Volumn 141, Issue 1, 2013, Pages 127-136

A genetic algorithm based heuristic for two machine no-wait flowshop scheduling problems with class setup times that minimizes maximum lateness

Author keywords

Class based setup time; Genetic algorithm; Maximum lateness; No wait flowshop

Indexed keywords

APPROXIMATION SOLUTION; CHEMICAL PRODUCTS; EFFICIENT SCHEDULING; FLOW SHOP SCHEDULING PROBLEM; FLOW-SHOPS; FOOD PROCESSING INDUSTRY; HEURISTIC APPROACH; MACHINE SCHEDULING PROBLEM; MANUFACTURING INDUSTRIES; MAXIMUM LATENESS; NO-WAIT; PRACTICAL PROBLEMS; PRODUCTION PROCESS; REAL-LIFE APPLICATIONS; SCHEDULING PROBLEM; SET-UP TIME; TWO MACHINES;

EID: 84869491856     PISSN: 09255273     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijpe.2012.06.017     Document Type: Article
Times cited : (18)

References (20)
  • 1
    • 34147159638 scopus 로고    scopus 로고
    • A self-adaptive differential evolution heuristic for two-stage assembly scheduling problem to minimize maximum lateness with setup times
    • F.S. Al-Anzi, and A. Allahverdi A self-adaptive differential evolution heuristic for two-stage assembly scheduling problem to minimize maximum lateness with setup times European Journal of Operational Research 182 2007 80 94
    • (2007) European Journal of Operational Research , vol.182 , pp. 80-94
    • Al-Anzi, F.S.1    Allahverdi, A.2
  • 2
    • 60349093593 scopus 로고    scopus 로고
    • Heuristics for a two-stage assembly flowshop with bicriteria of maximum lateness and makespan
    • F.S. Al-Anzi, and A. Allahverdi Heuristics for a two-stage assembly flowshop with bicriteria of maximum lateness and makespan Computers & Operations Research 36 2009 2682 2689
    • (2009) Computers & Operations Research , vol.36 , pp. 2682-2689
    • Al-Anzi, F.S.1    Allahverdi, A.2
  • 6
    • 0025824858 scopus 로고
    • Job lateness in a two machine flow shop with set up time separated
    • P. Dileepan, and T. Sen Job lateness in a two machine flow shop with set up time separated Computers and Operations Research 18 1991 549 556
    • (1991) Computers and Operations Research , vol.18 , pp. 549-556
    • Dileepan, P.1    Sen, T.2
  • 7
    • 0033906893 scopus 로고    scopus 로고
    • Hybrid flow shop scheduling with precedence constraints and time lags to minimize maximum lateness
    • V.B. Genoulaz Hybrid flow shop scheduling with precedence constraints and time lags to minimize maximum lateness International Journal of Production Economics 64 2000 101 111
    • (2000) International Journal of Production Economics , vol.64 , pp. 101-111
    • Genoulaz, V.B.1
  • 11
    • 0030134958 scopus 로고    scopus 로고
    • A survey of machine scheduling problems with blocking and no-wait in process
    • N.G. Hall, and C. Sriskandarajah A survey of machine scheduling problems with blocking and no-wait in process Operations Research 44 3 1996 510 525
    • (1996) Operations Research , vol.44 , Issue.3 , pp. 510-525
    • Hall, N.G.1    Sriskandarajah, C.2
  • 12
    • 0141509086 scopus 로고    scopus 로고
    • A case study in a two-stage hybrid flow shop with setup time and dedicated machines
    • H.T. Lin, and C.J. Liao A case study in a two-stage hybrid flow shop with setup time and dedicated machines International Journal of Production Economics 86 2003 133 143
    • (2003) International Journal of Production Economics , vol.86 , pp. 133-143
    • Lin, H.T.1    Liao, C.J.2
  • 15
    • 0028413569 scopus 로고
    • A no-wait flowshop scheduling heuristic to minimize makespan
    • C. Rajendran A no-wait flowshop scheduling heuristic to minimize makespan The Journal of the Operational Research Society 45 4 1994 472 478
    • (1994) The Journal of the Operational Research Society , vol.45 , Issue.4 , pp. 472-478
    • Rajendran, C.1
  • 16
    • 0015401303 scopus 로고
    • On the flow-shop sequencing problem with no wait in process
    • S.S. Reddi, and C.V. Ramamoorthy On the flow-shop sequencing problem with no wait in process Operational Research Quarterly 23 3 1972 323 331
    • (1972) Operational Research Quarterly , vol.23 , Issue.3 , pp. 323-331
    • Reddi, S.S.1    Ramamoorthy, C.V.2
  • 17
    • 0020291533 scopus 로고
    • Review of scheduling of process operations
    • G.V. Reklaitis Review of scheduling of process operations AIChE Symposium Series 78 1982 119 133
    • (1982) AIChE Symposium Series , vol.78 , pp. 119-133
    • Reklaitis, G.V.1
  • 18
    • 70449578984 scopus 로고    scopus 로고
    • New heuristics for no-wait flow ships with a linear combination of makespan and maximum lateness
    • R. Ruiz, and A. Allahverdi New heuristics for no-wait flow ships with a linear combination of makespan and maximum lateness International Journal of Production Research 47 20 2009 5717 5738
    • (2009) International Journal of Production Research , vol.47 , Issue.20 , pp. 5717-5738
    • Ruiz, R.1    Allahverdi, A.2
  • 19
    • 0033733028 scopus 로고    scopus 로고
    • A heuristic for scheduling two-machine no-wait flow shops with anticipatory setups
    • J.B. Sidney, C.N. Potts, and C. Sriskandarajah A heuristic for scheduling two-machine no-wait flow shops with anticipatory setups Operations Research Letters 26 2000 165 173
    • (2000) Operations Research Letters , vol.26 , pp. 165-173
    • Sidney, J.B.1    Potts, C.N.2    Sriskandarajah, C.3
  • 20
    • 26444474118 scopus 로고    scopus 로고
    • A heuristic approach for tow-machine no-wait flowshop scheduling with due dates and class setups
    • X. Wang, and T.C.E. Cheng A heuristic approach for tow-machine no-wait flowshop scheduling with due dates and class setups Computers and Operations Research 33 2006 1326 1344
    • (2006) Computers and Operations Research , vol.33 , pp. 1326-1344
    • Wang, X.1    Cheng, T.C.E.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.