Volumn 6, Issue 2, 2009, Pages 267-281

Development and application of a simulation model for throughput improvement in the melting shop of a steel plant

Author keywords

Bottleneck; Delay; Simulation; Steel plant; Throughput

Indexed keywords


EID: 67649419561     PISSN: 17457645     EISSN: 17457653     Source Type: Journal    
DOI: 10.1504/IJOR.2009.026538     Document Type: Article
Times cited : (6)

References (14)
  • 1
  • 2
    • 0027802003 scopus 로고
    • Simulation approach to assembly line modification: A case study
    • Chan, F.T.S. and Smith, A.M. (1993) 'Simulation approach to assembly line modification: A case study', Journal of Manufacturing System, Vol. 12, No. 3, pp.239-246.
    • (1993) Journal of Manufacturing System , vol.12 , Issue.3 , pp. 239-246
    • Chan, F.T.S.1    Smith, A.M.2
  • 3
    • 33846357486 scopus 로고    scopus 로고
    • Dispatching in flow shops with bottleneck machine
    • Chandrasekharan, R. and Knut, A. (2007) 'Dispatching in flow shops with bottleneck machine', Computers and Industrial Engineering, Vol. 52, No. 1, pp.89-106.
    • (2007) Computers and Industrial Engineering , vol.52 , Issue.1 , pp. 89-106
    • Chandrasekharan, R.1    Knut, A.2
  • 4
    • 0344193873 scopus 로고
    • Impact of re-sequencing on parallel assembly systems
    • Kumar, A., Haresh, G. and Sunder, K. (1995) 'Impact of re-sequencing on parallel assembly systems', Journal of Manufacturing System, Vol. 14, No. 2, pp.209-218.
    • (1995) Journal of Manufacturing System , vol.14 , Issue.2 , pp. 209-218
    • Kumar, A.1    Haresh, G.2    Sunder, K.3
  • 7
    • 0027579287 scopus 로고
    • Scheduling of maintenance activities in a sugar industry using simulation
    • Mathew, J. and Rajendran, C. (1993.) 'Scheduling of maintenance activities in a sugar industry using simulation', Computers in Industry, Vol. 21, pp.331-334.
    • (1993) Computers in Industry , vol.21 , pp. 331-334
    • Mathew, J.1    Rajendran, C.2
  • 9
    • 0032254839 scopus 로고    scopus 로고
    • Simulation and analysis of the Mercedes-Benz all activity vehicle (AAV) production facility
    • Park, Y.H., Matson, J.E. and Miller, D.M. (1998) 'Simulation and analysis of the Mercedes-Benz all activity vehicle (AAV) production facility', Proceedings of the 1998 Winter Simulation Conference, Vol. 2, pp.921-926.
    • (1998) Proceedings of the 1998 Winter Simulation Conference , vol.2 , pp. 921-926
    • Park, Y.H.1    Matson, J.E.2    Miller, D.M.3
  • 10
    • 33947719650 scopus 로고    scopus 로고
    • Simulation of automated guided vehicle (AGV) systems based on just-in-time (JIT) philosophy in a job-shop environment
    • Saadettin, E.K. and Omer, F.B. (2007) 'Simulation of automated guided vehicle (AGV) systems based on just-in-time (JIT) philosophy in a job-shop environment', Simulation Modelling Practice and Theory, Vol. 15, No. 3, pp.272-284.
    • (2007) Simulation Modelling Practice and Theory , vol.15 , Issue.3 , pp. 272-284
    • Saadettin, E.K.1    Omer, F.B.2
  • 11
    • 0042722284 scopus 로고    scopus 로고
    • A decision analysis model for comparing well completion techniques
    • Stewart, B.R. and Lee, J. (1997) 'A decision analysis model for comparing well completion techniques', International Journal of Production and Economics, Vol. 49, No. 3, pp.189-204.
    • (1997) International Journal of Production and Economics , vol.49 , Issue.3 , pp. 189-204
    • Stewart, B.R.1    Lee, J.2
  • 12
    • 33947593937 scopus 로고    scopus 로고
    • Simulation modeling and analysis of tool sharing and part scheduling decisions in single-stage multi machine flexible manufacturing systems
    • Suresh, K. and Sridharan, R. (2007) 'Simulation modeling and analysis of tool sharing and part scheduling decisions in single-stage multi machine flexible manufacturing systems', Robotics and Computer-Integrated Manufacturing, Vol. 23, No. 4, pp.361-370.
    • (2007) Robotics and Computer-Integrated Manufacturing , vol.23 , Issue.4 , pp. 361-370
    • Suresh, K.1    Sridharan, R.2
  • 13
    • 0030151648 scopus 로고    scopus 로고
    • Simulation-based scheduling: Meeting the semiconductor wafer fabrication challenge
    • Thompson, M. (1996) 'Simulation-based scheduling: Meeting the semiconductor wafer fabrication challenge', IIE Solutions, Vol. 28, No. 5, pp.30-34.
    • (1996) IIE Solutions , vol.28 , Issue.5 , pp. 30-34
    • Thompson, M.1
  • 14
    • 0030263692 scopus 로고    scopus 로고
    • Evaluating operations to increase production of a copper smelter aisle: A simulation approach
    • Welgama, P.S., Mills, R.G.J., Struthers, A. and Trucker, D. (1996) 'Evaluating operations to increase production of a copper smelter aisle: a simulation approach', Simulation, Vol. 67, No. 4, pp.247-267.
    • (1996) Simulation , vol.67 , Issue.4 , pp. 247-267
    • Welgama, P.S.1    Mills, R.G.J.2    Struthers, A.3    Trucker, D.4


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.