메뉴 건너뛰기




Volumn 35, Issue 10-11, 2004, Pages 715-724

Project time-cost analysis under generalised precedence relations

Author keywords

Linear programming; Optimisation; Project crashing; Project planning; Project structure; Time cost trade off

Indexed keywords

CONSTRAINT THEORY; COSTS; GENETIC ALGORITHMS; INTEGER PROGRAMMING; LINEAR PROGRAMMING; OPTIMIZATION; PLANNING; PROBLEM SOLVING; PROJECT MANAGEMENT;

EID: 7544238250     PISSN: 09659978     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.advengsoft.2004.03.017     Document Type: Article
Times cited : (54)

References (21)
  • 1
    • 0019067033 scopus 로고
    • Linear programming solution to network compression
    • Perera S. Linear programming solution to network compression. ASCE J Constr Div. 106:1980;315-327.
    • (1980) ASCE J Constr Div , vol.106 , pp. 315-327
    • Perera, S.1
  • 2
    • 34250094949 scopus 로고
    • Scheduling project networks with resource constraints and time windows
    • Bartusch M., Möhring R.H., Radermacher F.J. Scheduling project networks with resource constraints and time windows. Ann Oper Res. 16:1988;201-240.
    • (1988) Ann Oper Res , vol.16 , pp. 201-240
    • Bartusch, M.1    Möhring, R.H.2    Radermacher, F.J.3
  • 3
    • 0000480311 scopus 로고
    • An algorithm for a general class of precedence and resource constrained scheduling problems
    • Amsterdam
    • Patterson JH, Slowinski R, Talbot FB, Weglarz, J. An algorithm for a general class of precedence and resource constrained scheduling problems. Advances in project scheduling. Amsterdam; 1989. p. 03-28.
    • (1989) Advances in Project Scheduling , pp. 03-28
    • Patterson, J.H.1    Slowinski, R.2    Talbot, F.B.3    Weglarz, J.4
  • 5
    • 0029470313 scopus 로고
    • Construction time-cost trade-off analysis using LP/IP hybrid method
    • Liu L., Burns S.A., Feng C.W. Construction time-cost trade-off analysis using LP/IP hybrid method. ASCE J Constr Eng Manage. 121:(4):1995;446-454.
    • (1995) ASCE J Constr Eng Manage , vol.121 , Issue.4 , pp. 446-454
    • Liu, L.1    Burns, S.A.2    Feng, C.W.3
  • 6
    • 7544221549 scopus 로고
    • Decomposition of project networks
    • Parikh S.C., Jewell W.S. Decomposition of project networks. Manage Sci. 11:1965;444-459.
    • (1965) Manage Sci , vol.11 , pp. 444-459
    • Parikh, S.C.1    Jewell, W.S.2
  • 7
    • 0014928334 scopus 로고
    • Network reduction and solution
    • Crowston W.B., Decision C.P.M. Network reduction and solution. Oper Res Quart. 21:(4):1970;435-452.
    • (1970) Oper Res Quart , vol.21 , Issue.4 , pp. 435-452
    • Crowston, W.B.1    Decision, C.P.M.2
  • 8
    • 0016566179 scopus 로고
    • A dynamic programming solution to cost-time trade-off for CPM
    • Robinson D.R. A dynamic programming solution to cost-time trade-off for CPM. Manage Sci. 22:(2):1975;158-166.
    • (1975) Manage Sci , vol.22 , Issue.2 , pp. 158-166
    • Robinson, D.R.1
  • 9
    • 0017506038 scopus 로고
    • Cost-time model for large CPM project networks
    • Panagiotakopoulos D. Cost-time model for large CPM project networks. ASCE J Constr Div. 103:1977;201-211.
    • (1977) ASCE J Constr Div , vol.103 , pp. 201-211
    • Panagiotakopoulos, D.1
  • 10
    • 0029632618 scopus 로고
    • The discrete time-cost trade-off problem revisited
    • De P., Dunne E.J., Ghosh J.B., Wells C.E. The discrete time-cost trade-off problem revisited. Eur J Oper Res. 81:1995;225-238.
    • (1995) Eur J Oper Res , vol.81 , pp. 225-238
    • De, P.1    Dunne, E.J.2    Ghosh, J.B.3    Wells, C.E.4
  • 12
