메뉴 건너뛰기




Volumn 71, Issue 2, 2004, Pages 99-107

Evaluation of generation and transmission maintenance strategies based on reliability worth

Author keywords

Interruption costs; Maintenance strategies; Outage scheduling; Reliability worth

Indexed keywords

ALGORITHMS; COMPUTER SIMULATION; ELECTRIC POWER TRANSMISSION; HEURISTIC METHODS; MAINTENANCE; MONTE CARLO METHODS;

EID: 2542448579     PISSN: 03787796     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.epsr.2004.01.008     Document Type: Article
Times cited : (17)

References (17)
  • 1
    • 0015398090 scopus 로고
    • Adjusting maintenance schedules to levelize risk
    • Garver L.L. Adjusting maintenance schedules to levelize risk. IEEE Trans. PAS. 91:1972;2057-2063.
    • (1972) IEEE Trans. PAS , vol.91 , pp. 2057-2063
    • Garver, L.L.1
  • 2
    • 0019544908 scopus 로고
    • Maintenance scheduling for generation system planning
    • Stremmel J.P. Maintenance scheduling for generation system planning. IEEE Trans. PAS. 100:1981;1410-1419.
    • (1981) IEEE Trans. PAS , vol.100 , pp. 1410-1419
    • Stremmel, J.P.1
  • 3
    • 0021422665 scopus 로고
    • Generating unit maintenance scheduling for single and two interconnected systems
    • El-Sheikhi F.A., Billinton R. Generating unit maintenance scheduling for single and two interconnected systems. IEEE Trans. PAS. 103(5):1984;1038-1044.
    • (1984) IEEE Trans. PAS , vol.103 , Issue.5 , pp. 1038-1044
    • El-Sheikhi, F.A.1    Billinton, R.2
  • 4
    • 0024668655 scopus 로고
    • An interactive package for risk evaluation and maintenance scheduling
    • Contaxis G.C., Kavatza S.D., Vournas C.D. An interactive package for risk evaluation and maintenance scheduling. IEEE Trans. PWRS. 4(2):1989;389-395.
    • (1989) IEEE Trans. PWRS , vol.4 , Issue.2 , pp. 389-395
    • Contaxis, G.C.1    Kavatza, S.D.2    Vournas, C.D.3
  • 6
    • 0026203507 scopus 로고
    • Optimal generating unit maintenance scheduling for multi-area system with network constraints
    • Chen L., Toyoda J. Optimal generating unit maintenance scheduling for multi-area system with network constraints. IEEE Trans. Power Syst. 6:1991;1168-1174.
    • (1991) IEEE Trans. Power Syst. , vol.6 , pp. 1168-1174
    • Chen, L.1    Toyoda, J.2
  • 7
    • 0026909978 scopus 로고
    • An expert system for generator maintenance scheduling using operation index
    • Lin C.E., Huang C.J., Huang C.L., Liang C.C., Lee S.Y. An expert system for generator maintenance scheduling using operation index. IEEE Trans. Power Syst. 7(3):1992;1141-1148.
    • (1992) IEEE Trans. Power Syst. , vol.7 , Issue.3 , pp. 1141-1148
    • Lin, C.E.1    Huang, C.J.2    Huang, C.L.3    Liang, C.C.4    Lee, S.Y.5
  • 9
    • 0032592928 scopus 로고    scopus 로고
    • Long-term transmission maintenance scheduling with network, fuel and emission constraints
    • Marwali M.K.C., Mohammad S. Long-term transmission maintenance scheduling with network, fuel and emission constraints. IEEE Trans. Power Syst. 12(3):1999;1160-1165.
    • (1999) IEEE Trans. Power Syst. , vol.12 , Issue.3 , pp. 1160-1165
    • Marwali, M.K.C.1    Mohammad, S.2
  • 10
    • 0031276372 scopus 로고    scopus 로고
    • Reliability analysis for hydrothermal generating systems including the effect of maintenance scheduling
    • Juan J., Ortega I. Reliability analysis for hydrothermal generating systems including the effect of maintenance scheduling. IEEE Trans. Power Syst. 12(4):1997;1561-1568.
    • (1997) IEEE Trans. Power Syst. , vol.12 , Issue.4 , pp. 1561-1568
    • Juan, J.1    Ortega, I.2
  • 11
    • 84861401294 scopus 로고    scopus 로고
    • Generator maintenance scheduling to maximize reliability and revenues
    • Paper ICM-057, 29 August-2 September, Porto, Portugal
    • A.M. Leite da Silva, G.J. Anders, L.A.F. Manso, Generator maintenance scheduling to maximize reliability and revenues, IEEE Power Tech Conference, Paper ICM-057, 29 August-2 September 2001, Porto, Portugal.
    • (2001) IEEE Power Tech Conference
    • Da Silva, A.M.L.1    Anders, G.J.2    Manso, L.A.F.3
  • 13
    • 0034138495 scopus 로고    scopus 로고
    • Pseudo-chronological simulation for composite reliability analysis with time varying loads
    • Leite da Silva A.M., Manso L.A.F., Mello J.C.O., Billinton R. Pseudo-chronological simulation for composite reliability analysis with time varying loads. IEEE Trans. Power Syst. 15(1):2000;73-80.
    • (2000) IEEE Trans. Power Syst. , vol.15 , Issue.1 , pp. 73-80
    • Da Silva, A.M.L.1    Manso, L.A.F.2    Mello, J.C.O.3    Billinton, R.4
  • 14
    • 0032071144 scopus 로고    scopus 로고
    • Probabilistic evaluation of the effect of maintenance on reliability - An application
    • Endrenyi J., Anders G.J., Leite da Silva A.M. Probabilistic evaluation of the effect of maintenance on reliability - an application. IEEE Trans. Power Syst. 13(2):1998;576-583.
    • (1998) IEEE Trans. Power Syst. , vol.13 , Issue.2 , pp. 576-583
    • Endrenyi, J.1    Anders, G.J.2    Da Silva, A.M.L.3
  • 15
    • 0034186834 scopus 로고    scopus 로고
    • Cost related reliability measure for power system equipment
    • Anders G.J., Leite da Silva A.M. Cost related reliability measure for power system equipment. IEEE Trans. Power Syst. 15(2):2000;654-660.
    • (2000) IEEE Trans. Power Syst. , vol.15 , Issue.2 , pp. 654-660
    • Anders, G.J.1    Da Silva, A.M.L.2
  • 16
    • 0018544097 scopus 로고
    • IEEE reliability test system task force of the application of probability methods subcommittee, IEEE reliability test system
    • IEEE reliability test system task force of the application of probability methods subcommittee, IEEE reliability test system, IEEE Trans. PAS 98 (1979) 2047-2054.
    • (1979) IEEE Trans. PAS , vol.98 , pp. 2047-2054


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.