A new multi-objective multi-mode model for solving preemptive time-cost-quality trade-off project scheduling problems

Author keywords

Activity preemption; Discrete time cost trade off problem; Generalized precedence relations; Multi objective evolutionary algorithm; Project scheduling problem

Indexed keywords

CONFLICTING OBJECTIVES; DISCRETE TIME-COST TRADE-OFF PROBLEMS; GENERALIZED PRECEDENCE RELATIONS; MULTI OBJECTIVE EVOLUTIONARY ALGORITHMS; MULTI-OBJECTIVE MATHEMATICAL PROGRAMMING; PERFORMANCE METRICS; PROJECT SCHEDULING PROBLEM; SIMULTANEOUS OPTIMIZATION;

EID: 84888326307     PISSN: 09574174     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.eswa.2013.08.081     Document Type: Article
Times cited : (130)

References (57)
  • 2
    • 26044472796 scopus 로고    scopus 로고
    • A genetic algorithm approach for the time-cost trade-off in PERT networks
    • DOI 10.1016/j.amc.2004.10.021, PII S0096300304007040
    • A. Azaron, C. Perkgoz, and M. Sakawa A genetic algorithm approach for the time-cost trade-off in PERT networks Applied Mathematics and Computation 168 2 2005 1317 1339 (Pubitemid 41405681)
    • (2005) Applied Mathematics and Computation , vol.168 , Issue.2 , pp. 1317-1339
    • Azaron, A.1    Perkgoz, C.2    Sakawa, M.3
  • 3
    • 0029772743 scopus 로고    scopus 로고
    • Project management with time, cost, and quality considerations
    • DOI 10.1016/0377-2217(94)00202-9
    • A.J. Babu, and N. Suresh Project management with time, cost and quality considerations European Journal of Operational Research 88 1996 320 327 (Pubitemid 126378090)
    • (1996) European Journal of Operational Research , vol.88 , Issue.2 , pp. 320-327
    • Babu, A.J.G.1    Suresh, N.2
  • 6
    • 15344348592 scopus 로고    scopus 로고
    • Tight LP bounds for resource constrained project scheduling
    • DOI 10.1007/s00291-003-0155-1
    • P. Baptiste, and S. Demassey Tight LP bounds for resource constrained project scheduling OR Spectrum 26 2 2004 251 262 (Pubitemid 40549771)
    • (2004) OR Spectrum , vol.26 , Issue.2 , pp. 251-262
    • Baptiste, P.1    Demassey, S.2
  • 7
    • 84856537184 scopus 로고    scopus 로고
    • An exact algorithm to minimize the makespan in project scheduling with scarce resources and generalized precedence relations
    • L. Bianco, and M. Caramia An exact algorithm to minimize the makespan in project scheduling with scarce resources and generalized precedence relations European Journal of Operational Research 219 2012 73 85
    • (2012) European Journal of Operational Research , vol.219 , pp. 73-85
    • Bianco, L.1    Caramia, M.2
  • 9
    • 4544318435 scopus 로고    scopus 로고
    • The LP/IP hybrid method for construction time-cost trade-off analysis
    • S. Burns, L. Liu, and C. Feng The LP/IP hybrid method for construction time-cost trade-off analysis Construction Management and Economics 14 3 1996 265 276 (Pubitemid 126662979)
    • (1996) Construction Management and Economics , vol.14 , Issue.3 , pp. 265-276
    • Burns, S.A.1    Liu, L.2    Feng, C.-W.3
  • 12
    • 79951581770 scopus 로고    scopus 로고
    • Particle swarm optimization with justification and designed mechanisms for resource-constrained project scheduling problem
    • R.M. Chen Particle swarm optimization with justification and designed mechanisms for resource-constrained project scheduling problem Expert Systems with Applications 38 6 2011 7102 7111
    • (2011) Expert Systems with Applications , vol.38 , Issue.6 , pp. 7102-7111
    • Chen, R.M.1
  • 13
    • 70449527542 scopus 로고    scopus 로고
    • Using novel particle swarm optimization scheme to solve resource-constrained scheduling problem in PSPLIB
    • R.M. Chen, C.L. Wu, C.M. Wang, and S.T. Lo Using novel particle swarm optimization scheme to solve resource-constrained scheduling problem in PSPLIB Expert Systems with Applications 37 3 2010 1899 1910
    • (2010) Expert Systems with Applications , vol.37 , Issue.3 , pp. 1899-1910
    • Chen, R.M.1    Wu, C.L.2    Wang, C.M.3    Lo, S.T.4
  • 15
