메뉴 건너뛰기




Volumn 5, Issue 2, 2007, Pages 143-149

Incentivising project performance in the construction of new facilities: Utilising the earned value-based method

Author keywords

Contracts; Facilities; Incentive schemes; Project evaluation

Indexed keywords


EID: 84904197457     PISSN: 14725967     EISSN: 17410983     Source Type: Journal    
DOI: 10.1108/14725960710751889     Document Type: Article
Times cited : (4)

References (15)
  • 2
    • 0035279228 scopus 로고    scopus 로고
    • Defining cost/schedule performance indices and their ranges for design projects
    • April, -
    • Chang, A.S. (2001), “Defining cost/schedule performance indices and their ranges for design projects”, Journal of Management in Engineering, April, pp. 122-30.
    • (2001) Journal of Management in Engineering , pp. 122-130
    • Chang, A.S.1
  • 4
    • 15844410949 scopus 로고    scopus 로고
    • Engineering performance in the US industrial construction sector
    • Georgy, M.E., Luh-Maan, C. and Zhang, L. (2005), “Engineering performance in the US industrial construction sector”, Cost Engineering, Vol. 47 No. 1, pp. 27-36.
    • (2005) Cost Engineering , vol.47 , Issue.1 , pp. 27-36
    • Georgy, M.E.1    Luh-Maan, C.2    Zhang, L.3
  • 6
    • 84986099127 scopus 로고    scopus 로고
    • The application of facilities management expertise to the hotel renovation process
    • Hassanien, A. and Losekoot, E. (2002), “The application of facilities management expertise to the hotel renovation process”, Facilities, Vol. 20 Nos 7/8.
    • (2002) Facilities , vol.20 , Issue.7-8
    • Hassanien, A.1    Losekoot, E.2
  • 8
    • 0002401844 scopus 로고
    • The balanced scorecard – measures that drive performance
    • Kaplan, R.S. and Norton, D.P. (1992), “The balanced scorecard – measures that drive performance”, Harvard Business Review, Vol. 40 No. 1, pp. 7-9.
    • (1992) Harvard Business Review , vol.40 , Issue.1 , pp. 7-9
    • Kaplan, R.S.1    Norton, D.P.2
  • 9
    • 33745002741 scopus 로고    scopus 로고
    • Distortions and deceptions in strategic decisions
    • Lovallo, D.P. and Sibomy, O. (2006), “Distortions and deceptions in strategic decisions”, McKinsey Quarterly, Vol. 1, pp. 18-29.
    • (2006) McKinsey Quarterly , vol.1 , pp. 18-29
    • Lovallo, D.P.1    Sibomy, O.2
  • 10
    • 21444459526 scopus 로고    scopus 로고
    • The impact of principal-agent relationship and contract type on communication between project owner and manager
    • Muller, R. and Turner, J.R. (2005), “The impact of principal-agent relationship and contract type on communication between project owner and manager”, International Journal of Project Management, Vol. 23 No. 5, pp. 398-403.
    • (2005) International Journal of Project Management , vol.23 , Issue.5 , pp. 398-403
    • Muller, R.1    Turner, J.R.2
  • 12
    • 0032325778 scopus 로고    scopus 로고
    • Wall Street's contribution to management accounting: the Stern Stewart EVA financial management system
    • O'Hanlon, J. and Peasnell, K. (1998), “Wall Street's contribution to management accounting: the Stern Stewart EVA financial management system”, Management Accounting Research, Vol. 9 No. 4, pp. 421-44.
    • (1998) Management Accounting Research , vol.9 , Issue.4 , pp. 421-444
    • O'Hanlon, J.1    Peasnell, K.2
  • 14
    • 0036111161 scopus 로고    scopus 로고
    • RAVE: integrated value management for customer human, supplier and invested capital
    • Strack, R. and Villis, U. (2002), “RAVE: integrated value management for customer human, supplier and invested capital”, European Management Journal, Vol. 20 No. 2, pp. 147-58.
    • (2002) European Management Journal , vol.20 , Issue.2 , pp. 147-158
    • Strack, R.1    Villis, U.2
  • 15
    • 84889140049 scopus 로고
    • Managing design under lump-sum contract
    • March/April, -
    • Willoughby, T.J. (1995), “Managing design under lump-sum contract”, Journal of Management in Engineering, March/April, pp. 21-5.
    • (1995) Journal of Management in Engineering , pp. 21-25
    • Willoughby, T.J.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.