Volumn 23, Issue 4, 2008, Pages 1871-1882

Security coordinated maintenance scheduling in deregulation based on genco contribution to unserved energy

Author keywords

Maintenance scheduling; Medium term operations; Production scheduling; Restructured power systems

Indexed keywords

COORDINATION PROCESS; INDEPENDENT SYSTEM OPERATORS; LARGE-SCALE POWER SYSTEMS; MAINTENANCE PLANS; MAINTENANCE SCHEDULES; MAINTENANCE SCHEDULING; MEDIUM-TERM OPERATIONS; NEW APPROACHES; ONTARIO; POWER SYSTEMS; PRODUCTION SCHEDULING; RESTRUCTURED POWER SYSTEMS; SECURITY CONSTRAINED;

EID: 70350534857     PISSN: 08858950     EISSN: None     Source Type: Journal    
DOI: 10.1109/TPWRS.2008.2002296     Document Type: Article
Times cited : (35)

References (25)
  • 1
    • 0026203507 scopus 로고
    • Optimal generating unit maintenance scheduling for multi-area system with network constraints
    • Aug
    • L. N. Chen and J. Toyoda, "Optimal generating unit maintenance scheduling for multi-area system with network constraints," IEEE Trans. Power Syst., vol. 6, no. 3, pp. 1168-1174, Aug. 1991.
    • (1991) IEEE Trans. Power Syst , vol.6 , Issue.3 , pp. 1168-1174
    • Chen, L.N.1    Toyoda, J.2
  • 2
    • 0029405654 scopus 로고
    • A systems approach to least-cost maintenance scheduling for an interconnected power system
    • Nov
    • D. Chattopadhyay, K. Bhattacharya, and J. Parikh, "A systems approach to least-cost maintenance scheduling for an interconnected power system," IEEE Trans. Power Syst., vol. 10, no. 4, pp. 2002-2007, Nov. 1995.
    • (1995) IEEE Trans. Power Syst , vol.10 , Issue.4 , pp. 2002-2007
    • Chattopadhyay, D.1    Bhattacharya, K.2    Parikh, J.3
  • 3
    • 0032138729 scopus 로고    scopus 로고
    • Integrated generation and transmission maintenance scheduling with network constraints
    • Aug
    • M. K. C. Marwali and S. M. Shahidehpour, "Integrated generation and transmission maintenance scheduling with network constraints," IEEE Trans. Power Syst., vol. 13, no. 3, pp. 1063-1068, Aug. 1998.
    • (1998) IEEE Trans. Power Syst , vol.13 , Issue.3 , pp. 1063-1068
    • Marwali, M.K.C.1    Shahidehpour, S.M.2
  • 4
    • 0034186789 scopus 로고    scopus 로고
    • Generation maintenance scheduling considering transmission constraints
    • May
    • E. L. da Silva, M. T. Schilling, and M. C. Rafael, "Generation maintenance scheduling considering transmission constraints," IEEE Trans. Power Syst., vol. 15, no. 2, pp. 838-843, May 2000.
    • (2000) IEEE Trans. Power Syst , vol.15 , Issue.2 , pp. 838-843
    • da Silva, E.L.1    Schilling, M.T.2    Rafael, M.C.3
  • 6
    • 18944379628 scopus 로고    scopus 로고
    • Generation maintenance scheduling in restructured power systems
    • May
    • A. J. Conejo, R. Garcia-Bertrand, and M. Diaz-Salazar, "Generation maintenance scheduling in restructured power systems," IEEE Trans. Power Syst., vol. 20, no. 2, pp. 984-992, May 2005.
    • (2005) IEEE Trans. Power Syst , vol.20 , Issue.2 , pp. 984-992
    • Conejo, A.J.1    Garcia-Bertrand, R.2    Diaz-Salazar, M.3
  • 7
    • 39749084088 scopus 로고    scopus 로고
    • GENCO's risk-based maintenance outage scheduling
    • Feb
    • L. Wu and S. M. Shahidehpour, "GENCO's risk-based maintenance outage scheduling," IEEE Trans. Power Syst., vol. 23, no. 1, pp. 127-136, Feb. 2008.
