메뉴 건너뛰기




Volumn 2, Issue , 2006, Pages 483-488

Selection of appropriate schedule delay analysis method: Analytical hierarchy process (AHP)

Author keywords

[No Author keywords available]

Indexed keywords

ANALYTIC HIERARCHY PROCESS; CIVIL ENGINEERING; COMPUTER NETWORKS; CONSTRUCTION INDUSTRY; COST ACCOUNTING; INDUSTRIAL MANAGEMENT; PRODUCT LIABILITY; TUNNELING (EXCAVATION);

EID: 50849093556     PISSN: None     EISSN: None     Source Type: Conference Proceeding    
DOI: 10.1109/PICMET.2006.296646     Document Type: Conference Paper
Times cited : (15)

References (19)
  • 2
    • 84948506156 scopus 로고    scopus 로고
    • Alkass., S.,Mazerolle, M.,Tribaldos., and Harris, F. Computer aided construction delay analysis and claim preparation, Journal of Construction Management and Economics, 13, pp.335-352, 1995.
    • Alkass., S.,Mazerolle, M.,Tribaldos., and Harris, F. "Computer aided construction delay analysis and claim preparation," Journal of Construction Management and Economics, Vol.13, pp.335-352, 1995.
  • 3
    • 50849093132 scopus 로고    scopus 로고
    • Selecting a delay analysis method in resolving construction claims
    • Article in Press, September
    • Arditi David and Thanat Pattanakitchamroon. "Selecting a delay analysis method in resolving construction claims". International Journal Of Project Management, Article in Press, September 2005.
    • (2005) International Journal Of Project Management
    • David, A.1    Pattanakitchamroon, T.2
  • 4
    • 9144238349 scopus 로고    scopus 로고
    • Analytic Hierarchy Process Analyzes Risk of Operating Cross-Country Petroleum Pipelines in India
    • Dey, P. K, "Analytic Hierarchy Process Analyzes Risk of Operating Cross-Country Petroleum Pipelines in India," ASCE, Natural Hazards Review, Vol. 4, pp. 213-221, 2003
    • (2003) ASCE, Natural Hazards Review , vol.4 , pp. 213-221
    • Dey, P.K.1
  • 5
    • 0026854294 scopus 로고
    • Group decision support with analytic hierarchy process
    • Dyer R.F., and E.H Forman., "Group decision support with analytic hierarchy process," Decision support system, Vol. 8 pp. 99-124,1992.
    • (1992) Decision support system , vol.8 , pp. 99-124
    • Dyer, R.F.1    Forman, E.H.2
  • 6
    • 50849115411 scopus 로고    scopus 로고
    • Fruchtman E., Delay analysis-eliminating the smoke and mirrors, Trans AACE Int, CDR. 6.1-CDR.6.4, 2000.
    • Fruchtman E., "Delay analysis-eliminating the smoke and mirrors," Trans AACE Int, CDR. 6.1-CDR.6.4, 2000.
  • 7
    • 0028756101 scopus 로고    scopus 로고
    • Jentzen GH, P Spittler., Ponce de Leon G. Responsibility for delay after the expiration of the contract time. Trans AACE Int, DCL.9.1.-DCL.9.7, 1994.
    • Jentzen GH, P Spittler., Ponce de Leon G. "Responsibility for delay after the expiration of the contract time". Trans AACE Int, DCL.9.1.-DCL.9.7, 1994.
  • 8
    • 50849130490 scopus 로고    scopus 로고
    • McCulloough R. B. CPM schedules in construction claims from the Contractor's prespective. Trans AACE Int,CDR.2.1.-CDR.2.4, (1999).
    • McCulloough R. B. "CPM schedules in construction claims from the Contractor's prespective". Trans AACE Int,CDR.2.1.-CDR.2.4, (1999).
  • 9
    • 50849133152 scopus 로고    scopus 로고
    • Richard J.Long, P.E., Andrew Avalon, P.E., Ronald J. Rider, MBA and Anamaria Popescu, Ph.D. 2005. Long International's Schedule and Delay Analysis Methodologies, Retrived 1/18/06 www.long-intl.com/schedule.pdf
    • Richard J.Long, P.E., Andrew Avalon, P.E., Ronald J. Rider, MBA and Anamaria Popescu, Ph.D. 2005. "Long International's Schedule and Delay Analysis Methodologies, "Retrived 1/18/06 www.long-intl.com/schedule.pdf
  • 13
    • 0020164915 scopus 로고
    • Priority setting in complex problems
    • August
    • Saaty, T.L, "Priority setting in complex problems". IEEE Trans. Eng. Manage., Vol. 30, pp. 140-155, August 1983.
    • (1983) IEEE Trans. Eng. Manage , vol.30 , pp. 140-155
    • Saaty, T.L.1
  • 16
    • 29244433489 scopus 로고    scopus 로고
    • SCL-Society of Construction Law, Available from
    • SCL-Society of Construction Law. "Delay and Disruption protocol;" 2002. Available from: www.eotprotocol.com
    • (2002) Delay and Disruption protocol
  • 17
    • 44949288762 scopus 로고
    • An overview of the analytic hierarchy process and its applications,
    • Vargas, L.G.., "An overview of the analytic hierarchy process and its applications,". European Journal of Operation and Res, Vol. 48, pp. 2-8. 1990.
    • (1990) European Journal of Operation and Res , vol.48 , pp. 2-8
    • Vargas, L.G.1
  • 19
    • 0242411323 scopus 로고    scopus 로고
    • But-for schedule-analysis and defense
    • Zack Jr J., "But-for schedule-analysis and defense," Cost Engineering AACE, Vol 43), pp. 13-17, 2001.
    • (2001) Cost Engineering AACE , vol.43 , pp. 13-17
    • Zack Jr, J.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.