메뉴 건너뛰기




Volumn , Issue , 2009, Pages 199-205

Applying neural network ensemble concepts for modelling project success

Author keywords

ANNs model; Preproject planning; Project success

Indexed keywords

BOOSTING ALGORITHM; DEPENDENT VARIABLES; INDEPENDENT VARIABLES; MODEL DEVELOPMENT; NEURAL NETWORK ENSEMBLES; NEURAL NETWORKS MODEL; PLANNING PROCESS; PROJECT SUCCESS;

EID: 84863749517     PISSN: None     EISSN: None     Source Type: Conference Proceeding    
DOI: None     Document Type: Conference Paper
Times cited : (12)

References (13)
  • 1
    • 0030211964 scopus 로고    scopus 로고
    • Bagging predictors
    • Breiman, L. (1996). "Bagging predictors." Machine Learning Journal, 24(2), 123-140
    • (1996) Machine Learning Journal , vol.24 , Issue.2 , pp. 123-140
    • Breiman, L.1
  • 3
    • 0343078823 scopus 로고
    • The Construction Industry Institute Special Publication 39-2, Austin, TX
    • The Construction Industry Institute (1995). "Pre-Peoject Planning Handbook". Special Publication 39-2, Austin, TX
    • (1995) Pre-peoject Planning Handbook
  • 4
    • 84863737951 scopus 로고    scopus 로고
    • Project definition rating index (PDRI) - Industrial projects
    • The Construction Industry Institute Austin, TX
    • The Construction Industry Institute (1996). "Project Definition Rating Index (PDRI) - Industrial Projects". Implementation Resource 113-2, Austin, TX
    • (1996) Implementation Resource 113-2
  • 5
    • 84889166884 scopus 로고    scopus 로고
    • Project definition rating index (PDRI) - Building projects
    • The Construction Industry Institute Austin, TX
    • The Construction Industry Institute (1999). "Project Definition Rating Index (PDRI) - Building Projects". Implementation Resource 155-2, Austin, TX
    • (1999) Implementation Resource 155-2
  • 6
    • 33745303744 scopus 로고    scopus 로고
    • Tender price estimation using artificial neural networks. II: Modelling
    • Elhag, T. M. S., and Boussabaine, A. H. (2002). "Tender price estimation using artificial neural networks. II: Modelling.". J. Finan. Mange. Property Constr. 7(1), 49-64.
    • (2002) J. Finan. Mange. Property Constr. , vol.7 , Issue.1 , pp. 49-64
    • Elhag, T.M.S.1    Boussabaine, A.H.2
  • 10
    • 0006933356 scopus 로고    scopus 로고
    • A report to the Construction Industry Institute, Research Report 113-11, Austin, TX
    • Gibson, G. E. and Dumont, P.R. (1996). "Project Definition Rating Index (PDRI)" A report to the Construction Industry Institute, Research Report 113-11, Austin, TX
    • (1996) Project Definition Rating Index (PDRI)
    • Gibson, G.E.1    Dumont, P.R.2
  • 12
    • 0028530453 scopus 로고
    • Managing capital projects: Where have we been - Where are we going?
    • October
    • Merrow, E. W., and Yarossi, M. E. (1994). "Managing Capital Projects: Where Have We been - Where are We Going?" Chemical Engineering, October: 108-111
    • (1994) Chemical Engineering , pp. 108-111
    • Merrow, E.W.1    Yarossi, M.E.2