Volumn 21, Issue 3 PART 2, 2011, Pages 1786-1790
|
Production and quality assurance of main busbar interconnection splices during the LHC 2008-2009 shutdown
a
CERN
(Switzerland)
|
Author keywords
Busbars; Interconnections; Resistance measurement; Superconducting cables
|
Indexed keywords
ASSEMBLY PROCESS;
CONDUCTING STATE;
CRITICAL AREA;
ELECTRICAL CONTINUITY;
HEATING CYCLES;
INTERCONNECTIONS;
LARGE HADRON COLLIDER;
NON-DESTRUCTIVE TEST;
PRODUCTION PROCESS;
RESISTANCE MEASUREMENT;
ROOM TEMPERATURE RESISTANCE;
ULTRASONIC TEST;
VISUAL INSPECTION;
VISUALIZATION OF VOIDS;
BUSBARS;
CABLES;
ELECTRIC RESISTANCE MEASUREMENT;
GAMMA RADIOGRAPHY;
NONDESTRUCTIVE EXAMINATION;
QUALITY ASSURANCE;
QUALITY CONTROL;
RADIOLOGY;
SUPERCONDUCTIVITY;
ULTRASONIC TESTING;
VISUALIZATION;
SOLDERING;
|
EID: 79957913174
PISSN: 10518223
EISSN: None
Source Type: Journal
DOI: 10.1109/TASC.2010.2085072 Document Type: Article |
Times cited : (12)
|
References (10)
|