1
-
-
0029220230
-
Criticality in Resource Constrained Networks
-
Bowers, J.A., (1995) "Criticality in Resource Constrained Networks," Journal of the Operational Research Society 46:1, pp. 80-91.
-
(1995)
Journal of the Operational Research Society
, vol.46
, Issue.1
, pp. 80-91
-
-
Bowers, J.A.1
-
3
-
-
32644440855
-
Multi-Project Scheduling and Control: A Process-based Comparative Study of the Critical Chain Methodology and Some Alternatives
-
Cohen, I., A. Mandelbaum, et al., (2004) "Multi-Project Scheduling and Control: A Process-based Comparative Study of the Critical Chain Methodology and Some Alternatives," Project Management Journal, 35(2), pp. 39-50.
-
(2004)
Project Management Journal
, vol.35
, Issue.2
, pp. 39-50
-
-
Cohen, I.1
Mandelbaum, A.2
-
4
-
-
0031272722
-
New Benchmark Results for the Resource-Constrained Project Scheduling Problem
-
Demeulemeester, E.L., and W.S. Herroelen, (1997) "New Benchmark Results for the Resource-Constrained Project Scheduling Problem," Management Science 43:11, pp. 1485-1492.
-
(1997)
Management Science
, vol.43
, Issue.11
, pp. 1485-1492
-
-
Demeulemeester, E.L.1
Herroelen, W.S.2
-
5
-
-
0004227599
-
-
J. Wiley and Sons
-
Forsberg, K., H. Mooz, and H. Cotterman, (2000) Visualizing Project Management, 2nd ed., J. Wiley and Sons.
-
(2000)
Visualizing Project Management, 2Nd Ed
-
-
Forsberg, K.1
Mooz, H.2
Cotterman, H.3
-
6
-
-
0004260163
-
PMBOK and the Critical Chain
-
Globerson, S., (2000) "PMBOK and the Critical Chain," PM Network, 14(5), pp. 63-66.
-
(2000)
PM Network
, vol.14
, Issue.5
, pp. 63-66
-
-
Globerson, S.1
-
10
-
-
0004348327
-
Critical Chain
-
Goldratt, E.M., Critical Chain, IIE Transactions, 30 (1998), pp. 759-763.
-
(1998)
IIE Transactions
, vol.30
, pp. 759-763
-
-
Goldratt, E.M.1
-
12
-
-
0026207547
-
Parkinson's Law and its Implications for Project Management
-
Gutierrez, G., and P. Kouvelis, (1991) "Parkinson's Law and its Implications for Project Management," Management Science, 37(8), pp. 990-1001.
-
(1991)
Management Science
, vol.37
, Issue.8
, pp. 990-1001
-
-
Gutierrez, G.1
Kouvelis, P.2
-
13
-
-
1542422015
-
Critical Chain Project Scheduling: Do Not Oversimplify
-
Heroelen, W., R. Leus, and E. Demeulemeester, (2002) "Critical Chain Project Scheduling: Do Not Oversimplify," Project Management Journal, 33(4), pp. 48-60.
-
(2002)
Project Management Journal
, vol.33
, Issue.4
, pp. 48-60
-
-
Heroelen, W.1
Leus, R.2
Demeulemeester, E.3
-
14
-
-
0035480172
-
On the Merits and Pitfalls of Critical Chain Scheduling
-
Herroelen, W., and R. Leus, "On the Merits and Pitfalls of Critical Chain Scheduling," Journal of Operations Management, 19 (2001), pp. 559-577.
-
(2001)
Journal of Operations Management
, vol.19
, pp. 559-577
-
-
Herroelen, W.1
Leus, R.2
-
15
-
-
0032042933
-
Resource-Constrained Project Scheduling: A Survey of Recent Developments
-
Herroelen, W., B.D. Reyck, et al., (1998) "Resource-Constrained Project Scheduling: A Survey of Recent Developments," Computers and Operations Research, 25(4), pp. 279-302.
-
(1998)
Computers and Operations Research
, vol.25
, Issue.4
, pp. 279-302
-
-
Herroelen, W.1
Reyck, B.D.2
-
17
-
-
0002645824
-
Critical Chain Project Management Improves Project Performance
-
Leach, L.P., (1999) "Critical Chain Project Management Improves Project Performance," Project Management Journal, 30(2), pp. 39-51.
-
(1999)
Project Management Journal
, vol.30
, Issue.2
, pp. 39-51
-
-
Leach, L.P.1
-
19
-
-
80053380013
-
Final Report, "NASA Strategic Multi-project Resource Management 'CC-Lite',"
-
Lechler, T., B. Ronen, and E.A. Stohr, Final Report, "NASA Strategic Multi-project Resource Management 'CC-Lite'," NASA CPMR Project Report, Phase 1 (2005).
-
(2005)
NASA CPMR Project Report, Phase 1
-
-
Lechler, T.1
Ronen, B.2
Stohr, E.A.3
-
23
-
-
0004348327
-
Critical Chain
-
McKay, K.N., and T.E. Morton, (1998) "Critical Chain," IIE Transactions, 30(8), pp. 759-763.
-
(1998)
IIE Transactions
, vol.30
, Issue.8
, pp. 759-763
-
-
McKay, K.N.1
Morton, T.E.2
-
24
-
-
21444437471
-
Introduction
-
Morris, Peter and Jeffrey Pinto (eds.), John Wiley & Sons
-
Morris, Peter, and Jeffrey Pinto, "Introduction" in (2004) The Wiley Guide to Managing Projects, Morris, Peter and Jeffrey Pinto (eds.), John Wiley & Sons.
