Volumn 50, Issue 5-8, 2010, Pages 811-822

Project time-cost trade-off scheduling: A hybrid optimization approach

Author keywords

Project scheduling; Time cost trade off Hybrid approach Cutting plane Optimization

Indexed keywords

COMPUTATIONAL STUDIES; CUTTING PLANE METHODS; CUTTING PLANES; DECISION VARIABLES; DIRECT COSTS; HYBRID APPROACH; HYBRID OPTIMIZATION; ILLUSTRATIVE EXAMPLES; LINEAR COST FUNCTIONS; MONTE CARLO SIMULATIONS; NONLINEAR MATHEMATICAL PROGRAMS; OBJECTIVE FUNCTIONS; PERT NETWORKS; PROJECT COMPLETION; PROJECT SCHEDULING; TIME COST;

EID: 78650277585     PISSN: 02683768     EISSN: 14333015     Source Type: Journal    
DOI: 10.1007/s00170-010-2543-4     Document Type: Article
Times cited : (31)

References (52)
  • 1
    • 0000181338 scopus 로고
    • A network flow computation for project cost curve
    • Fulkerson DR (1961) A network flow computation for project cost curve. Manag Sci 7(2):167-178
    • (1961) Manag Sci , vol.7 , Issue.2 , pp. 167-178
    • Fulkerson, D.R.1
  • 2
    • 34250637152 scopus 로고    scopus 로고
    • The stochastic time-cost tradeoff problem: A robust optimization approach
    • Cohen I, Golany B, Shtub A (2007) The stochastic time-cost tradeoff problem: a robust optimization approach. Networks 49 (2):175-188
    • (2007) Networks , vol.49 , Issue.2 , pp. 175-188
    • Cohen, I.1    Golany, B.2    Shtub, A.3
  • 3
    • 0030289778 scopus 로고    scopus 로고
    • Time-resource tradeoff problem
    • Pulat PS, Horn SJ (1996) Time-resource tradeoff problem. IEEE Trans Eng Manage 43(4):411-417
    • (1996) IEEE Trans Eng Manage , vol.43 , Issue.4 , pp. 411-417
    • Pulat, P.S.1    Horn, S.J.2
  • 4
    • 0001267414 scopus 로고
    • A method for simultaneously planning, scheduling, and control of projects
    • Crowston W, Thompson GL, Decision CPM (1967) A method for simultaneously planning, scheduling, and control of projects. Oper Res 15(3):407-426
    • (1967) Oper Res , vol.15 , Issue.3 , pp. 407-426
    • Crowston, W.1    Thompson, G.L.2    Cpm, D.3
  • 5
    • 0016566179 scopus 로고
    • A dynamic programming solution to cost-time tradeoff for CPM
    • Robinson DR (1975) A dynamic programming solution to cost-time tradeoff for CPM. Manag Sci 22(2):158-166
    • (1975) Manag Sci , vol.22 , Issue.2 , pp. 158-166
    • Robinson, D.R.1
  • 6
    • 0005764899 scopus 로고
    • An implicit enumeration algorithm for the time/cost tradeoff problem in project network analysis
    • Harvey RT, Patterson JH (1979) An implicit enumeration algorithm for the time/cost tradeoff problem in project network analysis. Found Control Eng 4:107-117
    • (1979) Found Control Eng , vol.4 , pp. 107-117
    • Harvey, R.T.1    Patterson, J.H.2
  • 7
    • 0030571696 scopus 로고    scopus 로고
    • Optimal procedures for the discrete time/cost trade-off problem in project networks
    • Demeulemeester B, Elmaghraby SE, Herroelen W (1996) Optimal procedures for the discrete time/cost trade-off problem in project networks. Eur J Oper Res 88(1):50-68
    • (1996) Eur J Oper Res , vol.88 , Issue.1 , pp. 50-68
    • Demeulemeester, B.1    Elmaghraby, S.E.2    Herroelen, W.3
  • 9
    • 0025701915 scopus 로고
    • A multi stage non-deterministic model for a project scheduling under resource consideration
    • Tavares LV (1990) A multi stage non-deterministic model for a project scheduling under resource consideration. Eur J Oper Res 49(1):92-101
    • (1990) Eur J Oper Res , vol.49 , Issue.1 , pp. 92-101
    • Tavares, L.V.1
  • 10
    • 34848917527 scopus 로고    scopus 로고