    • 84862706043 scopus 로고    scopus 로고
    • Project scheduling with flexible resources: Formulation and inequalities
    • I. Correia, L.L. Lourenço, and F. Saldanha-da-Gama Project scheduling with flexible resources: Formulation and inequalities OR Spectrum 34 3 2012 635 663
    • (2012) OR Spectrum , vol.34 , Issue.3 , pp. 635-663
    • Correia, I.1    Lourenço, L.L.2    Saldanha-Da-Gama, F.3
  • 16
    • 0043114427 scopus 로고
    • Project planning with precedence lead/lag factors
    • K.C. Crandall Project planning with precedence lead/lag factors Project Management Quarterly 4 3 1973 18 27
    • (1973) Project Management Quarterly , vol.4 , Issue.3 , pp. 18-27
    • Crandall, K.C.1
  • 17
    • 0031102411 scopus 로고    scopus 로고
    • Complexity of the discrete time-cost tradeoff problem for project networks
    • P. De, E. Dunne, J. Ghosh, and C. Wells Complexity of the discrete time/cost trade-off problem for project networks Operations Research 45 1997 302 306 (Pubitemid 127684708)
    • (1997) Operations Research , vol.45 , Issue.2 , pp. 302-306
    • De, P.1    Dunne, E.J.2    Ghosh, J.B.3    Wells, C.E.4
  • 18
    • 0036530772 scopus 로고    scopus 로고
    • A fast and elitist multiobjective genetic algorithm: NSGA-II
    • DOI 10.1109/4235.996017, PII S1089778X02041012
    • K. Deb, A. Pratap, S. Agarwal, and T. Meyarivan A fast an elitist multi-objective genetic algorithm: NSGA-II IEEE Transactions on Evolutionary Computation 6 2 2002 182 197 (Pubitemid 34555372)
    • (2002) IEEE Transactions on Evolutionary Computation , vol.6 , Issue.2 , pp. 182-197
    • Deb, K.1    Pratap, A.2    Agarwal, S.3    Meyarivan, T.4
  • 19
    • 0034311599 scopus 로고    scopus 로고
    • The discrete time/resource trade-off problem in project networks: A branch-and-bound approach
    • E. Demeulemeester, B. De Reyck, and W. Herroelen The discrete time/resource trade-off problem in project networks: A branch-and-bound approach IIE Transactions 32 11 2000 1059 1069
    • (2000) IIE Transactions , vol.32 , Issue.11 , pp. 1059-1069
    • Demeulemeester, E.1    De Reyck, B.2    Herroelen, W.3
  • 20
    • 0030122629 scopus 로고    scopus 로고
    • An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem
    • E. Demeulemeester, and W. Herroelen An efficient optimal procedure for the preemptive resource-constrained project scheduling problem European Journal of Operational Research 90 1996 334 348 (Pubitemid 126652218)
    • (1996) European Journal of Operational Research , vol.90 , Issue.2 , pp. 334-348
    • Demeulemeester, E.L.1    Herroelen, W.S.2
  • 22
    • 3543055794 scopus 로고    scopus 로고
    • RanGen: A random network generator for activity-on-the-node networks
    • E. Demeulemeester, M. Vanhoucke, and W. Herroelen RanGen: A random network generator for activity-on-the-node networks Journal of Scheduling 6 2003 17 38
    • (2003) Journal of Scheduling , vol.6 , pp. 17-38
    • Demeulemeester, E.1    Vanhoucke, M.2    Herroelen, W.3
  • 23
    • 15944361924 scopus 로고    scopus 로고
    • Time-cost-quality trade-off analysis for highway construction
    • DOI 10.1061/(ASCE)0733-9364(2005)131:4(477)
    • K. El-Rayes, and A. Kandil Time-cost-quality trade-off analysis for highway construction Journal of Construction Engineering and Management 131 4 2005 477 486 (Pubitemid 40430144)
    • (2005) Journal of Construction Engineering and Management , vol.131 , Issue.4 , pp. 477-486
    • El-Rayes, K.1    Kandil, A.2
  • 24
    • 0035281212 scopus 로고    scopus 로고
    • Resource constrained project scheduling problem with multiple crashable modes: An exact solution method
    • DOI 10.1002/1520-6750(200103)48:2<107::AID-NAV1>3.0.CO;2-9
    • S.S. Erenguc, T. Ahn, and D.G. Conway The resource constrained project scheduling problem with multiple crashable modes: An exact solution method Naval Research Logistics 48 2 2001 107 127 (Pubitemid 32252182)
    • (2001) Naval Research Logistics , vol.48 , Issue.2 , pp. 107-127
    • Erenguc, S.S.1    Ahn, T.2    Conway, D.G.3
  • 25
