1
-
-
1642488326
-
Guidelines for tunnelling risk management: International Tunnelling Association, Working Group No. 2
-
S.D. Eskesen, P. Tengborg, J. Kampmann, T.H. Veicherts, "Guidelines for tunnelling risk management: International Tunnelling Association, Working Group No. 2". Tunnelling and Underground Space Technology 19 (2004), pp. 217-237.
-
(2004)
Tunnelling and Underground Space Technology
, vol.19
, pp. 217-237
-
-
Eskesen, S.D.1
Tengborg, P.2
Kampmann, T.H.3
Veicherts, J.4
-
2
-
-
43749125041
-
-
The International Tunnelling Insurance Group, January 2006. Available
-
The International Tunnelling Insurance Group, "A code of practice for risk management of tunnel works", January 2006. Available: http://www.munichre.com/publications/tunnel_code_of_practice_en.pdf
-
A code of practice for risk management of tunnel works
-
-
-
3
-
-
44349167263
-
Design and construction of a road tunnel in Korea including application of the Decision Aids for Tunneling, - A case study
-
S.Y. Min, T.K. Kim, J.S. Lee, H.H. Einstein, "Design and construction of a road tunnel in Korea including application of the Decision Aids for Tunneling, - A case study". Tunnelling and Underground Space Technology 23 (2008), pp. 91-102.
-
(2008)
Tunnelling and Underground Space Technology
, vol.23
, pp. 91-102
-
-
Min, S.Y.1
Kim, T.K.2
Lee, H.H.3
Einstein, J.S.4
-
5
-
-
34547820434
-
Simulation modeling techniques for underground infrastructure construction processes
-
J.Y. Ruwanpura, S.T. Ariaratnam, "Simulation modeling techniques for underground infrastructure construction processes". Tunnelling and Underground Space Technology 22 (2007), pp. 553-567.
-
(2007)
Tunnelling and Underground Space Technology
, vol.22
, pp. 553-567
-
-
Ruwanpura, J.Y.1
Ariaratnam, S.T.2
-
7
-
-
61449227351
-
Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBM
-
E.S. Hong et al., "Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBM". Tunnelling and Underground Space Technology 24 (2009), pp. 269-277.
-
(2009)
Tunnelling and Underground Space Technology
, vol.24
, pp. 269-277
-
-
Hong, E.S.1
-
8
-
-
3242656564
-
A methodology for assessing geotechnical hazards for TBM tunneling - illustrated by the Athens Metro, Greece
-
A.G. Benardos, D.C. Kaliampakos, "A methodology for assessing geotechnical hazards for TBM tunneling - illustrated by the Athens Metro, Greece". International Journal of Rock Mechanics & Mining Sciences 41 (2004), pp. 987-999.
-
(2004)
International Journal of Rock Mechanics & Mining Sciences
, vol.41
, pp. 987-999
-
-
Benardos, A.G.1
Kaliampakos, D.C.2
-
9
-
-
0030114753
-
Risk and decision analysis for large underground projects, as applied to the Stockholm ring road tunnels
-
R. Sturk, L. Olsson, J. Johansson, "Risk and decision analysis for large underground projects, as applied to the Stockholm ring road tunnels". Tunnelling and Underground Space Technology 11 (1996), pp. 157-164.
-
(1996)
Tunnelling and Underground Space Technology
, vol.11
, pp. 157-164
-
-
Sturk, R.1
Olsson, L.2
Johansson, J.3
-
12
-
-
79954494540
-
-
Formal Software Construction Ltd
-
OpenFTA Version 1.0 User Manual, Formal Software Construction Ltd., 2005.
-
(2005)
OpenFTA Version 1.0 User Manual
-
-
|