    • The discrete time/cost trade-off problem: Extensions and heuristic procedures
    • Vanhoucke M, Debels D (2007) The discrete time/cost trade-off problem: extensions and heuristic procedures. J Sched 10(4/5):311-326
    • (2007) J Sched , vol.10 , Issue.4-5 , pp. 311-326
    • Vanhoucke, M.1    Debels, D.2
  • 11
    • 71949090693 scopus 로고    scopus 로고
    • Ant colony optimization algorithm for stochastic project crashing problem in PERT networks using MC simulation
    • Aghaie A, Mokhtari H (2009) Ant colony optimization algorithm for stochastic project crashing problem in PERT networks using MC simulation. Int J Adv Manuf Technol 45:1051-1067
    • (2009) Int J Adv Manuf Technol , vol.45 , pp. 1051-1067
    • Aghaie, A.1    Mokhtari, H.2
  • 12
    • 0014804811 scopus 로고
    • Optimum time compression in project scheduling
    • Lamberson LR, Hocking RR (1970) Optimum time compression in project scheduling. Manag Sci 16(10):B597-B606
    • (1970) Manag Sci , vol.16 , Issue.10
    • Lamberson, L.R.1    Hocking, R.R.2
  • 13
    • 0042416400 scopus 로고
    • Resource allocation in PERT network under continuous time-cost functions
    • Berman EB (1964) Resource allocation in PERT network under continuous time-cost functions. Manag Sci 10(4):734-745
    • (1964) Manag Sci , vol.10 , Issue.4 , pp. 734-745
    • Berman, E.B.1
  • 14
    • 0015484051 scopus 로고
    • Critical path problem with concave cost-time curves
    • Falk J, Horowitz J (1972) Critical path problem with concave cost-time curves. Manag Sci 19(4):446-455
    • (1972) Manag Sci , vol.19 , Issue.4 , pp. 446-455
    • Falk, J.1    Horowitz, J.2
  • 15
    • 0028547527 scopus 로고
    • A decomposition approach to project compression with Concave activity cost functions
    • Kuyumcu A, Garcia-Diaz A. A decomposition approach to project compression with Concave activity cost functions. IIE Trans 1994;(26):63-73.
    • (1994) IIE Trans , Issue.26 , pp. 63-73
    • Kuyumcu, A.1    Garcia-Diaz, A.2
  • 16
    • 0022735435 scopus 로고
    • A goal programming model for project crashing with piecewise linear time-cost trade-off
    • Vrat P, Kriengkrairut C (1986) A goal programming model for project crashing with piecewise linear time-cost trade-off. Eng Costs Prod Econ 10(1/2):161-172
    • (1986) Eng Costs Prod Econ , vol.10 , Issue.1-2 , pp. 161-172
    • Vrat, P.1    Kriengkrairut, C.2
  • 17
    • 0001620447 scopus 로고
    • Critical-path planning and scheduling: Mathematical basis
    • Kelley JE (1961) Critical-path planning and scheduling: mathematical basis. Oper Res 9(3):296-320
    • (1961) Oper Res , vol.9 , Issue.3 , pp. 296-320
    • Kelley, J.E.1
  • 19
    • 0035193271 scopus 로고    scopus 로고
    • A GA-based fuzzy optimal model for construction time cost trade off
    • Leu S, Chen A, Yang C (2001) A GA-based fuzzy optimal model for construction time cost trade off. Int J Proj Manag 19(1):47-58
    • (2001) Int J Proj Manag , vol.19 , Issue.1 , pp. 47-58
    • Leu, S.1    Chen, A.2    Yang, C.3
  • 20
    • 4544318435 scopus 로고    scopus 로고
    • The Lp/Ip hybrid method for construction time cost trade off analysis
    • Burns SA, Liu L, Weifeng C (1996) The Lp/Ip hybrid method for construction time cost trade off analysis. Constr Manag Econ 14 (3):265-275
    • (1996) Constr Manag Econ , vol.14 , Issue.3 , pp. 265-275
    • Burns, S.A.1    Liu, L.2    Weifeng, C.3
  • 21
    • 0004374576 scopus 로고    scopus 로고
    • A time cost trade off model with resource consideration using genetic algorithm
