메뉴 건너뛰기




Volumn 199, Issue 1, 2012, Pages 361-372

A multicriteria decision model for assigning priority classes to activities in project management

Author keywords

Decision support; ELECTRE TRI; Multiple criteria sorting; Project management

Indexed keywords


EID: 84866121100     PISSN: 02545330     EISSN: 15729338     Source Type: Journal    
DOI: 10.1007/s10479-011-0853-z     Document Type: Article
Times cited : (26)

References (24)
  • 1
    • 24144481467 scopus 로고    scopus 로고
    • Multicriteria modeling of repair contract based on utility and ELECTRE I method with dependability and service quality criteria
    • Almeida, A. T. (2005). Multicriteria modeling of repair contract based on utility and ELECTRE I method with dependability and service quality criteria. Annals of Operations Research, Holanda, 138, 113-126.
    • (2005) Annals of Operations Research, Holanda , vol.138 , pp. 113-126
    • Almeida, A.T.1
  • 2
    • 34247645554 scopus 로고    scopus 로고
    • Multicriteria decision model for outsourcing contracts selection based on utility function and ELECTRE method
    • Almeida, A. T. (2007). Multicriteria decision model for outsourcing contracts selection based on utility function and ELECTRE method. Computers and Operations Research, 34(12), 3569-3574.
    • (2007) Computers and Operations Research , vol.34 , Issue.12 , pp. 3569-3574
    • Almeida, A.T.1
  • 3
    • 75149139330 scopus 로고    scopus 로고
    • Electre Tri-C: a multiple criteria sorting method based on characteristic reference actions
    • doi:10.1016/j.ejor.2009.10.018
    • Almeida-Dias, J., Figueira, J., & Roy, B. (2009). Electre Tri-C: a multiple criteria sorting method based on characteristic reference actions. European Journal of Operational Research. doi: 10. 1016/j. ejor. 2009. 10. 018.
    • (2009) European Journal of Operational Research
    • Almeida-Dias, J.1    Figueira, J.2    Roy, B.3
  • 5
    • 0000372281 scopus 로고
    • A preference ranking organization method, the PROMETHEE method for MCDM
    • Brans, J. P., & Vincke, P. H. (1985). A preference ranking organization method, the PROMETHEE method for MCDM. Management Science, 31, 647-656.
    • (1985) Management Science , vol.31 , pp. 647-656
    • Brans, J.P.1    Vincke, P.H.2
  • 6
    • 69749090825 scopus 로고    scopus 로고
    • A multicriteria model for risk sorting of natural gas pipelines based on ELECTRE TRI integrating utility theory
    • Brito, A. J., Almeida, A. T., & Mota, C. M. M. (2010). A multicriteria model for risk sorting of natural gas pipelines based on ELECTRE TRI integrating utility theory. European Journal of Operational Research, 200, 812-821.
    • (2010) European Journal of Operational Research , vol.200 , pp. 812-821
    • Brito, A.J.1    Almeida, A.T.2    Mota, C.M.M.3
  • 8
    • 0037117687 scopus 로고    scopus 로고
    • An aggregation/disaggregation approach to obtain robust conclusions with ELECTRE TRI
    • Dias, L. C., Mousseau, V., Figueira, J., & Clímaco, J. (2002). An aggregation/disaggregation approach to obtain robust conclusions with ELECTRE TRI. European Journal of Operational Research, 138(2), 332-348.
    • (2002) European Journal of Operational Research , vol.138 , Issue.2 , pp. 332-348
    • Dias, L.C.1    Mousseau, V.2    Figueira, J.3    Clímaco, J.4
  • 10
    • 59649100075 scopus 로고    scopus 로고
    • Overrun, overspent, overlooked
    • Greek, D., & Pullin, J. (1999). Overrun, overspent, overlooked. Professional Engineering, 12(3), 27-28.
    • (1999) Professional Engineering , vol.12 , Issue.3 , pp. 27-28
    • Greek, D.1    Pullin, J.2
  • 11
    • 0031153874 scopus 로고    scopus 로고
    • Project management in a long-term and global one-of-a-kind project
    • Hameri, A.-P. (1997). Project management in a long-term and global one-of-a-kind project. International Journal of Project Management, 15(3), 151-157.
    • (1997) International Journal of Project Management , vol.15 , Issue.3 , pp. 151-157
    • Hameri, A.-P.1
  • 12
    • 0041839992 scopus 로고    scopus 로고
    • IPMA, International Project Management Association, June
    • IPMA (2006). ICB-IPMA competence baseline. Version 3. 0. International Project Management Association, June.
    • (2006) ICB-IPMA competence baseline. Version 3. 0
  • 14
    • 0010014883 scopus 로고
    • Construction planning: revising the paradigm
    • Laufer, A., & Howell, G. (1993). Construction planning: revising the paradigm. Project Management Journal, 24(3), 23-33.
    • (1993) Project Management Journal , vol.24 , Issue.3 , pp. 23-33
    • Laufer, A.1    Howell, G.2
  • 16
    • 59649105935 scopus 로고    scopus 로고
    • A multiple criteria decision model for assigning priorities to activities in project management
    • Mota, C. M. M., Almeida, A. T., & Alencar, L. H. (2009). A multiple criteria decision model for assigning priorities to activities in project management. International Journal of Project Management, 27, 175-181.
    • (2009) International Journal of Project Management , vol.27 , pp. 175-181
    • Mota, C.M.M.1    Almeida, A.T.2    Alencar, L.H.3
  • 17
    • 0001102706 scopus 로고    scopus 로고
    • Inferring na ELECTRE TRI model from assignment examples
    • Mousseau, V., & Slowinski, R. (1998). Inferring na ELECTRE TRI model from assignment examples. Journal of Global Optimisation, 12, 157-174.
    • (1998) Journal of Global Optimisation , vol.12 , pp. 157-174
    • Mousseau, V.1    Slowinski, R.2
  • 21
    • 0036604809 scopus 로고    scopus 로고
    • Determining the weights of criteria in the ELECTRE type methods with a revised Simos' procedure
    • Roy, B., & Figueira, J. (2002). Determining the weights of criteria in the ELECTRE type methods with a revised Simos' procedure. European Journal of Operational Research, 139, 317-326.
    • (2002) European Journal of Operational Research , vol.139 , pp. 317-326
    • Roy, B.1    Figueira, J.2
  • 23
    • 34248402903 scopus 로고    scopus 로고
    • Causes and effects of delays in Malaysian construction industry
    • Sambasivan, M., & Wen Soon, I. (2006). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526.
    • (2006) International Journal of Project Management , vol.25 , Issue.5 , pp. 517-526
    • Sambasivan, M.1    Wen Soon, I.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.