    • (2008) IEEE Trans. Power Syst , vol.23 , Issue.1 , pp. 127-136
    • Wu, L.1    Shahidehpour, S.M.2
  • 8
    • 13844309961 scopus 로고    scopus 로고
    • Composite system maintenance coordination in a deregulated environment
    • Feb
    • R. Billinton and R. Mo, "Composite system maintenance coordination in a deregulated environment," IEEE Trans. Power Syst., vol. 20, no. 1, pp. 485-492, Feb. 2005.
    • (2005) IEEE Trans. Power Syst , vol.20 , Issue.1 , pp. 485-492
    • Billinton, R.1    Mo, R.2
  • 9
    • 0031079076 scopus 로고    scopus 로고
    • Contributions of individual generators to loads and flows
    • Feb
    • D. Kirschen, R. Allan, and G. Strbac, "Contributions of individual generators to loads and flows," IEEE Trans. Power Syst., vol. 12, no. 1, pp. 52-60, Feb. 1997.
    • (1997) IEEE Trans. Power Syst , vol.12 , Issue.1 , pp. 52-60
    • Kirschen, D.1    Allan, R.2    Strbac, G.3
  • 10
    • 0032592963 scopus 로고    scopus 로고
    • Goal programming approach to maintenance scheduling of generating units in large scale power systems
    • Aug
    • L. M. Moro and A. Ramos, "Goal programming approach to maintenance scheduling of generating units in large scale power systems," IEEE Trans. Power Syst., vol. 14, no. 3, pp. 1021-1028, Aug. 1999.
    • (1999) IEEE Trans. Power Syst , vol.14 , Issue.3 , pp. 1021-1028
    • Moro, L.M.1    Ramos, A.2
  • 11
    • 0030083055 scopus 로고    scopus 로고
    • A multi-area linear programming approach for analysis of economic operation of the Indian power system
    • Feb
    • J. Parikh and D. Chattopadhyay, "A multi-area linear programming approach for analysis of economic operation of the Indian power system," IEEE Trans. Power Syst., vol. 11, no. 1, pp. 52-58, Feb. 1996.
    • (1996) IEEE Trans. Power Syst , vol.11 , Issue.1 , pp. 52-58
    • Parikh, J.1    Chattopadhyay, D.2
  • 12
    • 0019544908 scopus 로고
    • Maintenance scheduling for generator system planning
    • Mar
    • J. P. Stremel, "Maintenance scheduling for generator system planning," IEEE Trans. Power App. Syst., vol. PAS-100, pp. 1410-1419, Mar. 1981.
    • (1981) IEEE Trans. Power App. Syst , vol.PAS-100 , pp. 1410-1419
    • Stremel, J.P.1
  • 13
    • 0026155671 scopus 로고
    • Power plant maintenance scheduling: Optimizing economics and reliability
    • May
    • R. Mukerji, H. M. Merrill, B. W. Erickson, and J. H. Parker, "Power plant maintenance scheduling: Optimizing economics and reliability," IEEE Trans. Power Syst., vol. 6, no. 2, pp. 476-483, May 1991.
    • (1991) IEEE Trans. Power Syst , vol.6 , Issue.2 , pp. 476-483
    • Mukerji, R.1    Merrill, H.M.2    Erickson, B.W.3    Parker, J.H.4
  • 14
    • 0032592946 scopus 로고    scopus 로고
    • A multi-objective operations planning model with unit commitment and transmission constraints
    • Aug
    • D. Chattopadhyay and J. Momoh, "A multi-objective operations planning model with unit commitment and transmission constraints," IEEE Trans. Power Syst., vol. 14, no. 3, pp. 1078-1084, Aug. 1999.
    • (1999) IEEE Trans. Power Syst , vol.14 , Issue.3 , pp. 1078-1084
    • Chattopadhyay, D.1    Momoh, J.2
  • 15
    • 0032204113 scopus 로고    scopus 로고
    • A practical maintenance scheduling program: Mathematical model and case study
    • Nov
    • D. Chattopadhyay, "A practical maintenance scheduling program: Mathematical model and case study," IEEE Trans. Power Syst., vol. 13, no. 4, pp. 1475-1480, Nov. 1998.