    • 80255123850 scopus 로고    scopus 로고
    • Extraction of decision alternatives in construction management projects: Application and adaptation of NSGA-II and MOPSO
    • E. Fallah-Mehdipour, O. Bozorg Haddad, M.R. Tabari, and M.A. Mariño Extraction of decision alternatives in construction management projects: Application and adaptation of NSGA-II and MOPSO Expert Systems with Applications 39 3 2012 2794 2803
    • (2012) Expert Systems with Applications , vol.39 , Issue.3 , pp. 2794-2803
    • Fallah-Mehdipour, E.1    Bozorg Haddad, O.2    Tabari, M.R.3    Mariño, M.A.4
  • 26
    • 0036684673 scopus 로고    scopus 로고
    • A self-adapting genetic algorithm for project scheduling under resource constraints
    • DOI 10.1002/nav.10029
    • S. Hartmann A self-adapting genetic algorithm for project scheduling under resource constraints Naval Research Logistics 49 5 2002 433 448 (Pubitemid 34878877)
    • (2002) Naval Research Logistics , vol.49 , Issue.5 , pp. 433-448
    • Hartmann, S.1
  • 30
    • 84870192596 scopus 로고    scopus 로고
    • A new multi-objective particle swarm optimization method for solving reliability redundancy allocation problems
    • K. Khalili-Damghani, A.-R. Abtahi, and M. Tavana A new multi-objective particle swarm optimization method for solving reliability redundancy allocation problems Reliability Engineering and System Safety 111 2013 58 75
    • (2013) Reliability Engineering and System Safety , vol.111 , pp. 58-75
    • Khalili-Damghani, K.1    Abtahi, A.-R.2    Tavana, M.3
  • 31
    • 84859517787 scopus 로고    scopus 로고
    • Solving binary-state multi-objective reliability redundancy allocation series-parallel problem using a hybrid efficient epsilon-constraint constraint, multi-start partial bound enumeration algorithm, and DEA
    • K. Khalili-Damghani, and M. Amiri Solving binary-state multi-objective reliability redundancy allocation series-parallel problem using a hybrid efficient epsilon-constraint constraint, multi-start partial bound enumeration algorithm, and DEA Reliability Engineering and System Safety 103 2012 35 44
    • (2012) Reliability Engineering and System Safety , vol.103 , pp. 35-44
    • Khalili-Damghani, K.1    Amiri, M.2
  • 32
    • 84868468248 scopus 로고    scopus 로고
    • An integrated multi-objective framework for solving multi-period project selection problems
    • K. Khalili-Damghani, M. Tavana, and S. Sadi-Nezhad An integrated multi-objective framework for solving multi-period project selection problems Applied Mathematics and Computations 219 2012 3122 3138
    • (2012) Applied Mathematics and Computations , vol.219 , pp. 3122-3138
    • Khalili-Damghani, K.1    Tavana, M.2    Sadi-Nezhad, S.3
  • 33
    • 0033177842 scopus 로고    scopus 로고
    • Time, cost and quality trade-off in project management: A case study
    • D. Khang, and Y. Myint Time, cost and quality trade-off in project management: A case study International Journal of Project Management 17 1999 249 256
    • (1999) International Journal of Project Management , vol.17 , pp. 249-256
    • Khang, D.1    Myint, Y.2
  • 34
    • 84655169583 scopus 로고    scopus 로고
    • A practical approach to project scheduling: Considering the potential quality loss cost in the time-cost tradeoff problem
    • J. Kim, C. Kang, and I. Hwang A practical approach to project scheduling: Considering the potential quality loss cost in the time-cost tradeoff problem International Journal of Project Management 30 2 2012 264 272
    • (2012) International Journal of Project Management , vol.30 , Issue.2 , pp. 264-272
    • Kim, J.1    Kang, C.2    Hwang, I.3
  • 36
    • 67349211166 scopus 로고    scopus 로고
    • Effective implementation of the epsilon-constraint method in multi-objective mathematical programming problems
    • G. Mavrotas Effective implementation of the epsilon-constraint method in multi-objective mathematical programming problems Applied Mathematics and Computations 213 2009 455 465
    • (2009) Applied Mathematics and Computations , vol.213 , pp. 455-465