    • 0031185451 scopus 로고    scopus 로고
    • Using genetic algorithms to solve construction time-cost trade-off problems
    • Feng C.W., Liu L., Burns S.A. Using genetic algorithms to solve construction time-cost trade-off problems. ASCE J Comput Civil Eng. 11:(3):1997;184-189.
    • (1997) ASCE J Comput Civil Eng , vol.11 , Issue.3 , pp. 184-189
    • Feng, C.W.1    Liu, L.2    Burns, S.A.3
  • 13
    • 0032638332 scopus 로고    scopus 로고
    • Using machine learning and genetic algorithms to solve time-cost trade-off problems (MLGAS)
    • Li H., Cao J.N., Love P.E.D. Using machine learning and genetic algorithms to solve time-cost trade-off problems (MLGAS). ASCE J Constr Eng Manage. 125:(5):1999;347-353.
    • (1999) ASCE J Constr Eng Manage , vol.125 , Issue.5 , pp. 347-353
    • Li, H.1    Cao, J.N.2    Love, P.E.D.3
  • 14
    • 0033312040 scopus 로고    scopus 로고
    • GA-based multicriteria optimal model for construction scheduling
    • Leu S.S., Yang C.H. GA-based multicriteria optimal model for construction scheduling. J Constr Eng Manage. 125:(6):1999;420-427.
    • (1999) J Constr Eng Manage , vol.125 , Issue.6 , pp. 420-427
    • Leu, S.S.1    Yang, C.H.2
  • 15
    • 0002395681 scopus 로고
    • Chance-constrained programming
    • Charnes A., Cooper W. Chance-constrained programming. Manage Sci. 6:1959;73-79.
    • (1959) Manage Sci , vol.6 , pp. 73-79
    • Charnes, A.1    Cooper, W.2
  • 16
    • 0021609393 scopus 로고
    • Optimal probabilistic compression of PERT networks
    • Coskunoglu O. Optimal probabilistic compression of PERT networks. ASCE J Constr Eng Manage. 110:(4):1984;437-446.
    • (1984) ASCE J Constr Eng Manage , vol.110 , Issue.4 , pp. 437-446
    • Coskunoglu, O.1
  • 17
    • 0022099676 scopus 로고
    • Bounding the project completion time distribution in PERT networks
    • Dodin B.N. Bounding the project completion time distribution in PERT networks. Oper Res. 33:1985;862-881.
    • (1985) Oper Res , vol.33 , pp. 862-881
    • Dodin, B.N.1
  • 18
    • 0022745027 scopus 로고
    • Stochastic bounds on distributions of optimal value functions with applications to PERT, network flows and reliability
    • Weiss G. Stochastic bounds on distributions of optimal value functions with applications to PERT, network flows and reliability. Oper Res. 34:(4):1986;595-605.
    • (1986) Oper Res , vol.34 , Issue.4 , pp. 595-605
    • Weiss, G.1
  • 19
    • 0034172005 scopus 로고    scopus 로고
    • Stochastic construction time-cost trade-off analysis
    • Feng C.W., Liu L., Burns S.A. Stochastic construction time-cost trade-off analysis. ASCE J Comput Civil Eng. 14:(2):2000;117-126.
    • (2000) ASCE J Comput Civil Eng , vol.14 , Issue.2 , pp. 117-126
    • Feng, C.W.1    Liu, L.2    Burns, S.A.3
  • 20
    • 0001215033 scopus 로고
    • The analysis of activity networks under generalized precedence relations
    • Elmaghraby S.E., Kamburowski J. The analysis of activity networks under generalized precedence relations. Manage Sci. 38:1992;1245-1263.
    • (1992) Manage Sci , vol.38 , pp. 1245-1263
    • Elmaghraby, S.E.1    Kamburowski, J.2
  • 21
    • 0000647152 scopus 로고
    • Heuristics for the minimum project duration problem with minimal and maximal time lags under fixed resource constraints
    • Neumann K., Zhan J. Heuristics for the minimum project duration problem with minimal and maximal time lags under fixed resource constraints. J Intell Manuf. 6:1995;145-154.
    • (1995) J Intell Manuf , vol.6 , pp. 145-154
    • Neumann, K.1    Zhan, J.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.