Volumn 35, Issue 12, 2011, Pages 3044-3047

On electrical load tracking scheduling for a steel plant

Author keywords

Load tracking; Mixed integer linear programming; Steel plant

Indexed keywords

COMPUTATION TIME; CONTINUOUS TIME; CONTINUOUS TIME FORMULATIONS; ELECTRICAL LOAD; ELECTRICITY-CONSUMPTION; INTEGER LINEAR PROGRAMMING FORMULATION; LOAD TRACKING; MIXED INTEGER LINEAR PROGRAMMING; PERIODIC ENERGY; RELATIVE POSITIONS; STEEL MANUFACTURING; STEEL PLANT; TIME-PERIODS;

EID: 80053911225     PISSN: 00981354     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.compchemeng.2011.03.006     Document Type: Article
Times cited : (46)

References (11)
  • 1
    • 76449097098 scopus 로고    scopus 로고
    • Integrated production and utility system approach for optimizing industrial unit operations
    • Agha M., Thery R., Hetreux G., Haït A., Le Lann J.-M. Integrated production and utility system approach for optimizing industrial unit operations. Energy 2010, 35(2):611-627.
    • (2010) Energy , vol.35 , Issue.2 , pp. 611-627
    • Agha, M.1    Thery, R.2    Hetreux, G.3    Haït, A.4    Le Lann, J.-M.5
  • 2
    • 0005022772 scopus 로고
    • Hierarchical approach to steel production scheduling under a global energy constraint
    • Boukas E., Haurie A., Soumis F. Hierarchical approach to steel production scheduling under a global energy constraint. Annals of Operations Research 1990, 26(1-4):289-311.
    • (1990) Annals of Operations Research , vol.26 , Issue.1-4 , pp. 289-311
    • Boukas, E.1    Haurie, A.2    Soumis, F.3
  • 3
    • 67849109965 scopus 로고    scopus 로고
    • A new continuous-time scheduling formulation for continuous plants under variable electricity cost
    • Castro P., Harjunkoski I., Grossmann I. A new continuous-time scheduling formulation for continuous plants under variable electricity cost. Industrial & Engineering Chemistry Research 2009, 48(14):6701-6714.
    • (2009) Industrial & Engineering Chemistry Research , vol.48 , Issue.14 , pp. 6701-6714
    • Castro, P.1    Harjunkoski, I.2    Grossmann, I.3
  • 4
    • 0141749146 scopus 로고    scopus 로고
    • Total-site scheduling for better energy utilization
    • Cheung K.-Y., Hui C.-W. Total-site scheduling for better energy utilization. Journal of Cleaner Production 2004, 12:171-184.
    • (2004) Journal of Cleaner Production , vol.12 , pp. 171-184
    • Cheung, K.-Y.1    Hui, C.-W.2
  • 5
    • 34447103177 scopus 로고    scopus 로고
    • Reflexion on implementing industrial ecology through eco-industrial park development
    • Gibbs D., Deutz P. Reflexion on implementing industrial ecology through eco-industrial park development. Journal of Cleaner Production 2007, 15(17):1683-1695.
    • (2007) Journal of Cleaner Production , vol.15 , Issue.17 , pp. 1683-1695
    • Gibbs, D.1    Deutz, P.2
  • 8
    • 0035890549 scopus 로고    scopus 로고
    • A decomposition approach for the scheduling of a steel plant production
    • Harjunkoski I., Grossmann I. A decomposition approach for the scheduling of a steel plant production. Computers and Chemical Engineering 2001, 25:1647-1660.
    • (2001) Computers and Chemical Engineering , vol.25 , pp. 1647-1660
    • Harjunkoski, I.1    Grossmann, I.2
  • 9
    • 80053896098 scopus 로고    scopus 로고
    • Optimal control of switched-input and uncertain systems. Ph.D. thesis, ETH Zurich, Automatic Control Laboratory.
    • Nolde, K. (2008). Optimal control of switched-input and uncertain systems. Ph.D. thesis, ETH Zurich, Automatic Control Laboratory.
    • (2008)
    • Nolde, K.1
  • 10
    • 77956872862 scopus 로고    scopus 로고
    • Electrical load tracking scheduling of a steel plant
    • Nolde K., Morari M. Electrical load tracking scheduling of a steel plant. Computers and Chemical Engineering 2010, 34:1899-1903.
    • (2010) Computers and Chemical Engineering , vol.34 , pp. 1899-1903
    • Nolde, K.1    Morari, M.2
  • 11
    • 80053923521 scopus 로고
    • A zero-one programming approach to scheduling with limited resources. Tech. Rep. RM-5561-PR, RAND Corporation.
    • Pritsker, A., & Watters, L. (1968). A zero-one programming approach to scheduling with limited resources. Tech. Rep. RM-5561-PR, RAND Corporation.
    • (1968)
    • Pritsker, A.1    Watters, L.2