Volumn 30, Issue 4, 2008, Pages 1334-1366
|
A lesson from Argentina: Setting transmission tolls in a competitive auction is much better than regulating them
|
Author keywords
Auctions; BOM contract; Comahue; GEEAC; Transener; Transmission
|
Indexed keywords
COSTS;
ELECTRIC LINES;
ELECTRIC POWER SYSTEMS;
ELECTRIC POWER TRANSMISSION;
MATHEMATICAL MODELS;
REGULATORY COMPLIANCE;
STANDARDS;
SOCIAL WELFARE;
TRANSMISSION TOLLS;
ELECTRICITY;
COMPETITIVENESS;
COST;
ELECTRICITY SUPPLY;
MODELING;
REGULATORY FRAMEWORK;
WELFARE IMPACT;
ARGENTINA;
SOUTH AMERICA;
|
EID: 43449132764
PISSN: 01409883
EISSN: None
Source Type: Journal
DOI: 10.1016/j.eneco.2008.01.009 Document Type: Article |
Times cited : (6)
|
References (16)
|