    • Chua DKH, Chan WT, Govindan K (1997) A time cost trade off model with resource consideration using genetic algorithm. Civ Eng Environ Syst 14:291-311
    • (1997) Civ Eng Environ Syst , vol.14 , pp. 291-311
    • Dkh, C.1    Chan, W.T.2    Govindan, K.3
  • 22
    • 33749155193 scopus 로고    scopus 로고
    • Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting
    • Buddhakulsomsiri J, Kim D (2006) Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting. Eur J Oper Res 175(1):279-295
    • (2006) Eur J Oper Res , vol.175 , Issue.1 , pp. 279-295
    • Buddhakulsomsiri, J.1    Kim, D.2
  • 23
    • 0000302371 scopus 로고
    • A note on "a Simple CPM Time-Cost Tradeoff Algorithm"
    • SK GOYAL (1975) A note on "A Simple CPM Time-Cost Tradeoff Algorithm". Manag Sci 21(6):718-722
    • (1975) Manag Sci , vol.21 , Issue.6 , pp. 718-722
    • Goyal, S.K.1
  • 24
    • 19244376018 scopus 로고
    • A simple CPM time-cost tradeoff algorithm
    • Siemens N (1971) A simple CPM time-cost tradeoff algorithm. Manag Sci 17(6):354-363
    • (1971) Manag Sci , vol.17 , Issue.6 , pp. 354-363
    • Siemens, N.1
  • 25
    • 13444269168 scopus 로고    scopus 로고
    • Project scheduling under uncertainty: Survey and research potentials
    • Herroelen W, Leus R (2005) Project scheduling under uncertainty: survey and research potentials. Eur J Oper Res 165(2):289-306
    • (2005) Eur J Oper Res , vol.165 , Issue.2 , pp. 289-306
    • Herroelen, W.1    Leus, R.2
  • 26
    • 21844509199 scopus 로고
    • Stochastic gradient-based time-cost tradeoffs in PERT networks using simulation
    • Bowman RA (1994) Stochastic gradient-based time-cost tradeoffs in PERT networks using simulation. Ann Oper Res 53(1):533-551
    • (1994) Ann Oper Res , vol.53 , Issue.1 , pp. 533-551
    • Bowman, R.A.1
  • 27
    • 0035313915 scopus 로고    scopus 로고
    • Crashing PERT networks using mathematical programming
    • Abbasi G, Mukattash AM (2001) Crashing PERT networks using mathematical programming. Int J Proj Manag 19(3):181-188
    • (2001) Int J Proj Manag , vol.19 , Issue.3 , pp. 181-188
    • Abbasi, G.1    Mukattash, A.M.2
  • 28
    • 0000439471 scopus 로고
    • Optimal time-cost trade-offs in GERT networks
    • Arisawa S, Elmaghraby SE (1972) Optimal time-cost trade-offs in GERT networks. Manag Sci 18(11):589-599
    • (1972) Manag Sci , vol.18 , Issue.11 , pp. 589-599
    • Arisawa, S.1    Elmaghraby, S.E.2
  • 29
    • 0032120296 scopus 로고    scopus 로고
    • A heuristic for network project scheduling with random activity durations depending on the resource allocation
    • Golenko-Ginzberg D, Gonik A (1998) A heuristic for network project scheduling with random activity durations depending on the resource allocation. Int J Prod Econ 55(2):149-162
    • (1998) Int J Prod Econ , vol.55 , Issue.2 , pp. 149-162
    • Golenko-Ginzberg, D.1    Gonik, A.2
  • 30
    • 0347410241 scopus 로고
    • Net-present value cost/time trade off
    • Sunde L, Lichtenberg S (1995) Net-present value cost/time trade off. Int J Proj Manag 13(1):45-49
    • (1995) Int J Proj Manag , vol.13 , Issue.1 , pp. 45-49
    • Sunde, L.1    Lichtenberg, S.2
  • 31
    • 0027222453 scopus 로고
    • PERT and crashing revisited: Mathematical generalization
    • Foldes S, Soumis F (1993) PERT and crashing revisited: mathematical generalization. Eur J Oper Res 64(2):286-294
    • (1993) Eur J Oper Res , vol.64 , Issue.2 , pp. 286-294
    • Foldes, S.1    Soumis, F.2
  • 32
    • 0347110998 scopus 로고    scopus 로고
