Volumn 4446 LNCS, Issue , 2007, Pages 25-35

A genetic algorithm for the resource renting problem with minimum and maximum time lags

Author keywords

Genetic algorithms; Metaheuristic algorithms; Project scheduling; Resource costs; Temporal constraints

Indexed keywords

COSTS; HEURISTIC ALGORITHMS; PROBLEM SOLVING; PROJECT MANAGEMENT;

EID: 38049013796     PISSN: 03029743     EISSN: 16113349     Source Type: Book Series    
DOI: 10.1007/978-3-540-71615-0_3     Document Type: Conference Paper
Times cited : (15)

References (16)
  • 1
    • 38049012190 scopus 로고
    • Construction performance control by networks
    • New York
    • Ahuja, H.N.: Construction performance control by networks. (1976) John Wiley, New York.
    • (1976) John Wiley
    • Ahuja, H.N.1
  • 2
    • 38049013617 scopus 로고    scopus 로고
    • Resource leveling in make-to-order production: Modeling and heuristic solution method, accepted for the International
    • Ballestín, F., Schwindt, C., Zimmermann, J.: Resource leveling in make-to-order production: modeling and heuristic solution method, accepted for the International Journal of Operations Research.
    • Journal of Operations Research
    • Ballestín, F.1    Schwindt, C.2    Zimmermann, J.3
  • 3
    • 0000463458 scopus 로고
    • Minimizing resource availability costs in time-limited project networks
    • Demeulemeester, E.: Minimizing resource availability costs in time-limited project networks. Management Science 41 (1995) 1590-1598.
    • (1995) Management Science , vol.41 , pp. 1590-1598
    • Demeulemeester, E.1
  • 4
    • 0026376478 scopus 로고
    • Scheduling of project networks by job assignment
    • Drexl, A.; Scheduling of project networks by job assignment. Management Science, 37 (1991) 1590-1602.
    • (1991) Management Science , vol.37 , pp. 1590-1602
    • Drexl, A.1
  • 6
    • 0032042933 scopus 로고    scopus 로고
    • Resource-Constrained Project Scheduling: A Survey of Recent Developments
    • Herroelen, W., B. De Reyck, and E. Demeulemeester. (1998). "Resource-Constrained Project Scheduling: A Survey of Recent Developments." Computers and Operations Research 25(4), 279-302.
    • (1998) Computers and Operations Research , vol.25 , Issue.4 , pp. 279-302
    • Herroelen, W.1    De Reyck, B.2    Demeulemeester, E.3
  • 7
    • 38049074673 scopus 로고    scopus 로고
    • Holland, H. J.: Adaptation in natural and artificial systems. (1975) University of Michigan Press, Ann Arbor.
    • Holland, H. J.: Adaptation in natural and artificial systems. (1975) University of Michigan Press, Ann Arbor.
  • 9
    • 0002030301 scopus 로고    scopus 로고
    • Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis
    • J. Weglarz Ed, Kluwer Academic Publishers, Berlin
    • Kolisch, R., Hartmann, S.: Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis, in: J. Weglarz (Ed.), Project Scheduling: Recent Models, Algorithms and Applications, Kluwer Academic Publishers, Berlin, (1999), pp. 147-178.
    • (1999) Project Scheduling: Recent Models, Algorithms and Applications , pp. 147-178
    • Kolisch, R.1    Hartmann, S.2
  • 11
    • 38049063766 scopus 로고    scopus 로고
    • Project Scheduling with Time Windows and Scarce Resources
    • Berlin
    • Neumann, K., Schwindt, C., Zimmermann, J.: Project Scheduling with Time Windows and Scarce Resources. (2003) Springer, Berlin.
    • (2003) Springer
    • Neumann, K.1    Schwindt, C.2    Zimmermann, J.3
  • 12
    • 0034559447 scopus 로고    scopus 로고
    • Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints
    • Neumann, K., Zimmermann, J.: Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints. European Journal of Operational Research, 127 (2000) 425-443.
    • (2000) European Journal of Operational Research , vol.127 , pp. 425-443
    • Neumann, K.1    Zimmermann, J.2
  • 14
    • 0442327390 scopus 로고    scopus 로고
    • The resource renting problem subject to temporal constraints
    • Nübel, H.: The resource renting problem subject to temporal constraints, OR Spektrum 23 (2001) 359-381.
    • (2001) OR Spektrum , vol.23 , pp. 359-381
    • Nübel, H.1
  • 15
    • 0029636114 scopus 로고
    • Semi-active, active and non-delay schedules for the resource-constrained project scheduling problem
    • Sprecher, A., Kolisch, R. and Drexl, A.: Semi-active, active and non-delay schedules for the resource-constrained project scheduling problem. European Journal of Operational Research 80 (1995) 94-102.
    • (1995) European Journal of Operational Research , vol.80 , pp. 94-102
    • Sprecher, A.1    Kolisch, R.2    Drexl, A.3
  • 16
    • 0035617606 scopus 로고    scopus 로고
    • An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem
    • Vanhoucke, M., Demeulemeester, E.L. and Herroelen, W. S.: An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem. Annals of Operations Research, 102 (2001) 179-196.
    • (2001) Annals of Operations Research , vol.102 , pp. 179-196
    • Vanhoucke, M.1    Demeulemeester, E.L.2    Herroelen, W.S.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.