Volumn 36, Issue 2 PART 2, 2009, Pages 2947-2960

Web-based CBR system applied to early cost budgeting for pavement maintenance project

Author keywords

Budgeting; Case based reasoning; Cost estimate; Pavement maintenance operations; Web technology

Indexed keywords

BUDGET CONTROL; CASE BASED REASONING; COST ESTIMATING; DECISION MAKING; DEVELOPING COUNTRIES; HIGHWAY PLANNING; INFORMATION MANAGEMENT; MAINTENANCE; PAVEMENTS; WEBSITES;

EID: 56349153507     PISSN: 09574174     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.eswa.2008.01.025     Document Type: Article
Times cited : (99)

References (53)
  • 2
    • 0032206533 scopus 로고    scopus 로고
    • The omnipresence of case-based reasoning in science and application
    • Aha D.W. The omnipresence of case-based reasoning in science and application. Knowledge-Based Systems 11 5-6 (1998) 261-273
    • (1998) Knowledge-Based Systems , vol.11 , Issue.5-6 , pp. 261-273
    • Aha, D.W.1
  • 3
    • 37849184985 scopus 로고    scopus 로고
    • A case-based reasoning system with the two-dimensional reduction technique for customer classification
    • Ahn H., Kim K.-J., and Han I. A case-based reasoning system with the two-dimensional reduction technique for customer classification. Expert Systems with Applications 32 4 (2007) 1011-1019
    • (2007) Expert Systems with Applications , vol.32 , Issue.4 , pp. 1011-1019
    • Ahn, H.1    Kim, K.-J.2    Han, I.3
  • 4
    • 0031705846 scopus 로고    scopus 로고
    • Factors affecting contractors' risk of cost overburden
    • Akinci B., and Fischer M. Factors affecting contractors' risk of cost overburden. Journal of Management in Engineering 14 1 (1998) 67-76
    • (1998) Journal of Management in Engineering , vol.14 , Issue.1 , pp. 67-76
    • Akinci, B.1    Fischer, M.2
  • 5
    • 2242459831 scopus 로고    scopus 로고
    • Analysis of factors influencing project cost estimating practice
    • Akintoye A. Analysis of factors influencing project cost estimating practice. Construction Management and Economics 18 1 (2000) 77-89
    • (2000) Construction Management and Economics , vol.18 , Issue.1 , pp. 77-89
    • Akintoye, A.1
  • 6
    • 0024181879 scopus 로고
    • ERASME, an expert system for pavement maintenance
    • Allez, et al. ERASME, an expert system for pavement maintenance. Transportation Research Record 1205 (1988) 1-5
    • (1988) Transportation Research Record , vol.1205 , pp. 1-5
    • Allez1
  • 7
    • 0033100590 scopus 로고    scopus 로고
    • Preliminary cost estimation of highway construction using neural networks
    • Al-Tabtabai H., Alex A.P., and Tantash M. Preliminary cost estimation of highway construction using neural networks. Cost Engineering 41 3 (1999) 19-24
    • (1999) Cost Engineering , vol.41 , Issue.3 , pp. 19-24
    • Al-Tabtabai, H.1    Alex, A.P.2    Tantash, M.3
  • 8
    • 33847026525 scopus 로고    scopus 로고
    • A case-based reasoning cost estimating model using experience by analytic hierarchy process
    • An S.-H., Kim G.-H., and Kang K.-I. A case-based reasoning cost estimating model using experience by analytic hierarchy process. Building and Environment 42 7 (2007) 2573-2579
    • (2007) Building and Environment , vol.42 , Issue.7 , pp. 2573-2579
    • An, S.-H.1    Kim, G.-H.2    Kang, K.-I.3
  • 9
    • 33746873723 scopus 로고    scopus 로고
    • Legal case-based reasoning as practical reasoning
    • Atkinson K., and Bench-Capon T. Legal case-based reasoning as practical reasoning. Artificial Intelligence and Law 13 1 (2005) 93-131
    • (2005) Artificial Intelligence and Law , vol.13 , Issue.1 , pp. 93-131
    • Atkinson, K.1    Bench-Capon, T.2
  • 11
    • 33750447991 scopus 로고    scopus 로고
    • A hybrid system by evolving case-based reasoning with genetic algorithm in wholesaler's returning book forecasting
    • Chang P.-C., Lai C.-Y., and Lai K.R. A hybrid system by evolving case-based reasoning with genetic algorithm in wholesaler's returning book forecasting. Decision Support Systems 42 3 (2006) 1715-1729
    • (2006) Decision Support Systems , vol.42 , Issue.3 , pp. 1715-1729
    • Chang, P.-C.1    Lai, C.-Y.2    Lai, K.R.3
  • 14
    • 33749583888 scopus 로고    scopus 로고
    • Quantity-based approach to preliminary cost estimates for highway projects
    • Chou J.-S., et al. Quantity-based approach to preliminary cost estimates for highway projects. Transportation Research Record 1946 (2006) 22-30
    • (2006) Transportation Research Record , vol.1946 , pp. 22-30
    • Chou, J.-S.1
  • 15
    • 27644590365 scopus 로고    scopus 로고
