An integrated approach for requirement selection and scheduling in software release planning

Author keywords

Integer linear programming (ILP); Release planning; Requirement dependency; Requirement scheduling; Requirement selection; Scrum; Simulation

Indexed keywords

INTEGER LINEAR PROGRAMMING; RELEASE PLANNING; REQUIREMENT DEPENDENCY; REQUIREMENT SCHEDULING; REQUIREMENT SELECTION; SCRUM; SIMULATION;

EID: 79751537620     PISSN: 09473602     EISSN: 1432010X     Source Type: Journal    
DOI: 10.1007/s00766-010-0104-x     Document Type: Article
Times cited : (52)

References (49)
  • 1
    • 34547695210 scopus 로고    scopus 로고
    • Market-driven requirements engineering for software products
    • Aurum, A, Wohlin, C, Springer, Dordrecht
    • Regnell B, Brinkkemper S (2005) Market-driven requirements engineering for software products. In: Aurum A, Wohlin C (eds) Engineering and managing software requirements. Springer, Dordrecht, pp 287-308.
    • (2005) Engineering and managing software requirements , pp. 287-308
    • Regnell, B.1    Brinkkemper, S.2
  • 5
    • 0031234218 scopus 로고    scopus 로고
    • A cost-value approach for prioritizing requirements
    • Joachim K, Kevin R (1997) A cost-value approach for prioritizing requirements. IEEE Softw 14(5): 67-74.
    • (1997) IEEE Softw , vol.14 , Issue.5 , pp. 67-74
    • Joachim, K.1    Kevin, R.2
  • 6
    • 1842755059 scopus 로고    scopus 로고
    • Release planning in market-driven software product development: provoking an understanding
    • Carlshamre P (2002) Release planning in market-driven software product development: provoking an understanding. Requir Eng 7(3): 139-151.
    • (2002) Requir Eng , vol.7 , Issue.3 , pp. 139-151
    • Carlshamre, P.1
  • 7
    • 6344254486 scopus 로고    scopus 로고
    • Prioritizing requirements
    • Firesmith D (2004) Prioritizing requirements. J Object Technol 3(8): 35-47.
    • (2004) J Object Technol , vol.3 , Issue.8 , pp. 35-47
    • Firesmith, D.1
  • 8
    • 0742307215 scopus 로고    scopus 로고
    • Software release planning: an evolutionary and iterative approach
    • Greer D, Ruhe G (2004) Software release planning: an evolutionary and iterative approach. Inf Softw Technol 46: 243-253.
    • (2004) Inf Softw Technol , vol.46 , pp. 243-253
    • Greer, D.1    Ruhe, G.2
  • 10
    • 0032122207 scopus 로고    scopus 로고
    • Optimizing value and cost in requirements analysis
    • Ho-Won Jung (1998) Optimizing value and cost in requirements analysis. IEEE Softw 15(4): 74-78.
    • (1998) IEEE Softw , vol.15 , Issue.4 , pp. 74-78
    • Ho-Won, J.1
  • 11
    • 28244472252 scopus 로고    scopus 로고
    • The art and science of software release planning
    • Ruhe G, Saliu M. Omolade (2005) The art and science of software release planning. IEEE Softw 22(6): 47-53.
    • (2005) IEEE Softw , vol.22 , Issue.6 , pp. 47-53
    • Ruhe, G.1    Omolade, S.M.2
  • 13
    • 36549032766 scopus 로고    scopus 로고
    • Software product release planning through optimization andwhat-if analysis
    • van den Akker JM, Brinkkemper S, Diepen G, Versendaal J (2008) Software product release planning through optimization andwhat-if analysis. Inf Softw Technol 50(1-2): 101-111.
    • (2008) Inf Softw Technol , vol.50 , Issue.1-2 , pp. 101-111
    • van den Akker, J.M.1    Brinkkemper, S.2    Diepen, G.3    Versendaal, J.4
  • 16
    • 60449109741 scopus 로고    scopus 로고
    • Optimized resource allocation for software release planning
    • Ngo-The A, Ruhe G (2009) Optimized resource allocation for software release planning. IEEE Trans Softw Eng 35(1): 109-123.
    • (2009) IEEE Trans Softw Eng , vol.35 , Issue.1 , pp. 109-123
    • Ngo-The, A.1    Ruhe, G.2
  • 23
    • 0034228837 scopus 로고    scopus 로고
    • The scrum software development process for small teams
    • Rising L, Norman JS (2000) The scrum software development process for small teams. IEEE Softw 17(4): 26-32.
    • (2000) IEEE Softw , vol.17 , Issue.4 , pp. 26-32
