Volumn 53, Issue 1-2, 2000, Pages 105-112

Resource supportability simulation model for a man-machine production system

Author keywords

Cyclic coordinate descent method; Knapsack resource reallocation model; Man machine production system; Predetermined resource delivery schedule; Resource constrained scheduling

Indexed keywords


EID: 0346106258     PISSN: 03784754     EISSN: None     Source Type: Journal    
DOI: 10.1016/s0378-4754(00)00175-0     Document Type: Article
Times cited : (3)

References (8)
  • 1
    • 0011746296 scopus 로고
    • On solving a large-scale resource reallocation problem in production planning
    • Proceedings of a Joint German/USA Conference. Hagen, Germany, 25-26 June 1992
    • C. Dillenberger, L.F. Escudero, A. Wollensak, Wu. Zhang, On solving a large-scale resource reallocation problem in production planning. In: Operations Research in Production Planning and Control, Proceedings of a Joint German/USA Conference. Hagen, Germany, 25-26 June 1992, (1993) 105-119.
    • (1993) Operations Research in Production Planning and Control , pp. 105-119
    • Dillenberger, C.1    Escudero, L.F.2    Wollensak, A.3    Zhang, Wu.4
  • 2
    • 0031338250 scopus 로고    scopus 로고
    • Job-shop resource scheduling via simulating random operations
    • D. Golenko-Ginzburg, A. Gonik, Job-shop resource scheduling via simulating random operations, J. Math. Comput. Simulation 44 (1997) 427-440.
    • (1997) J. Math. Comput. Simulation , vol.44 , pp. 427-440
    • Golenko-Ginzburg, D.1    Gonik, A.2
  • 3
    • 0030735291 scopus 로고    scopus 로고
    • Stochastic network project scheduling with non-consumable limited resources
    • D. Golenko-Ginzburg, A. Gonik, Stochastic network project scheduling with non-consumable limited resources, Int. J. Prod. Econ. 48 (1997) 29-37.
    • (1997) Int. J. Prod. Econ. , vol.48 , pp. 29-37
    • Golenko-Ginzburg, D.1    Gonik, A.2
  • 4
    • 0032120296 scopus 로고    scopus 로고
    • A heuristic for network project scheduling with random activity durations depending on the resource reallocation
    • D. Golenko-Ginzburg, A. Gonik, A heuristic for network project scheduling with random activity durations depending on the resource reallocation, Int. J. Prod. Econ. 55 (1998) 149-162.
    • (1998) Int. J. Prod. Econ. , vol.55 , pp. 149-162
    • Golenko-Ginzburg, D.1    Gonik, A.2
  • 5
    • 0000623498 scopus 로고
    • Hierarchical control of semi-automated production systems
    • D. Golenko-Ginzburg, Z. Sinuany-Stern, Hierarchical control of semi-automated production systems, Prod. Plan. Control 4 (4) (1993) 361-370.
    • (1993) Prod. Plan. Control , vol.4 , Issue.4 , pp. 361-370
    • Golenko-Ginzburg, D.1    Sinuany-Stern, Z.2
  • 6
    • 0028462456 scopus 로고
    • Kanban Systems as a manufacturing control system with feedback
    • A.A. Pervozvanskiy, I.Ye. Sheynis, Kanban Systems as a manufacturing control system with feedback, J. Comput. Syst. Sci. Int. 32 (4) (1994) 153-157.
    • (1994) J. Comput. Syst. Sci. Int. , vol.32 , Issue.4 , pp. 153-157
    • Pervozvanskiy, A.A.1    Sheynis, I.Ye.2
  • 7
    • 0038654496 scopus 로고
    • Why projects are always late: A rational based on simulation of a PERT/CPM network
    • R.I. Shoenberger, Why projects are always late: a rational based on simulation of a PERT/CPM network, Interfaces 11 (5) (1981) 66-70.
    • (1981) Interfaces , vol.11 , Issue.5 , pp. 66-70
    • Shoenberger, R.I.1