    • Chou, J.-S., et al. (2005). Preliminary cost estimates using probabilistic simulation for highway bridge replacement projects. In American Society of Civil Engineers. 2005: Construction Research Congress 2005: Broadening Perspectives - Proceedings of the Congress (pp. 939-948).
    • Chou, J.-S., et al. (2005). Preliminary cost estimates using probabilistic simulation for highway bridge replacement projects. In American Society of Civil Engineers. 2005: Construction Research Congress 2005: Broadening Perspectives - Proceedings of the Congress (pp. 939-948).
  • 18
    • 33748765247 scopus 로고    scopus 로고
    • Determining attribute weights in a CBR model for early cost prediction of structural systems
    • Dogan S.Z., Arditi D., and Gunaydin H.M. Determining attribute weights in a CBR model for early cost prediction of structural systems. Journal of Construction Engineering and Management 132 10 (2006) 1092-1098
    • (2006) Journal of Construction Engineering and Management , vol.132 , Issue.10 , pp. 1092-1098
    • Dogan, S.Z.1    Arditi, D.2    Gunaydin, H.M.3
  • 19
    • 0033354365 scopus 로고    scopus 로고
    • Cost estimation during design step: Parametric method versus case based reasoning method
    • Duverlie P., and Castelain J.M. Cost estimation during design step: Parametric method versus case based reasoning method. International Journal of Advanced Manufacturing Technology 15 12 (1999) 895-906
    • (1999) International Journal of Advanced Manufacturing Technology , vol.15 , Issue.12 , pp. 895-906
    • Duverlie, P.1    Castelain, J.M.2
  • 20
    • 0036744325 scopus 로고    scopus 로고
    • Data modelling and the application of a neural network approach to the prediction of total construction costs
    • Emsley M.W., et al. Data modelling and the application of a neural network approach to the prediction of total construction costs. Construction Management and Economics 20 6 (2002) 465
    • (2002) Construction Management and Economics , vol.20 , Issue.6 , pp. 465
    • Emsley, M.W.1
  • 22
    • 33749667379 scopus 로고    scopus 로고
    • Research planning approach using knowledge map integrated with case-based reasoning
    • Gang K.W. Research planning approach using knowledge map integrated with case-based reasoning. IEEE International Engineering Management Conference II (2005) 897-901
    • (2005) IEEE International Engineering Management Conference , vol.II , pp. 897-901
    • Gang, K.W.1
  • 23
    • 56349159881 scopus 로고    scopus 로고
    • Haas, C., & Shen, (1987). PRESERVER, A knowledge based pavement maintenance consulting programme. In 2nd North American conference on managing pavement (pp. 2.327-2.338).
    • Haas, C., & Shen, (1987). PRESERVER, A knowledge based pavement maintenance consulting programme. In 2nd North American conference on managing pavement (pp. 2.327-2.338).
  • 24
    • 24144456508 scopus 로고    scopus 로고
    • Case-based tutoring systems for procedural problem solving on the www
    • Han S.-G., Lee S.-G., and Jo G.-S. Case-based tutoring systems for procedural problem solving on the www. Expert Systems with Applications 29 3 (2005) 573-582
    • (2005) Expert Systems with Applications , vol.29 , Issue.3 , pp. 573-582
    • Han, S.-G.1    Lee, S.-G.2    Jo, G.-S.3
  • 25
    • 0036353695 scopus 로고    scopus 로고
    • Using models in parametric estimating for transportation projects
    • Harbuck R.H. Using models in parametric estimating for transportation projects. AACE International Transactions EST.05 ES51 (2002) EST.05.1-EST.05.09
    • (2002) AACE International Transactions , vol.EST.05 , Issue.ES51
    • Harbuck, R.H.1
  • 26
    • 0000794253 scopus 로고    scopus 로고
    • Neural network model for parametric cost estimation of highway projects
    • Hegazy T., and Ayed A. Neural network model for parametric cost estimation of highway projects. Journal of Construction Engineering and Management 124 3 (1998) 210-219
    • (1998) Journal of Construction Engineering and Management , vol.124 , Issue.3 , pp. 210-219
    • Hegazy, T.1    Ayed, A.2
  • 27
    • 56349169657 scopus 로고    scopus 로고
    • Hemaya, P. B. (1992). Knowledge-based advisory system for flexible pavement routine maintenance, M.Eng. Thesis. Canada: Memorial University of Newfoundland.
    • Hemaya, P. B. (1992). Knowledge-based advisory system for flexible pavement routine maintenance, M.Eng. Thesis. Canada: Memorial University of Newfoundland.
  • 28
    • 33750992805 scopus 로고    scopus 로고
    • Integrating data mining with case-based reasoning for chronic diseases prognosis and diagnosis
    • Huang M.-J., Chen M.-Y., and Lee S.-C. Integrating data mining with case-based reasoning for chronic diseases prognosis and diagnosis. Expert Systems with Applications 32 3 (2007) 856-867