    • A stochastic branch-and-bound approach to activity crashing in project management
    • Gutjahr WJ, Strauss C, Wagner E (2000) A stochastic branch-and-bound approach to activity crashing in project management. INFORMS J Comput 12(2):125-135
    • (2000) INFORMS J Comput , vol.12 , Issue.2 , pp. 125-135
    • Gutjahr, W.J.1    Strauss, C.2    Wagner, E.3
  • 33
    • 50849083841 scopus 로고    scopus 로고
    • A heuristic procedure for solving the dynamic probabilistic project expediting problem
    • Bergman RL (2009) A heuristic procedure for solving the dynamic probabilistic project expediting problem. Eur J Oper Res 192(1):125-137
    • (2009) Eur J Oper Res , vol.192 , Issue.1 , pp. 125-137
    • Bergman, R.L.1
  • 34
    • 34848847781 scopus 로고    scopus 로고
    • An effective methodology for the stochastic project compression problem
    • Mitchell G, Klastorin T (2007) An effective methodology for the stochastic project compression problem. IIE Trans 39(10):957-969
    • (2007) IIE Trans , vol.39 , Issue.10 , pp. 957-969
    • Mitchell, G.1    Klastorin, T.2
  • 35
    • 33846884364 scopus 로고    scopus 로고
    • A stochastic multimode model for time cost tradeoffs under management flexibility
    • Godinho PC, Costa JP (2007) A stochastic multimode model for time cost tradeoffs under management flexibility. OR Spectrum 29 (2):311-334
    • (2007) OR Spectrum , vol.29 , Issue.2 , pp. 311-334
    • Godinho, P.C.1    Costa, J.P.2
  • 36
    • 60749118499 scopus 로고    scopus 로고
    • A simulation approach to the PERT/ CPM time-cost trade-off problem
    • Haga W, Marold K (2004) A simulation approach to the PERT/ CPM time-cost trade-off problem. Proj Manage J 35(2):31-37
    • (2004) Proj Manage J , vol.35 , Issue.2 , pp. 31-37
    • Haga, W.1    Marold, K.2
  • 37
    • 60749091369 scopus 로고    scopus 로고
    • Monitoring and control of PERT networks
    • Haga W, Marold K (2005) Monitoring and control of PERT networks. Bus Rev Cambridge 3(2):240-245
    • (2005) Bus Rev Cambridge , vol.3 , Issue.2 , pp. 240-245
    • Haga, W.1    Marold, K.2
  • 38
    • 0025701917 scopus 로고
    • Project compression: A method for speeding up resource constrained projects which preserve the activity schedule
    • Yau C, Ritche E (1990) Project compression: a method for speeding up resource constrained projects which preserve the activity schedule. Eur J Oper Res 49(1):140-152
    • (1990) Eur J Oper Res , vol.49 , Issue.1 , pp. 140-152
    • Yau, C.1    Ritche, E.2
  • 39
    • 0034172005 scopus 로고    scopus 로고
    • Stochastic construction time-cost trade off analysis
    • Feng CW, Liu L, Burns SA (2000) Stochastic construction time-cost trade off analysis. J Comput Civil Eng 14(2):117-126
    • (2000) J Comput Civil Eng , vol.14 , Issue.2 , pp. 117-126
    • Feng, C.W.1    Liu, L.2    Burns, S.A.3
  • 40
    • 26044472796 scopus 로고    scopus 로고
    • A genetic algorithm approach for the time-cost trade-off in PERT networks
    • Azaron A, Perkgoz C, Sakawa M (2005) A genetic algorithm approach for the time-cost trade-off in PERT networks. Appl Math Comput 168(2):1317-1339
    • (2005) Appl Math Comput , vol.168 , Issue.2 , pp. 1317-1339
    • Azaron, A.1    Perkgoz, C.2    Sakawa, M.3
  • 41
    • 33645892898 scopus 로고    scopus 로고
    • A multi objective resource allocation problem in PERT networks
    • Azaron A, Katagiri H, Sakawa M, Kato K, Memariani A (2006) A multi objective resource allocation problem in PERT networks. Eur J Oper Res 172(3):838-854
    • (2006) Eur J Oper Res , vol.172 , Issue.3 , pp. 838-854