    • (1998) IEEE Trans. Power Syst , vol.13 , Issue.4 , pp. 1475-1480
    • Chattopadhyay, D.1
  • 16
    • 0031999189 scopus 로고    scopus 로고
    • A new long-term hydro-production scheduling method for maximizing the profit of hydroelectric systems
    • Feb
    • Z. Yu, F. T. Sparrow, and B. H. Bowen, "A new long-term hydro-production scheduling method for maximizing the profit of hydroelectric systems," IEEE Trans. Power Syst., vol. 13, no. 1, pp. 66-71, Feb. 1998.
    • (1998) IEEE Trans. Power Syst , vol.13 , Issue.1 , pp. 66-71
    • Yu, Z.1    Sparrow, F.T.2    Bowen, B.H.3
  • 17
    • 0004479496 scopus 로고    scopus 로고
    • A probabilistic approach to generation maintenance scheduler with network constraints
    • M. K. C. Marwali and S. M. Shahidehpour, "A probabilistic approach to generation maintenance scheduler with network constraints," Elect. Power Energy Syst., vol. 21, pp. 533-545, 1999.
    • (1999) Elect. Power Energy Syst , vol.21 , pp. 533-545
    • Marwali, M.K.C.1    Shahidehpour, S.M.2
  • 18
    • 0028550745 scopus 로고
    • CHOPIN, a heuristic model for long term transmission expansion planning
    • Nov
    • G. L. Bayona and I. J. P. Arriaga, "CHOPIN, a heuristic model for long term transmission expansion planning," IEEE Trans. Power Syst., vol. 9, no. 4, pp. 1886-1894, Nov. 1994.
    • (1994) IEEE Trans. Power Syst , vol.9 , Issue.4 , pp. 1886-1894
    • Bayona, G.L.1    Arriaga, I.J.P.2
  • 19
    • 0142071752 scopus 로고    scopus 로고
    • Analysis of heuristic algorithms for the transportation model in static and multistage planning in network expansion systems
    • Sep
    • R. Romero, C. Rocha, and J. R. S. Mantovani, "Analysis of heuristic algorithms for the transportation model in static and multistage planning in network expansion systems," Proc. Inst. Elect. Eng., Gen., Transm., Distrib., vol. 150, no. 5, pp. 521-526, Sep. 2003.
    • (2003) Proc. Inst. Elect. Eng., Gen., Transm., Distrib , vol.150 , Issue.5 , pp. 521-526
    • Romero, R.1    Rocha, C.2    Mantovani, J.R.S.3
  • 20
    • 70350555194 scopus 로고    scopus 로고
    • Available
    • [Online]. Available: http://www.theimo.com.
  • 21
    • 70350544964 scopus 로고    scopus 로고
    • Available
    • [Online]. Available: http://www.hydroone.com.
  • 22
    • 70350563015 scopus 로고    scopus 로고
    • Available: .on.ca
    • [Online]. Available: http://www.powerauthority.on.ca.
  • 23
    • 0032592961 scopus 로고    scopus 로고
    • The IEEE reliability test system-1996
    • Aug
    • "The IEEE reliability test system-1996," IEEE Trans. Power Syst. vol. 14, no. 3, pp. 1010-1020, Aug. 1999.
    • (1999) IEEE Trans. Power Syst , vol.14 , Issue.3 , pp. 1010-1020
  • 24
    • 0018544097 scopus 로고    scopus 로고
    • P. M. Subcommittee, IEEE reliability test system, IEEE Trans. Power App. Syst., PAS-98, no. 6, pp. 2047-2054, Nov./Dec. 1979.
    • P. M. Subcommittee, "IEEE reliability test system," IEEE Trans. Power App. Syst., vol. PAS-98, no. 6, pp. 2047-2054, Nov./Dec. 1979.
  • 25
    • 70350562876 scopus 로고    scopus 로고
    • GAMS Development Corporation, A User's Guide, 2005, GAMS Release 2.50.
    • GAMS Development Corporation, A User's Guide, 2005, GAMS Release 2.50.


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.