Volumn 12, Issue 4, 2001, Pages 388-398

Annualized hours as a capacity planning tool in make-to-order or assemble-to-order environment: An agricultural implements company case

Author keywords

Annualized hours; Assemble to order; Flexible capacity; Make to order; Rough cut capacity planning

Indexed keywords

COMPUTER SIMULATION; CONTROL SYSTEM ANALYSIS; INVENTORY CONTROL; LINEAR PROGRAMMING; STRATEGIC PLANNING;

EID: 0035384304     PISSN: 09537287     EISSN: None     Source Type: Journal    
DOI: 10.1080/09537280152005012     Document Type: Article
Times cited : (16)

References (40)
  • 1
    • 0011718706 scopus 로고
    • Capacity planning techniques for manufacturing control systems: Information requirements and operational features
    • Berry, W.L., Schmitt, T.G., and Vollmann, T.E., 1982, Capacity planning techniques for manufacturing control systems: information requirements and operational features. Journal of Operations Management, 3, 13-25.
    • (1982) Journal of Operations Management , vol.3 , pp. 13-25
    • Berry, W.L.1    Schmitt, T.G.2    Vollmann, T.E.3
  • 2
    • 0022676381 scopus 로고
    • Production planning of style goods with high set-up costs and forecast revisions
    • Bitran, G.R., Haas, E.A., and Mastsuo, H., 1986, Production planning of style goods with high set-up costs and forecast revisions. Operations Research, 34, 226-236.
    • (1986) Operations Research , vol.34 , pp. 226-236
    • Bitran, G.R.1    Haas, E.A.2    Mastsuo, H.3
  • 3
    • 0004140981 scopus 로고
    • Cincinnati, OH: South-Western Publishing
    • Blackstone, J.H., 1989, Capacity Management (Cincinnati, OH: South-Western Publishing).
    • (1989) Capacity Management
    • Blackstone, J.H.1
  • 4
    • 0030836896 scopus 로고    scopus 로고
    • Nonlinear programming for multiperiod capacity planning in a manufacturing system
    • Bretthauer, K.M., and Côté, M.J., 1996, Nonlinear programming for multiperiod capacity planning in a manufacturing system. European Journal of Operational Research, 96, 167-179.
    • (1996) European Journal of Operational Research , vol.96 , pp. 167-179
    • Bretthauer, K.M.1    Côté, M.J.2
  • 6
    • 0002718913 scopus 로고
    • Annual hours brings productivity boost to spicers
    • July
    • Curran, P., 1992, Annual hours brings productivity boost to spicers. Management Services, July, 32-33.
    • (1992) Management Services , pp. 32-33
    • Curran, P.1
  • 7
    • 0030193969 scopus 로고    scopus 로고
    • Production strategies for stochastic lot-sizing problem with constant capacity
    • Dellaert, N.P., and Melo, M.T., 1996, Production strategies for stochastic lot-sizing problem with constant capacity. European Journal of Operational Research, 92, 281-301.
    • (1996) European Journal of Operational Research , vol.92 , pp. 281-301
    • Dellaert, N.P.1    Melo, M.T.2
  • 8
    • 0029250512 scopus 로고
    • A decision support system (DSS) for agricultural pesticide production planning
    • Eliman, A.A., 1995, A decision support system (DSS) for agricultural pesticide production planning. European Journal of Operational Research, 81, 17-34.
    • (1995) European Journal of Operational Research , vol.81 , pp. 17-34
    • Eliman, A.A.1
  • 9
    • 0030284990 scopus 로고    scopus 로고
    • Capacity management through Lagrangean relaxation: An application to tyres production
    • Fumero, F., and Vercellis, C., 1996, Capacity management through Lagrangean relaxation: an application to tyres production. Production Planning & Control, 7, 604-614.
    • (1996) Production Planning & Control , vol.7 , pp. 604-614
    • Fumero, F.1    Vercellis, C.2
  • 11
    • 0030231648 scopus 로고    scopus 로고
    • Allocating production capacity among multiple products
    • Glasserman, P., 1996, Allocating production capacity among multiple products. Operations Research, 44, 724-734.
    • (1996) Operations Research , vol.44 , pp. 724-734
    • Glasserman, P.1
  • 12
    • 0031118844 scopus 로고    scopus 로고
    • Rough-cut capacity planning for remanufacturing firms
    • Guide, V.D.R., and Spencer, M.S., 1997, Rough-cut capacity planning for remanufacturing firms. Production Planning & Control, 8, 237-244.
    • (1997) Production Planning & Control , vol.8 , pp. 237-244
    • Guide, V.D.R.1    Spencer, M.S.2
  • 15
    • 0032624548 scopus 로고    scopus 로고
    • Scheduling a workforce under annualised hours
    • Hung, R., 1999, Scheduling a workforce under annualised hours. International Journal of Production Research, 37, 2419-2427.
    • (1999) International Journal of Production Research , vol.37 , pp. 2419-2427
    • Hung, R.1
  • 16
    • 0026170526 scopus 로고
    • Job content and working time: The scope for joint change
    • Koogi, K., 1991, Job content and working time: the scope for joint change. Ergonomics, 34, 757-773.