    • Mavrotas, G.1
  • 37
    • 0037871958 scopus 로고    scopus 로고
    • Solving project scheduling problems by minimum cut computations
    • R.H. Möhring, A.S. Schulz, F. Stork, and M. Uetz Solving project scheduling problems by minimum cut computations Management Science 49 2003 330 350
    • (2003) Management Science , vol.49 , pp. 330-350
    • Möhring, R.H.1    Schulz, A.S.2    Stork, F.3    Uetz, M.4
  • 38
    • 33750585495 scopus 로고    scopus 로고
    • Incorporating quality considerations into project time/cost tradeoff analysis and decision making
    • DOI 10.1109/TEM.2006.883705
    • B. Pollack-Johnson, and M. Liberatore Incorporating quality considerations into project time/cost tradeoff analysis and decision making IEEE Transactions on Engineering Management 53 2006 534 542 (Pubitemid 44680691)
    • (2006) IEEE Transactions on Engineering Management , vol.53 , Issue.4 , pp. 534-542
    • Pollack-Johnson, B.1    Liberatore, M.J.2
  • 40
    • 70449446451 scopus 로고    scopus 로고
    • Multi objective particle swarm optimization for a discrete time, cost and quality trade-off problem
    • M. Rahimi, and H. Iranmanesh Multi objective particle swarm optimization for a discrete time, cost and quality trade-off problem World Applied Sciences Journal 4 2 2008 270 276
    • (2008) World Applied Sciences Journal , vol.4 , Issue.2 , pp. 270-276
    • Rahimi, M.1    Iranmanesh, H.2
  • 41
    • 80052569757 scopus 로고    scopus 로고
    • Resource constraint scheduling with a fractional shared resource
    • G. Singh, and A.T. Ernst Resource constraint scheduling with a fractional shared resource Operations Research Letters 39 2011 363 368
    • (2011) Operations Research Letters , vol.39 , pp. 363-368
    • Singh, G.1    Ernst, A.T.2
  • 42
    • 0032208139 scopus 로고    scopus 로고
    • Approximation algorithms for the discrete Time-Cost Tradeoff Problem
    • M. Skutella Approximation algorithms for the discrete time-cost tradeoff problem Mathematics of Operations Research 23 4 1998 909 929 (Pubitemid 128508563)
    • (1998) Mathematics of Operations Research , vol.23 , Issue.4 , pp. 909-929
    • Skutella, M.1
  • 43
    • 84861348428 scopus 로고    scopus 로고
    • A hybrid genetic algorithm for the discrete time-cost trade-off problem
    • R. Sonmez, and Ö.H. Bettemir A hybrid genetic algorithm for the discrete time-cost trade-off problem Expert Systems with Applications 39 13 2012 11428 11434
    • (2012) Expert Systems with Applications , vol.39 , Issue.13 , pp. 11428-11434
    • Sonmez, R.1    Bettemir, Ö.H.2
  • 45
    • 81555204455 scopus 로고    scopus 로고
    • An integer programming formulation for the project scheduling problem with irregular time-cost tradeoffs
    • G.J. Szmerekovsky, and P. Venkateshanb An integer programming formulation for the project scheduling problem with irregular time-cost tradeoffs Computers and Operations Research 39 7 2012 1402 1410
    • (2012) Computers and Operations Research , vol.39 , Issue.7 , pp. 1402-1410
    • Szmerekovsky, G.J.1    Venkateshanb, P.2
  • 46
    • 33750488440 scopus 로고    scopus 로고
    • On the discrete time, cost and quality trade-off problem
    • DOI 10.1016/j.amc.2006.02.029, PII S0096300306002499
    • H.R. Tareghian, and S.H. Taheri On the discrete time, cost and quality trade-off problem Applied Mathematics and Computation 181 2006 1305 1312 (Pubitemid 44646603)
    • (2006) Applied Mathematics and Computation , vol.181 , Issue.2 , pp. 1305-1312
    • Tareghian, H.R.1    Taheri, S.H.2
  • 47
    • 34250621376 scopus 로고    scopus 로고
    • A solution procedure for the discrete time, cost and quality tradeoff problem using electromagnetic scatter search
    • DOI 10.1016/j.amc.2007.01.100, PII S0096300307001336
    • H.R. Tareghian, and S.H. Taheri A solution procedure for the discrete time, cost and quality tradeoff problem using electromagnetic scatter search Applied Mathematics and Computation 190 2007 1136 1145 (Pubitemid 46935855)
    • (2007) Applied Mathematics and Computation , vol.190 , Issue.2 , pp. 1136-1145
