메뉴 건너뛰기




Volumn 7, Issue 6, 2011, Pages 2187-2194

A hybrid genetic algorithm for integrated project task and multi-skilled workforce scheduling

Author keywords

Genetic algorithm; Priority rules; Project scheduling; Skilled workforce; Staffing

Indexed keywords

COMPUTATIONAL EXPERIMENT; CPU TIME; FITNESS VALUES; HYBRID GENETIC ALGORITHMS; INTEGER-NONLINEAR PROGRAMMING; INTEGRATED PROJECT; MULTIPLE TASKS; PARALLEL SCHEDULES; PRIORITY RULES; PROJECT COST; PROJECT DURATION; PROJECT SCHEDULING; PROJECT SCHEDULING PROBLEM; RULE BASED; SKILLED WORKFORCE; SOLUTION SPACE; STAFFING; WORKFORCE SCHEDULING;

EID: 79959578665     PISSN: 15539105     EISSN: None     Source Type: Journal    
DOI: None     Document Type: Article
Times cited : (4)

References (7)
  • 1
    • 0031223441 scopus 로고    scopus 로고
    • Integrated project task and manpower scheduling
    • H. K. Alfares and J. E. Bailey. Integrated project task and manpower scheduling. IIE Transactions. 1997, 29(9): 711-717.
    • (1997) IIE Transactions , vol.29 , Issue.9 , pp. 711-717
    • Alfares, H.K.1    Bailey, J.E.2
  • 2
    • 33947217417 scopus 로고    scopus 로고
    • Software project management with GAs
    • E. Alba and J. F. Chicano. Software project management with GAs. Information Sciences. 2007, 177: 2380-2401.
    • (2007) Information Sciences , vol.177 , pp. 2380-2401
    • Alba, E.1    Chicano, J.F.2
  • 3
    • 77349123567 scopus 로고    scopus 로고
    • Scheduling and staffing multiple projects with a multi-skilled workforce
    • C. Heimerl and R. Kolisch. Scheduling and staffing multiple projects with a multi-skilled workforce. OR Spectrum. 2010, 32: 343-368.
    • (2010) OR Spectrum , vol.32 , pp. 343-368
    • Heimerl, C.1    Kolisch, R.2
  • 4
    • 0030231487 scopus 로고    scopus 로고
    • Efficient priority rules for the resource-constrained project scheduling problem
    • R. Kolisch. Efficient priority rules for the resource-constrained project scheduling problem. Journal of Operations Management, 1996, 14: 179-192.
    • (1996) Journal of Operations Management , vol.14 , pp. 179-192
    • Kolisch, R.1
  • 5
    • 0001096735 scopus 로고
    • Genetic algorithms and random keys for sequencing and optimization
    • J. C. Bean. Genetic algorithms and random keys for sequencing and optimization. ORSA Journal of Computing. 1994, 6(2): 154-160.
    • (1994) ORSA Journal of Computing , vol.6 , Issue.2 , pp. 154-160
    • Bean, J.C.1
  • 6
    • 67349221528 scopus 로고    scopus 로고
    • Design of a genetic algorithm for bi-objective unrelated parallel machines scheduling with sequence-dependent setup times and precedence constraints
    • R. Tavakkoli-Moghaddam, F. Taheri, M. Bazzazi, M. Izadi and F. Sassani. Design of a genetic algorithm for bi-objective unrelated parallel machines scheduling with sequence-dependent setup times and precedence constraints. Computers & Operations Research. 2009, 36: 3224-3230.
    • (2009) Computers & Operations Research , vol.36 , pp. 3224-3230
    • Tavakkoli-Moghaddam, R.1    Taheri, F.2    Bazzazi, M.3    Izadi, M.4    Sassani, F.5
  • 7
    • 0035521426 scopus 로고    scopus 로고
    • Generating experimental data for computational testing with machine scheduling applications
    • N. G. Hall and M. E. Posner. Generating experimental data for computational testing with machine scheduling applications. Operations Research. 2001, 49: 854-865.
    • (2001) Operations Research , vol.49 , pp. 854-865
    • Hall, N.G.1    Posner, M.E.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.