    • (1991) Ergonomics , vol.34 , pp. 757-773
    • Koogi, K.1
  • 17
    • 0011778390 scopus 로고
    • Production smoothing under piecewise concave costs, capacity constraints and nondecreasing requirements
    • Korgaonker, M.G., 1977, Production smoothing under piecewise concave costs, capacity constraints and nondecreasing requirements. Management Science, 24, 302-311.
    • (1977) Management Science , vol.24 , pp. 302-311
    • Korgaonker, M.G.1
  • 18
    • 0028730010 scopus 로고
    • Making strategy work with sales and operations planning
    • Ling, R.C., 1994, Making strategy work with sales and operations planning. APICS 37th Conference Proceedings, pp. 96-98.
    • (1994) APICS 37th Conference Proceedings , pp. 96-98
    • Ling, R.C.1
  • 19
    • 0020183161 scopus 로고
    • Operations research and capacity expansion problems: A survey
    • Luss, H., 1982, Operations research and capacity expansion problems: a survey. Operational Research, 30, 907-947.
    • (1982) Operational Research , vol.30 , pp. 907-947
    • Luss, H.1
  • 22
    • 0000751990 scopus 로고
    • Stochastic sequencing problem for style goods with forecast revisions and hierarchical structure
    • Matsuo, H., 1990, Stochastic sequencing problem for style goods with forecast revisions and hierarchical structure. Management Science, 36, 332-347.
    • (1990) Management Science , vol.36 , pp. 332-347
    • Matsuo, H.1
  • 23
    • 0001913255 scopus 로고
    • Coming: The annual workweek
    • April
    • Mazur, L., 1995, Coming: The Annual Workweek. Across the Board, April, 42-45.
    • (1995) Across the Board , pp. 42-45
    • Mazur, L.1
  • 24
    • 0011749264 scopus 로고
    • Integrating current end-item inventory conditions into optimization-based long-run aggregate production and distribution planning
    • Miller, T.C., 1991, Integrating current end-item inventory conditions into optimization-based long-run aggregate production and distribution planning. Production and Inventory Management Journal, 32, 74-80.
    • (1991) Production and Inventory Management Journal , vol.32 , pp. 74-80
    • Miller, T.C.1
  • 26
    • 0030174006 scopus 로고    scopus 로고
    • Reserve production capacity in a production inventory system
    • Obuko, B., 1996, Reserve production capacity in a production inventory system. International Journal of Production Economics, 44, 159-166.
    • (1996) International Journal of Production Economics , vol.44 , pp. 159-166
    • Obuko, B.1
  • 28
    • 0032635740 scopus 로고    scopus 로고
    • Delivery date decision support system for the large scale make-to-order manufacturing companies: A Korean electric motor company case
    • Park, C.J., Song, J., Kim, J.G., and Kim, I., 1999, Delivery date decision support system for the large scale make-to-order manufacturing companies: a Korean Electric motor company case. Production Planning & Control, 10, 585-597.
    • (1999) Production Planning & Control , vol.10 , pp. 585-597
    • Park, C.J.1    Song, J.2    Kim, J.G.3    Kim, I.4
  • 29
    • 84933484845 scopus 로고
    • Annual hours: A year of living dangerously
    • Pickard, J., 1991, Annual hours: a year of living dangerously. Personnel Management, 8, 38-43.
    • (1991) Personnel Management , vol.8 , pp. 38-43
    • Pickard, J.1
  • 35
    • 0011714882 scopus 로고
    • Flexiyear schedules - Only a matter of time?
    • Teriet, B., 1977, Flexiyear schedules - only a matter of time? Monthly Labor Review, 100, 62-65.
    • (1977) Monthly Labor Review , vol.100 , pp. 62-65
    • Teriet, B.1
  • 36
    • 0026243392 scopus 로고
    • Multi-criteria models for capacity analysis and aggregate planning in manufacturing systems
    • Vercellis, C., 1991, Multi-criteria models for capacity analysis and aggregate planning in manufacturing systems. International Journal of Production Economics, 23, 262-272.
    • (1991) International Journal of Production Economics , vol.23 , pp. 262-272
    • Vercellis, C.1
  • 38
    • 0345072524 scopus 로고    scopus 로고
    • On the risk-based aggregate planning for seasonal products
    • Vörös, J., 1999, On the risk-based aggregate planning for seasonal products. International Journal of Production Economics, 59, 195-201.
    • (1999) International Journal of Production Economics , vol.59 , pp. 195-201
    • Vörös, J.1
  • 40
    • 0029350747 scopus 로고
    • Comparison of information systems for engineer-to-order and make-to-stock situations
    • Wortmann, H., 1995, Comparison of information systems for engineer-to-order and make-to-stock situations. Computers in Industry, 26, 261-271.
    • (1995) Computers in Industry , vol.26 , pp. 261-271
    • Wortmann, H.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.