    • Azaron, A.1    Katagiri, H.2    Sakawa, M.3    Kato, K.4    Memariani, A.5
  • 42
    • 33749527990 scopus 로고    scopus 로고
    • A multi objective resource allocation problem in dynamic PERT networks
    • Azaron A, Tavakkoli-Moghaddam R (2006) A multi objective resource allocation problem in dynamic PERT networks. Eur J Oper Res 181(1):163-174
    • (2006) Eur J Oper Res , vol.181 , Issue.1 , pp. 163-174
    • Azaron, A.1    Tavakkoli-Moghaddam, R.2
  • 43
    • 33846882404 scopus 로고    scopus 로고
    • Time-cost trade-off via optimal control theory in Markov PERT networks
    • Azaron A, Katagiri H, Sakawa M (2007) Time-cost trade-off via optimal control theory in Markov PERT networks. Ann Oper Res 150(1):47-64
    • (2007) Ann Oper Res , vol.150 , Issue.1 , pp. 47-64
    • Azaron, A.1    Katagiri, H.2    Sakawa, M.3
  • 44
    • 47349107175 scopus 로고    scopus 로고
    • Time-cost optimization: Using GA and fuzzy sets theory for uncertainties in cost
    • Eshtehardian E, Afshar A, Abbasnia R (2008) Time-cost optimization: using GA and fuzzy sets theory for uncertainties in cost. Constr Manag Econ 26(7):679-691
    • (2008) Constr Manag Econ , vol.26 , Issue.7 , pp. 679-691
    • Eshtehardian, E.1    Afshar, A.2    Abbasnia, R.3
  • 45
    • 78650299960 scopus 로고    scopus 로고
    • Statistical Research Paper No. 18, City University, November 1997, ISBN 1 901615 18 9
    • Wolstenholme LC (1997) A Characterization of Phase Type Distributions, Statistical Research Paper No. 18, City University, November 1997, ISBN 1 901615 18 9
    • (1997) A Characterization of Phase Type Distributions
    • Wolstenholme, L.C.1
  • 46
    • 78650302772 scopus 로고    scopus 로고
    • Crawford, Department of Statistics, University of California, Berkeley, Fall 2008
    • Crawford, Statistical Course Textbook: 200A (2008) Department of Statistics, University of California, Berkeley, Fall 2008
    • (2008) Statistical Course Textbook 200A
  • 48
    • 0000738834 scopus 로고
    • Monte Carlo methods and the PERT problem
    • Van Slyke RM (1963) Monte Carlo methods AND the PERT problem. Oper Res 11(5):839-860
    • (1963) Oper Res , vol.11 , Issue.5 , pp. 839-860
    • Van Slyke, R.M.1
  • 49
    • 0018738242 scopus 로고
    • The use of cutsets in Monte Carlo analysis of stochastic networks
    • Signal CE, Pritsker AAB, Solberg JJ (1979) The use of cutsets in Monte Carlo analysis of stochastic networks. Math Comput Simul 21(4):376-384
    • (1979) Math Comput Simul , vol.21 , Issue.4 , pp. 376-384
    • Signal, C.E.1    Aab, P.2    Solberg, J.J.3
  • 50
    • 0029203560 scopus 로고
    • Efficient estimation of arc criticalities in stochastic activity networks
    • Bowman RA (1995) Efficient estimation of arc criticalities in stochastic activity networks. Manag Sci 41(1):58-67
    • (1995) Manag Sci , vol.41 , Issue.1 , pp. 58-67
    • Bowman, R.A.1
  • 51
    • 0028393308 scopus 로고
    • The most critical path in a PERT Network
    • Soroush HM (1994) The most critical path in a PERT Network. J Opl Res Soc 45(3):287-300
    • (1994) J Opl Res Soc , vol.45 , Issue.3 , pp. 287-300
    • Soroush, H.M.1
  • 52
    • 0037125664 scopus 로고    scopus 로고
    • Path critical index and activity critical index in PERT networks
    • Fatemi Ghomi SMT, Teimouri E (2002) Path critical index and activity critical index in PERT networks. Eur J Oper Res 141(1):147-152
    • (2002) Eur J Oper Res , vol.141 , Issue.1 , pp. 147-152
    • Fatemi Ghomi, S.M.T.1    Teimouri, E.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.