1
-
-
0038522575
-
Insertion techniques for static and dynamic resource-constrained project scheduling
-
C. Artigues, P. Michelon, S. Reusser, "Insertion techniques for static and dynamic resource-constrained project scheduling," European Journal of Operational Research, vol, 149, pp. 249-267, 2003.
-
(2003)
European Journal of Operational Research
, vol.149
, pp. 249-267
-
-
Artigues, C.1
Michelon, P.2
Reusser, S.3
-
2
-
-
0019342681
-
Scheduling projects to resource constraints: Classification and complexity
-
Blazewicz, J., Lenstra, J.K. and Rinnooy Kan, A. H. G., "Scheduling projects to resource constraints: Classification and complexity," Discrete Applied Mathematics, vol. 5, pp. 11-24, 1959.
-
(1959)
Discrete Applied Mathematics
, vol.5
, pp. 11-24
-
-
Blazewicz, J.1
Lenstra, J.K.2
Rinnooy Kan, A.H.G.3
-
3
-
-
0030124780
-
A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes
-
F.F. Boctor, "A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes", European Journal of Operational Research, vol.90, pp. 349-361, 1996.
-
(1996)
European Journal of Operational Research
, vol.90
, pp. 349-361
-
-
Boctor, F.F.1
-
4
-
-
0037508562
-
A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple modes version
-
K. Bouleimen, H. Lecocq, "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple modes version," European Journal of Operational Research, vol. 149, pp. 268-281, 2003.
-
(2003)
European Journal of Operational Research
, vol.149
, pp. 268-281
-
-
Bouleimen, K.1
Lecocq, H.2
-
5
-
-
0001691215
-
Scheduling Parallel Manufacturing Cells with Resource Flexibility
-
R. L. Daniels, B. J. Hoopes, and J. B. Mazzola, "Scheduling Parallel Manufacturing Cells with Resource Flexibility," Management Science, vol. 42, pp. 1260-1276, 1996.
-
(1996)
Management Science
, vol.42
, pp. 1260-1276
-
-
Daniels, R.L.1
Hoopes, B.J.2
Mazzola, J.B.3
-
6
-
-
0043173975
-
Extensions of an integrated approach for multi-resource shop scheduling
-
S. Dauzere-Peres, C. Pavageau, "Extensions of an integrated approach for multi-resource shop scheduling," IEEE Transactions, vol. 33, pp. 207-213, 2003.
-
(2003)
IEEE Transactions
, vol.33
, pp. 207-213
-
-
Dauzere-Peres, S.1
Pavageau, C.2
-
7
-
-
0032094795
-
Multi-resource shop scheduling with resource flexibility
-
S. Dauzere-Peres, J. Roux, J.B. Lasserre, "Multi-resource shop scheduling with resource flexibility," European Journal of Operational Research, vol. 107, pp. 289-305, 1998.
-
(1998)
European Journal of Operational Research
, vol.107
, pp. 289-305
-
-
Dauzere-Peres, S.1
Roux, J.2
Lasserre, J.B.3
-
8
-
-
0042403497
-
The discrete time/resource trade-off problem in project networks-A branch-and-bound approach
-
9717, Department of Applied Economics, K.U. Leuven
-
Demeulemeester, E., Reyck, B. D. and Herroelen, W., "The discrete time/resource trade-off problem in project networks-A branch-and-bound approach", Research report 9717, Department of Applied Economics, K.U. Leuven, 1997.
-
(1997)
Research report
-
-
Demeulemeester, E.1
Reyck, B.D.2
Herroelen, W.3
-
9
-
-
0034559432
-
Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem
-
S. Hartmann, R. Kolisch, "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," European Journal of Operational Research, vol. 127, pp. 394-407, 2000.
-
(2000)
European Journal of Operational Research
, vol.127
, pp. 394-407
-
-
Hartmann, S.1
Kolisch, R.2
-
10
-
-
0040577754
-
-
S. Hartmann and A. Drexl, Project scheduling with multiple modes: A comparison of exact algorithms, Networks, 32, pp. 283-297, 1, 998.
-
S. Hartmann and A. Drexl, "Project scheduling with multiple modes: A comparison of exact algorithms," Networks, vol. 32, pp. 283-297, 1, 998.
-
-
-
-
11
-
-
0032042933
-
Resource- Constrained Project Scheduling: A survey of recent developments
-
W. Herroelen, B. De Reyck and E. Demeulemeester, "Resource- Constrained Project Scheduling: A survey of recent developments," Computer Ops Res., vol. 25, pp. 279-302, 1998.
-
(1998)
Computer Ops Res
, vol.25
, pp. 279-302
-
-
Herroelen, W.1
De Reyck, B.2
Demeulemeester, E.3
-
12
-
-
33745797772
-
Experimental investigation of heuristics for resource-constrained project scheduling: An update
-
to appear
-
R. Kolisch, S. Hartmann, "Experimental investigation of heuristics for resource-constrained project scheduling: An update," European Journal of Operational Researeh, 2005, to appear.
-
(2005)
European Journal of Operational Researeh
-
-
Kolisch, R.1
Hartmann, S.2
-
13
-
-
0000698758
-
Characterization and generation of a general class of resource-constrained project scheduling problems
-
R. Kolisch, A. Sprecher and A. Drexl, "Characterization and generation of a general class of resource-constrained project scheduling problems", Management Science, vol. 41, pp. 1693-1703, 1995.
-
(1995)
Management Science
, vol.41
, pp. 1693-1703
-
-
Kolisch, R.1
Sprecher, A.2
Drexl, A.3
-
14
-
-
0030121479
-
Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation
-
R. Kolisch, "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, vol. 90, pp. 320-333.1996.
-
(1996)
European Journal of Operational Research
, vol.90
, pp. 320-333
-
-
Kolisch, R.1
-
15
-
-
0002577337
-
Effective Neighborhood Functions for the Flexible Job Shop Problem
-
M. Mastrolilli, L.M. Gambardella, "Effective Neighborhood Functions for the Flexible Job Shop Problem", Journal of Scheduling, vol. 3, pp.3-20, 2000.
-
(2000)
Journal of Scheduling
, vol.3
, pp. 3-20
-
-
Mastrolilli, M.1
Gambardella, L.M.2
-
16
-
-
51749100127
-
Greedy Heuristic and Genetic Algorithms for the Muiti- Shop Scheduling with Resource Flexibility
-
France
-
Y. Mati, N. Rezg, and X. Xie, "Greedy Heuristic and Genetic Algorithms for the Muiti- Shop Scheduling with Resource Flexibility," INRIA, MACSI Project, France, 2002.
-
(2002)
INRIA, MACSI Project
-
-
Mati, Y.1
Rezg, N.2
Xie, X.3
-
17
-
-
0010909013
-
Class-Based Control Schemes for Parameterized Project Scheduling Heuristics,
-
Technical Report 456, Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel, April
-
A. Schimer, S. Riesenberg "Class-Based Control Schemes for Parameterized Project Scheduling Heuristics," Technical Report 456, Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel, April 1998.
-
(1998)
-
-
Schimer, A.1
Riesenberg, S.2
-
18
-
-
0029636114
-
Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem
-
A. Sprecher, R. Kolisch, A. Drexl, "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, vol. 80, pp. 94-102, 1995.
-
(1995)
European Journal of Operational Research
, vol.80
, pp. 94-102
-
-
Sprecher, A.1
Kolisch, R.2
Drexl, A.3
|