    • (2007) Expert Systems with Applications , vol.32 , Issue.3 , pp. 856-867
    • Huang, M.-J.1    Chen, M.-Y.2    Lee, S.-C.3
  • 29
    • 2642564315 scopus 로고    scopus 로고
    • Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoning
    • Kim G.-H., An S.-H., and Kang K.-I. Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoning. Building and Environment 39 10 (2004) 1235-1242
    • (2004) Building and Environment , vol.39 , Issue.10 , pp. 1235-1242
    • Kim, G.-H.1    An, S.-H.2    Kang, K.-I.3
  • 30
    • 85164392958 scopus 로고
    • A study of cross-validation and bootstrap for accuracy estimation and model selection
    • Morgan Kaufman, San Francisco, CA
    • Kohavi R. A study of cross-validation and bootstrap for accuracy estimation and model selection. The 14th international joint conference on artificial intelligence (IJCAI) (1995), Morgan Kaufman, San Francisco, CA 1137-1145
    • (1995) The 14th international joint conference on artificial intelligence (IJCAI) , pp. 1137-1145
    • Kohavi, R.1
  • 31
    • 0003602869 scopus 로고
    • Morgan Kaufmann Publishers Inc., San Mateo, California
    • Kolodner J.L. Case-based reasoning (1993), Morgan Kaufmann Publishers Inc., San Mateo, California
    • (1993) Case-based reasoning
    • Kolodner, J.L.1
  • 32
    • 0042303841 scopus 로고    scopus 로고
    • Estimating safety benefits of road improvements: Case based approach
    • Lin F., Sayed T., and Deleur P. Estimating safety benefits of road improvements: Case based approach. Journal of Transportation Engineering 129 4 (2003) 385-391
    • (2003) Journal of Transportation Engineering , vol.129 , Issue.4 , pp. 385-391
    • Lin, F.1    Sayed, T.2    Deleur, P.3
  • 36
    • 56349131565 scopus 로고    scopus 로고
    • MOTC. , 2006 [cited Nov. 2006]; Available from .
    • MOTC. , 2006 [cited Nov. 2006]; Available from .
  • 39
    • 0031344631 scopus 로고    scopus 로고
    • Developing an integrated framework for feature-based early manufacturing cost estimation
    • Ou-Yang C., and Lin T.S. Developing an integrated framework for feature-based early manufacturing cost estimation. International Journal of Advanced Manufacturing Technology 13 9 (1997) 618-629
    • (1997) International Journal of Advanced Manufacturing Technology , vol.13 , Issue.9 , pp. 618-629
    • Ou-Yang, C.1    Lin, T.S.2
  • 44
    • 33746881784 scopus 로고    scopus 로고
    • Case-based reasoning investigation of therapy inefficacy
    • Schmidt R., and Vorobieva O. Case-based reasoning investigation of therapy inefficacy. Knowledge-Based Systems 19 5 (2006) 333-340
    • (2006) Knowledge-Based Systems , vol.19 , Issue.5 , pp. 333-340
    • Schmidt, R.1    Vorobieva, O.2
  • 45
    • 0028668331 scopus 로고
    • Model to estimate highway earthwork cost in Nepal
    • Sthapit N., and Mori H. Model to estimate highway earthwork cost in Nepal. Journal of Transportation Engineering 120 3 (1994) 498-504
    • (1994) Journal of Transportation Engineering , vol.120 , Issue.3 , pp. 498-504
    • Sthapit, N.1    Mori, H.2
  • 48
    • 33744552905 scopus 로고    scopus 로고
    • Web-based CBR (case-based reasoning) as a tool with the application to tooling selection
    • Toussaint J., and Cheng K. Web-based CBR (case-based reasoning) as a tool with the application to tooling selection. International Journal of Advanced Manufacturing Technology 29 1-2 (2006) 24-34
    • (2006) International Journal of Advanced Manufacturing Technology , vol.29 , Issue.1-2 , pp. 24-34
    • Toussaint, J.1    Cheng, K.2
  • 51
    • 0032073403 scopus 로고    scopus 로고
    • Applying case-based reasoning technique to retaining wall selection
    • Yau N.-J., and Yang J.-B. Applying case-based reasoning technique to retaining wall selection. Automation in Construction 7 4 (1998) 271-283
    • (1998) Automation in Construction , vol.7 , Issue.4 , pp. 271-283
    • Yau, N.-J.1    Yang, J.-B.2
  • 52
    • 33645120103 scopus 로고    scopus 로고
    • PIREM: A new model for conceptual cost estimation
    • Yu W.-D. PIREM: A new model for conceptual cost estimation. Construction Management and Economics 24 3 (2006) 259-270
    • (2006) Construction Management and Economics , vol.24 , Issue.3 , pp. 259-270
    • Yu, W.-D.1
  • 53
    • 26444548002 scopus 로고    scopus 로고
    • Hybridization of CBR and numeric soft computing techniques for mining of scarce construction databases
    • Yu W.-D., and Liu Y.-C. Hybridization of CBR and numeric soft computing techniques for mining of scarce construction databases. Automation in Construction 15 1 (2006) 33-46
    • (2006) Automation in Construction , vol.15 , Issue.1 , pp. 33-46
    • Yu, W.-D.1    Liu, Y.-C.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.