    • Tareghian, H.R.1    Taheri, S.H.2
  • 48
    • 70349276753 scopus 로고    scopus 로고
    • A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem
    • V. Van Peteghem, and M. Vanhoucke A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem European Journal of Operational Research 201 2 2010 409 418
    • (2010) European Journal of Operational Research , vol.201 , Issue.2 , pp. 409-418
    • Van Peteghem, V.1    Vanhoucke, M.2
  • 49
    • 13444280108 scopus 로고    scopus 로고
    • New computational results for the discrete time/cost trade-off problem with time-switch constraints
    • DOI 10.1016/j.ejor.2004.04.007, PII S0377221704002450, Project Management and Scheduling
    • M. Vanhoucke New computational results for the discrete time/cost trade-off problem with time-switch constraints European Journal of Operational Research 165 2 2005 359 374 (Pubitemid 40206367)
    • (2005) European Journal of Operational Research , vol.165 , Issue.2 , pp. 359-374
    • Vanhoucke, M.1
  • 50
    • 34848917527 scopus 로고    scopus 로고
    • The discrete time/cost trade-off problem: Extensions and heuristic procedures
    • DOI 10.1007/s10951-007-0031-y
    • M. Vanhoucke, D. Debels, and J. Sched The discrete time/cost trade-off problem: Extensions and heuristic procedures Journal of Scheduling 10 4-5 2007 311 326 (Pubitemid 47501053)
    • (2007) Journal of Scheduling , vol.10 , Issue.4-5 , pp. 311-326
    • Vanhoucke, M.1    Debels, D.2
  • 52
    • 67349195453 scopus 로고    scopus 로고
    • A multi-mode resource-constrained discrete time-cost trade-off problem and its genetic algorithm based solution
    • P. Wuliang, and W. Chengen A multi-mode resource-constrained discrete time-cost trade-off problem and its genetic algorithm based solution International Journal of Project Management 27 6 2009 600 609
    • (2009) International Journal of Project Management , vol.27 , Issue.6 , pp. 600-609
    • Wuliang, P.1    Chengen, W.2
  • 53
    • 84866400598 scopus 로고    scopus 로고
    • Discrete time-cost-environment trade-off problem for large-scale construction systems with s under fuzzy uncertainty and its application to Jinping-II hydroelectric project
    • J. Xu, H. Zheng, Z. Zeng, S. Wu, and M. Shen Discrete time-cost-environment trade-off problem for large-scale construction systems with s under fuzzy uncertainty and its application to Jinping-II hydroelectric project International Journal of Project Management 30 8 2012 950 966
    • (2012) International Journal of Project Management , vol.30 , Issue.8 , pp. 950-966
    • Xu, J.1    Zheng, H.2    Zeng, Z.3    Wu, S.4    Shen, M.5
  • 54
    • 84888334946 scopus 로고    scopus 로고
    • Stochastic time-cost tradeoff analysis: A distribution-free approach with focus on correlation and stochastic dominance
    • T. Yang Stochastic time-cost tradeoff analysis: A distribution-free approach with focus on correlation and stochastic dominance Automation in Construction 43 2011 1 11
    • (2011) Automation in Construction , vol.43 , pp. 1-11
    • Yang, T.1
  • 55
    • 0033897639 scopus 로고    scopus 로고
    • Finding the critical path in an activity network with time-switch constraints
    • DOI 10.1016/S0377-2217(98)00390-7
    • H. Yang, and Y. Chen Finding the critical path in an activity network with time-switch constraints European Journal of Operational Research 120 3 2000 603 613 (Pubitemid 30516820)
    • (2000) European Journal of Operational Research , vol.120 , Issue.3 , pp. 603-613
    • Yang, H.-H.1    Chen, Y.-L.2
  • 57
    • 78149282590 scopus 로고    scopus 로고
    • Fuzzy-multi-objective particle swarm optimization for time-cost-quality tradeoff in construction
    • H. Zhang, and F. Xing Fuzzy-multi-objective particle swarm optimization for time-cost-quality tradeoff in construction Automation in Construction 19 8 2010 1067 1075
    • (2010) Automation in Construction , vol.19 , Issue.8 , pp. 1067-1075
    • Zhang, H.1    Xing, F.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.