    • Rising, L.1    Norman, J.S.2
  • 28
    • 0032070635 scopus 로고    scopus 로고
    • An exact algorithm for the resource-constrained project scheduling problem based on a new mathematical formulation
    • Aristide M, Vittorio M, Salvatore R, Lucio B (1998) An exact algorithm for the resource-constrained project scheduling problem based on a new mathematical formulation. Manag Sci 44(5): 714-729.
    • (1998) Manag Sci , vol.44 , Issue.5 , pp. 714-729
    • Aristide, M.1    Vittorio, M.2    Salvatore, R.3    Lucio, B.4
  • 30
    • 0019342681 scopus 로고
    • Scheduling projects subject to resource constraints: classification and complexity
    • Blazewicz J, Lenstra JK, Rinnooy Kan AHG (1983) Scheduling projects subject to resource constraints: classification and complexity. Discrete Appl Math 5: 11-24.
    • (1983) Discrete Appl Math , vol.5 , pp. 11-24
    • Blazewicz, J.1    Lenstra, J.K.2    Rinnooy Kan, A.H.G.3
  • 31
    • 33845274958 scopus 로고
    • Strength and adaptability of problem-space based neighborhoods for resource-constrained scheduling
    • Jorge LV, Balakrishnan R (1995) Strength and adaptability of problem-space based neighborhoods for resource-constrained scheduling. OR Spectr 17(1-3): 173-182.
    • (1995) OR Spectr , vol.17 , Issue.1-3 , pp. 173-182
    • Lv, J.1    Balakrishnan, R.2
  • 32
    • 0002907360 scopus 로고
    • A branch-and-bound procedure for the multiple resource-constrained project scheduling problem
    • Demeulemeester E, Herroelen W (1992) A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Manag Sci 38(12): 1803-1818.
    • (1992) Manag Sci , vol.38 , Issue.12 , pp. 1803-1818
    • Demeulemeester, E.1    Herroelen, W.2
  • 37
    • 0001559895 scopus 로고
    • Formulating the single machine sequencing problem with release dates as a mixed integer program
    • Dyer ME, Wolsey LA (1990) Formulating the single machine sequencing problem with release dates as a mixed integer program. Discrete Appl Math 26(2-3): 255-270.
    • (1990) Discrete Appl Math , vol.26 , Issue.2-3 , pp. 255-270
    • Dyer, M.E.1    Wolsey, L.A.2
  • 40
    • 79751527436 scopus 로고    scopus 로고
    • ILOG Cplex
    • ILOG Cplex. http://www. 01. ibm. com/software/integration/optimization/cplex.
  • 41
    • 79751537300 scopus 로고    scopus 로고
    • ILP Product Comparison
    • ILP Product Comparison. http://www. lionhrtpub. com/orms/surveys/LP/LP-survey. html.
  • 43
    • 79751533554 scopus 로고    scopus 로고
    • Release Dataset
    • Release Dataset. http://www. home. cs. utwente. nl/~lic/Resources. html.
  • 44
    • 0042866850 scopus 로고    scopus 로고
    • An industrial case study on distributed prioritisation in market-driven requirements engineering for packaged software
    • Regnell B, Höst M, Natt och Dag J, Beremark P, Hjelm T (2001) An industrial case study on distributed prioritisation in market-driven requirements engineering for packaged software. Requir Eng 6(1): 51-62.
    • (2001) Requir Eng , vol.6 , Issue.1 , pp. 51-62
    • Regnell, B.1    Höst, M.2    Nattoch Dag, J.3    Beremark, P.4    Hjelm, T.5
  • 45
    • 0038715816 scopus 로고    scopus 로고
    • Resource constrained scheduling simulation model for alternative stochastic network projects
    • Golenko-Ginzburg D, Gonik A, Laslo Z (2003) Resource constrained scheduling simulation model for alternative stochastic network projects. Math Comput Simul 63(2): 105-117.
    • (2003) Math Comput Simul , vol.63 , Issue.2 , pp. 105-117
    • Golenko-Ginzburg, D.1    Gonik, A.2    Laslo, Z.3
  • 46
    • 40249098866 scopus 로고    scopus 로고
    • Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities
    • Lambrechts O, Demeulemeester E, Herroelen W (2008) Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities. J Sched 11(2): 121-136.
    • (2008) J Sched , vol.11 , Issue.2 , pp. 121-136
    • Lambrechts, O.1    Demeulemeester, E.2    Herroelen, W.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.