-
(2004)
The Wiley Guide to Managing Projects
-
-
Morris, P.1
Pinto, J.2
-
26
-
-
0242364616
-
Management by the Market Constraint in the Hi Tech Industry
-
Pass, S., and B. Ronen, (2003) "Management by the Market Constraint in the Hi Tech Industry," International Journal of Production Research, 41(4), pp. 713-724.
-
(2003)
International Journal of Production Research
, vol.41
, Issue.4
, pp. 713-724
-
-
Pass, S.1
Ronen, B.2
-
27
-
-
32644446899
-
Program Management-Turning Many Projects into Few Priorities with TOC
-
Patrick, F., "Program Management-Turning Many Projects into Few Priorities with TOC," Project Management Institute Symposium (1998a).
-
(1998)
Project Management Institute Symposium
-
-
Patrick, F.1
-
28
-
-
0004357092
-
Critical Chain Scheduling and Buffer Management-Getting Out From Between Parkinson's Rock and Murphy's Hard Place
-
Patrick, F.S., "Critical Chain Scheduling and Buffer Management-Getting Out From Between Parkinson's Rock and Murphy's Hard Place," PM Network, 13 (1998b), pp. 57-62.
-
(1998)
PM Network
, vol.13
, pp. 57-62
-
-
Patrick, F.S.1
-
29
-
-
0004288045
-
Some Constraints on the Theory of Constraints-Taking a Critical Look at the Critical Chain
-
Pinto, J.K., (1999) "Some Constraints on the Theory of Constraints-Taking a Critical Look at the Critical Chain," PM Network, 13(8), pp. 49-51.
-
(1999)
PM Network
, vol.13
, Issue.8
, pp. 49-51
-
-
Pinto, J.K.1
-
34
-
-
0033896225
-
Critical Chain: The Theory of Constraints Applied to Project Management
-
Rand, G.K., (2000) "Critical Chain: The Theory of Constraints Applied to Project Management," International Journal of Project Management, 18(3), pp. 173-177.
-
(2000)
International Journal of Project Management
, vol.18
, Issue.3
, pp. 173-177
-
-
Rand, G.K.1
-
35
-
-
18144388787
-
A Critical Look at Critical Chain Project Management
-
Raz, T., R. Barnes, et al., (2003) "A Critical Look at Critical Chain Project Management," Project Management Journal, 34(4), pp. 24-32.
-
(2003)
Project Management Journal
, vol.34
, Issue.4
, pp. 24-32
-
-
Raz, T.1
Barnes, R.2
-
36
-
-
0025657214
-
Synchronized Manufacturing as in OPT: From Practice to Theory
-
August
-
Ronen, B., and M.K. Starr, "Synchronized Manufacturing as in OPT: From Practice to Theory," Computers and Industrial Engineering, 18:8 (August 1990), pp. 585-600.
-
(1990)
Computers and Industrial Engineering
, vol.18
, Issue.8
, pp. 585-600
-
-
Ronen, B.1
Starr, M.K.2
-
38
-
-
84955154307
-
Estimation of Project Buffers in Critical Chain Project Management
-
Shou, Y., and K.T. Yeo, "Estimation of Project Buffers in Critical Chain Project Management," ICMIT (2000), pp. 162-167.
-
(2000)
ICMIT
, pp. 162-167
-
-
Shou, Y.1
Yeo, K.T.2
-
39
-
-
58149433367
-
Rational Choice and the Structure of the Environment
-
Simon, H.A., "Rational Choice and the Structure of the Environment," Psychological Review, 63 (1956), pp. 129-138.
-
(1956)
Psychological Review
, vol.63
, pp. 129-138
-
-
Simon, H.A.1
-
40
-
-
0035426806
-
An Investigation into the Fundamentals of Critical Chain Project Scheduling
-
Steyn, H., "An Investigation into the Fundamentals of Critical Chain Project Scheduling," International Journal of Project Management, 19 (2000), pp. 363-369.
-
(2000)
International Journal of Project Management
, vol.19
, pp. 363-369
-
-
Steyn, H.1
-
41
-
-
0036132285
-
Project Management Applications of the Theory of Constraints Beyond Critical Chain Scheduling
-
Steyn, H., "Project Management Applications of the Theory of Constraints Beyond Critical Chain Scheduling," International Journal of Project Management, 20 (2002), pp. 75-80.
-
(2002)
International Journal of Project Management
, vol.20
, pp. 75-80
-
-
Steyn, H.1
-
42
-
-
0001876346
-
R&D Project Planning with QGERT Network Modeling and Simulation
-
Taylor, B.W., and L.J. Moore, (1980) "R&D Project Planning with QGERT Network Modeling and Simulation," Management Science, 26(1), pp. 44-59.
-
(1980)
Management Science
, vol.26
, Issue.1
, pp. 44-59
-
-
Taylor, B.W.1
Moore, L.J.2
-
43
-
-
0039599042
-
Manage Your Projects for Success: An Application of the Theory of Constraints
-
Umble, M., and E. Umble, (2000) "Manage Your Projects for Success: An Application of the Theory of Constraints," Production and Inventory Management Journal, 41(2), pp. 27-32.
-
(2000)
Production and Inventory Management Journal
, vol.41
, Issue.2
, pp. 27-32
-
-
Umble, M.1
Umble, E.2
-
44
-
-
0035922498
-
Maximizing the Present Value of a Project with Linearly Time-Dependent Cash Flows
-
Vanhouke, M., E. Demeulemeester, and W. Herroelen, (2001) "Maximizing the Present Value of a Project with Linearly Time-Dependent Cash Flows," International Journal of Production Research, 39(14), pp. 3159-3181.
-
(2001)
International Journal of Production Research
, vol.39
, Issue.14
, pp. 3159-3181
-
-
Vanhouke, M.1
Demeulemeester, E.2
Herroelen, W.3
|