메뉴 건너뛰기




Volumn 21, Issue 8, 2010, Pages 760-773

The use of performance measurement as a basis for project control of offshore modification oil and gas projects

Author keywords

benchmarking; cost estimating; cost risk simulation; earned value; experience transfer; offshore modifications; oil and gas industry; performance measurement; project control

Indexed keywords

COST ESTIMATING; COST RISK SIMULATION; EARNED VALUE; EXPERIENCE TRANSFER; OFFSHORE MODIFICATIONS; OIL AND GAS INDUSTRY; PERFORMANCE MEASUREMENTS; PROJECT CONTROL;

EID: 78649497318     PISSN: 09537287     EISSN: 13665871     Source Type: Journal    
DOI: 10.1080/09537281003661385     Document Type: Article
Times cited : (12)

References (48)
  • 3
    • 78649514959 scopus 로고    scopus 로고
    • High attention Norwegian projects with substantial cost/time overrun: Lessons to be learned
    • Vienna, Austria
    • Andersen, E. S. and Rolstadås, A., 2002. High attention Norwegian projects with substantial cost/time overrun: lessons to be learned. PM-Days Research Conference. Vienna, Austria.
    • (2002) PM-days Research Conference
    • Andersen, E.S.1    Rolstadås, A.2
  • 4
    • 84948924858 scopus 로고
    • Risk management in cost engineering
    • Artto, K., 1988. Risk management in cost engineering. The Cost Engineer, 24(3), 16-18.
    • (1988) The Cost Engineer , vol.24 , Issue.3 , pp. 16-18
    • Artto, K.1
  • 5
    • 0041113413 scopus 로고
    • Accuracy in cost engineering estimates
    • Ashworth, A., 1988. Accuracy in cost engineering estimates. The Cost Engineer, 24(6), 12-15.
    • (1988) The Cost Engineer , vol.24 , Issue.6 , pp. 12-15
    • Ashworth, A.1
  • 8
    • 1542425689 scopus 로고    scopus 로고
    • The role of scientific method in quality management
    • Bisgaard, S., 2000. The role of scientific method in quality management. Total Quality Management, 11(3), 295-306.
    • (2000) Total Quality Management , vol.11 , Issue.3 , pp. 295-306
    • Bisgaard, S.1
  • 12
    • 78649502595 scopus 로고
    • Cost engineering in the North Sea oil industry: Failure or lack of success?
    • Drake, J. and Falconer, D., 1987. Cost engineering in the North Sea oil industry: failure or lack of success? The Cost Engineer, 25(3), 4-7.
    • (1987) The Cost Engineer , vol.25 , Issue.3 , pp. 4-7
    • Drake, J.1    Falconer, D.2
  • 16
    • 45849086928 scopus 로고    scopus 로고
    • Investigating the relationship between planning reliability and project performance
    • Gonzalez, V., Alarcon, L. F., and Mundacea, F., 2008. Investigating the relationship between planning reliability and project performance. Production Planning and Control, 19(5), 461-474.
    • (2008) Production Planning and Control , vol.19 , Issue.5 , pp. 461-474
    • Gonzalez, V.1    Alarcon, L.F.2    Mundacea, F.3
  • 19
  • 22
    • 78649494767 scopus 로고    scopus 로고
    • online. Decisioneering Inc. Available from:, Accessed 11 January 2006
    • Hulett, D. A., 2002/2003. Project risk analysis using crystal ball [online]. Decisioneering Inc. Available from: http://www.decisioneering.com [Accessed 11 January 2006].
    • (2002) Project Risk Analysis Using Crystal Ball
    • Hulett, D.A.1
  • 27
    • 0442277824 scopus 로고    scopus 로고
    • Process performance measurement system: A tool to support process-based organisations
    • Kueng, P., 2000. Process performance measurement system: a tool to support process-based organisations. Total Quality Management, 11(1), 67-85.
    • (2000) Total Quality Management , vol.11 , Issue.1 , pp. 67-85
    • Kueng, P.1
  • 31
    • 57349163213 scopus 로고    scopus 로고
    • Project agility assessment: An integrated decision analysis approach
    • Mafakheri, F., Nasiri, F., and Mousavi, M., 2008. Project agility assessment: an integrated decision analysis approach. Production Planning and Control, 19(6), 567-576.
    • (2008) Production Planning and Control , vol.19 , Issue.6 , pp. 567-576
    • Mafakheri, F.1    Nasiri, F.2    Mousavi, M.3
  • 35
    • 0442310612 scopus 로고    scopus 로고
    • Quality improvement in the construction industry: Three systematic approaches
    • Ortega, I. and Bisgaard, S., 2000. Quality improvement in the construction industry: three systematic approaches. Total Quality Management, 11 (4-6), 383-392.
    • (2000) Total Quality Management , vol.11 , Issue.4-6 , pp. 383-392
    • Ortega, I.1    Bisgaard, S.2
  • 37
    • 58049139009 scopus 로고    scopus 로고
    • Project Management Institute Standards Committee, 3rd ed. Newtown Square, PA: PMI
    • Project Management Institute Standards Committee, 2004. A guide to the project management body of knowledge. 3rd ed. Newtown Square, PA: PMI.
    • (2004) A Guide to the Project Management Body of Knowledge
  • 38
    • 78649502195 scopus 로고    scopus 로고
    • Form operations management to project management
    • Renesse, The Netherlands
    • Rolstadås, A., 2002. Form operations management to project management. IRNOP Conference, Renesse, The Netherlands.
    • (2002) IRNOP Conference
    • Rolstadås, A.1
  • 40
    • 78649618384 scopus 로고    scopus 로고
    • From protective to offensive project management
    • Malta
    • Rolstadås, A. and Johansen, A., 2008. From protective to offensive project management. PMI EMEA Congress, Malta.
    • (2008) PMI EMEA Congress
    • Rolstadås, A.1    Johansen, A.2
  • 41
    • 78649526516 scopus 로고    scopus 로고
    • Operational excellence won't do it: Towards a new project management maturity mode
    • Project Management Institute
    • Shenhar, A. J. and Stefanovic, J., 2006. Operational excellence won't do it: towards a new project management maturity mode. PMI Research Conference, Project Management Institute.
    • (2006) PMI Research Conference
    • Shenhar, A.J.1    Stefanovic, J.2
  • 44
    • 78649494942 scopus 로고    scopus 로고
    • Skjønn og skivebom: Hvordan vi bedømmer usikkerhet
    • Oslo
    • Teigen, K. H., 2006. Skjønn og skivebom: hvordan vi bedømmer usikkerhet. Seminar NFP, Oslo.
    • (2006) Seminar NFP
    • Teigen, K.H.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.