multi-stage process in the minimum total time - A quick method of obtaining a near optimum
    • D.S. Palmer Sequencing jobs through a multi-stage process in the minimum total time - A quick method of obtaining a near optimum Operations Research Quarterly 16 1965 101 107
    • (1965) Operations Research Quarterly , vol.16 , pp. 101-107
    • Palmer, D.S.1
  • 34
    • 33744990802 scopus 로고    scopus 로고
    • An algorithm for minimizing weighted earliness penalty in assembly job shops
    • DOI 10.1016/j.ijpe.2005.08.002, PII S0925527305002288
    • S. Pathumnakul, and P.J. Egbelu An algorithm for minimizing weighted earliness penalty in assembly job shops International Journal of Production Economics 103 1 2006 230 245 (Pubitemid 43866477)
    • (2006) International Journal of Production Economics , vol.103 , Issue.1 , pp. 230-245
    • Pathumnakul, S.1    Egbelu, P.J.2
  • 36
    • 31544451276 scopus 로고    scopus 로고
    • Lean manufacturing - A systematic approach to improving productivity in the precast concrete industry
    • B. Ray, P. Ripley, and D. Neal Lean manufacturing - A systematic approach to improving productivity in the precast concrete industry PCI Journal 51 2006 62 71 (Pubitemid 43159758)
    • (2006) PCI Journal , vol.51 , Issue.1 , pp. 62-71
    • Ray, B.1    Ripley, P.2    Neal, D.3
  • 37
    • 33750403562 scopus 로고    scopus 로고
    • Optimal reservoir operation using multi-objective evolutionary algorithm
    • DOI 10.1007/s11269-005-9011-1
    • M.J. Reddy, and D.N. Kumar Optimal reservoir operation using multi-objective evolutionary algorithm Water Resources Management 20 2006 861 878 (Pubitemid 44642567)
    • (2006) Water Resources Management , vol.20 , Issue.6 , pp. 861-878
    • Reddy, M.J.1    Kumar, D.N.2
  • 38
    • 34247897041 scopus 로고    scopus 로고
    • Multi-objective master production scheduling in make-to-order manufacturing
    • DOI 10.1080/00207540600847152, PII 778110131
    • T. Sawik Multi-objective master production scheduling in make-to-order manufacturing International Journal of Production Research 45 12 2007 2629 2653 (Pubitemid 46693173)
    • (2007) International Journal of Production Research , vol.45 , Issue.12 , pp. 2629-2653
    • Sawik, T.1
  • 44
    • 0032254705 scopus 로고    scopus 로고
    • Use of simulation for construction elements manufacturing
    • Vern, K., Gunal, A. (1998). Use of simulation for construction elements manufacturing. In Proceedings of the winter simulation conference, (Vol. 2, pp. 1273-1277).
    • (1998) Proceedings of the Winter Simulation Conference , vol.2 , pp. 1273-1277
    • Vern, K.1    Gunal, A.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.