Volumn 37, Issue , 2015, Pages 1-16

Makespan estimation of a production process affected by uncertainty: Application on MTO production of NC machine tools

Author keywords

ETO; Makespan; Manufacturing; MTO; Project scheduling; Uncertainty

Indexed keywords

COMPLEX NETWORKS; MANUFACTURE; SCHEDULING;

EID: 84953319524     PISSN: 02786125     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.jmsy.2015.10.001     Document Type: Article
Times cited : (18)

References (23)
  • 1
    • 34547524657 scopus 로고    scopus 로고
    • Due date quoting and scheduling interaction in production lines
    • A. Alfieri Due date quoting and scheduling interaction in production lines Int J Comput Integr Manuf 20 6 2007 579 587
    • (2007) Int J Comput Integr Manuf , vol.20 , Issue.6 , pp. 579-587
    • Alfieri, A.1
  • 2
    • 84862300001 scopus 로고    scopus 로고
    • A project scheduling approach to production and material requirement planning in manufacturing-to-order environments
    • A. Alfieri, T. Tolio, and M. Urgo A project scheduling approach to production and material requirement planning in manufacturing-to-order environments J Intell Manuf 23 3 2012 575 585
    • (2012) J Intell Manuf , vol.23 , Issue.3 , pp. 575-585
    • Alfieri, A.1    Tolio, T.2    Urgo, M.3
  • 3
    • 84865351186 scopus 로고    scopus 로고
    • A two-stage stochastic programming project scheduling approach to production planning
    • A. Alfieri, T. Tolio, and M. Urgo A two-stage stochastic programming project scheduling approach to production planning Int J Adv Manuf Technol 62 1 2012 279 290
    • (2012) Int J Adv Manuf Technol , vol.62 , Issue.1 , pp. 279-290
    • Alfieri, A.1    Tolio, T.2    Urgo, M.3
  • 5
    • 0021469459 scopus 로고
    • Determining the K most critical paths in PERT networks
    • B.M. Dodin Determining the K most critical paths in PERT networks Oper Res 32 4 1982
    • (1982) Oper Res , vol.32 , Issue.4
    • Dodin, B.M.1
  • 6
    • 0022099676 scopus 로고
    • Bounding the project completion time distribution in pert networks
    • B.M. Dodin Bounding the project completion time distribution in pert networks Oper Res 1985 862 881
    • (1985) Oper Res , pp. 862-881
    • Dodin, B.M.1
  • 9
    • 84941998014 scopus 로고    scopus 로고
    • Revenue management approach to due date quoting and scheduling in a assemble-to-order production system
    • H. Guhlich, M. Fleishmann, and R. Stolletz Revenue management approach to due date quoting and scheduling in a assemble-to-order production system OR Spectrum 37 2015 951 982
    • (2015) OR Spectrum , vol.37 , pp. 951-982
    • Guhlich, H.1    Fleishmann, M.2    Stolletz, R.3
  • 10
    • 49149093475 scopus 로고    scopus 로고
    • Scheduling and due-date quotation in a make-to-order supply chain
    • P. Kaminsky, and O. Kaya Scheduling and due-date quotation in a make-to-order supply chain Naval Res Logist 55 2008 444 458
    • (2008) Naval Res Logist , vol.55 , pp. 444-458
    • Kaminsky, P.1    Kaya, O.2
  • 15
    • 0043289765 scopus 로고    scopus 로고
    • A computational study on bounding the makespan distribution in stochastic project networks
    • A. Ludwig, R.H. Möring, and F. Stork A computational study on bounding the makespan distribution in stochastic project networks Ann Oper Res 102 2001 49 64
    • (2001) Ann Oper Res , vol.102 , pp. 49-64
    • Ludwig, A.1    Möring, R.H.2    Stork, F.3
  • 16
    • 0001501655 scopus 로고
    • Application of a technique for research and developement program evaluation
    • D.G. Malcolm, J.H. Roseboom, C.E. Clark, and W. Fazar Application of a technique for research and developement program evaluation Oper Res 7 1959 646 669
    • (1959) Oper Res , vol.7 , pp. 646-669
    • Malcolm, D.G.1    Roseboom, J.H.2    Clark, C.E.3    Fazar, W.4
  • 18
    • 84929297631 scopus 로고    scopus 로고
    • A risk management-based evaluation of inventory allocations for make-to-order production
    • A.M. Radke, T. Tolio, M.M. Tseng, and M. Urgo A risk management-based evaluation of inventory allocations for make-to-order production CIRP Ann Manuf Technol 1 62 2013 459 462
    • (2013) CIRP Ann Manuf Technol , vol.1 , Issue.62 , pp. 459-462
    • Radke, A.M.1    Tolio, T.2    Tseng, M.M.3    Urgo, M.4
  • 20
    • 34250179507 scopus 로고    scopus 로고
    • A rolling horizon approach to plan outsourcing in manufacturing-to-order environments affected by uncertainty
    • T. Tolio, and M. Urgo A rolling horizon approach to plan outsourcing in manufacturing-to-order environments affected by uncertainty CIRP Ann Manuf Technol 56 1 2007 487 490
    • (2007) CIRP Ann Manuf Technol , vol.56 , Issue.1 , pp. 487-490
    • Tolio, T.1    Urgo, M.2
  • 21
    • 84953247903 scopus 로고    scopus 로고
    • Stochastic scheduling of machining centers production, estimating the makespan distribution
    • K. Windt
    • T. Tolio, and M. Urgo Stochastic scheduling of machining centers production, estimating the makespan distribution K. Windt, Robust manufacturing control 2013 121 133
    • (2013) Robust Manufacturing Control , pp. 121-133
    • Tolio, T.1    Urgo, M.2
  • 22
    • 79957652035 scopus 로고    scopus 로고
    • Robust production control against propagation of disruptions
    • T. Tolio, M. Urgo, and J. Váncza Robust production control against propagation of disruptions CIRP Ann Manuf Technol 1 60 2011 489 492
    • (2011) CIRP Ann Manuf Technol , vol.1 , Issue.60 , pp. 489-492
    • Tolio, T.1    Urgo, M.2    Váncza, J.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.